BTO · Transition - Stage 04 · Worked example Greystone FM Group · 3 packs · 14 contracts · 42 sites · Q2 2026 (Months 1-3) · £184,200 variation value recovered
BuiltAI
Built to Order™
Service Transition Plan
BTO-GFM-STP-001
← BTO Pack
Built to Order™ · Service Transition Plan Built AI Example Output · Redacted for illustration

Service Transition Plan

Structured handover from pilot to ongoing Built to Order™ managed delivery. Covers pilot outcomes, transition timeline, data setup, governance activation, first-month delivery plan and exit provisions.
Client
Greystone FM Group
Transition
Pilot → Managed Delivery
Pilot Period
3–28 March 2026
Go-Live
1 April 2026
Active Packs
3 (CCK · Cockpit · Dispatch)
Reference
BTO-GFM-STP-001
Scroll to begin
Section 01

Pilot Outcomes

Summary of the four-week pilot conducted in March 2026 across three workflow packs. All success criteria met — COO approval received 28 March 2026.

Pilot Result
All three packs met success criteria. COO approved transition to managed delivery.
During the four-week pilot, Built AI produced 47 outputs across Commercial Control Kit, Margin Cockpit and The Dispatch Desk. Quality score averaged 86% (against an 80% pilot target). No governance breaches, no data incidents. Client feedback scored 8.2/10. D. Farrow approved the transition on 28 March with a go-live date of 1 April 2026.
Pilot Outputs
47
Across 3 packs · 4 weeks
Quality Score
86%
Target: ≥ 80% (pilot)
Client Feedback
8.2
Out of 10 (survey)

Pilot success criteria — results

CriterionTargetActualStatus
Output quality (first-pass acceptance)≥ 80%86%Exceeded
Turnaround time≤ 3 days2.6 days avgMet
Governance complianceZero breaches0Met
Data handlingZero incidents0Met
Client feedback≥ 7/108.2/10Exceeded
COO approval to proceedYes/NoYes (28 Mar)Approved
Section 02

Transition Timeline

Five-phase transition from pilot close-out to steady-state managed delivery. Total transition window: 10 working days.

01
Days 1–2 · 25–26 March
Pilot close-out & approval
Compile pilot results. Present to D. Farrow. Receive go/no-go decision. Document lessons learned and template refinements from pilot. Archive pilot working files.
02
Days 3–4 · 27–28 March
Contracts & governance setup
Finalise service agreement. Confirm SLA targets. Issue Service Onboarding Pack. Set up governance calendar (weekly/monthly/quarterly). Confirm named contacts on both sides. Establish escalation matrix.
03
Days 5–6 · 29–30 March
Data & systems setup
Configure shared workspace with folder structure per pack. Set up secure data transfer channel. Test upload/download cycle with L. Osei. Configure processing templates from pilot-refined versions. Set up automated validation checks.
04
Day 7 · 31 March
Team briefing & dry run
Joint briefing with Greystone operational leads (K. Rhodes, T. Brennan). Walk through the weekly delivery cycle. Confirm Monday data upload process. Confirm Friday delivery summary format. Run a dry-run delivery cycle using pilot data to verify the full workflow.
05
Day 8 · 1 April 2026
Go-live
First live data upload received. Week 1 delivery cycle commences. Built AI Delivery Manager (S. Okoro) available for same-day queries. First Weekly Delivery Summary issued Friday 4 April by 14:00.
Section 03

Transition RACI

Responsibility assignment for each transition activity. R = Responsible, A = Accountable, C = Consulted, I = Informed.

ActivityJ. Whitmore
Built AI
S. Okoro
Built AI
D. Farrow
COO
K. Rhodes
Commercial
T. Brennan
FM Ops
L. Osei
IT
Pilot close-out reportRCAII
Service agreement sign-offRACC
Shared workspace setupCRIIA
Secure data channel configCRA
SLA targets confirmedRCACC
Team briefing & dry runRRIAAC
Go-live (Week 1)CRIAAC
Section 04

Data Readiness Checklist

Pre-go-live checklist confirming all data systems, access and processes are ready. All items must be completed before Week 1 commences.

Technical setup

  • Shared workspace created with pack-specific folder structure
  • Secure data transfer channel configured and tested
  • Upload validation script deployed (file-size, format, corruption check)
  • Built AI team access provisioned (S. Okoro, M. Patel, R. Chen)
  • Greystone team access provisioned (K. Rhodes, T. Brennan, L. Osei)
  • Test upload/download cycle completed successfully

Data & templates

  • CCK templates (variation narrative, change event log, notice tracker) — V2.0 from pilot
  • Cockpit templates (margin snapshot, WIP tracker, invoice blocker) — V1.0
  • Dispatch Desk templates (triage flow, ticket format, handover summary) — V1.0
  • Contract register loaded — 14 active contracts with key commercial terms
  • Site register loaded — 42 Harland Properties sites with SLA matrices
  • Historical data baseline established for KPI measurement

Governance

  • Service Onboarding Pack issued and acknowledged
  • SLA targets agreed and documented
  • Escalation matrix confirmed with named contacts
  • Governance calendar issued for Q2 2026
  • Data handling agreement signed
  • Weekly delivery cycle walkthrough completed with Greystone leads
Section 05

Month 1 Delivery Plan

Week-by-week plan for the first month of managed delivery. Designed to ramp volume gradually while validating the operating rhythm.

WeekFocusPlanned OutputsRisk
Week 1
1–4 Apr
Establish rhythm. First live data cycle. Validate upload → process → deliver → review loop.CCK: 4 items
Cockpit: 2 items
Dispatch: 8 items
Ramp-up
Week 2
7–11 Apr
Increase volume. Begin processing variation backlog. First dispatch morning handovers.CCK: 6 items
Cockpit: 2 items
Dispatch: 10 items
Ramp-up
Week 3
14–18 Apr
Steady-state target volume. Full weekly delivery cycle operating across all packs.CCK: 7 items
Cockpit: 3 items
Dispatch: 10 items
Stabilising
Week 4
21–25 Apr
Steady-state. Prepare Month 1 Governance Report. Collect KPI baseline data.CCK: 8 items
Cockpit: 3 items
Dispatch: 12 items
Steady state
5 MayMonth 1 Governance Review — first formal governance meetingMonthly Governance ReportPlanned
Ramp-up expectation. Weeks 1–2 are deliberately lower-volume to allow both teams to validate the operating rhythm. Quality and turnaround are prioritised over volume during ramp-up. Full steady-state volume is expected from Week 3.
Section 06

Success Criteria & Exit Provisions

How success is measured during the first 90 days of managed delivery, and the provisions for either party to exit the engagement.

90-day success criteria

CriterionTargetMeasured At
SLA compliance≥ 95% average across 90 daysQ2 QBR (30 June)
Quality score≥ 90% by Month 3Month 3 Governance Review
Client satisfaction≥ 7/10 survey scoreQ2 QBR survey
Governance complianceZero breachesContinuous
Data handlingZero incidentsContinuous
Measurable commercial impactEvidenced commercial recovery attributable to BTO outputsQ2 QBR

Continuation

If the 90-day criteria are met, the engagement continues on a rolling quarterly basis. Each quarter is reviewed at the QBR. Pack expansion, scope changes or fee adjustments are agreed at QBR level with COO approval. No automatic price escalation without 60 days' written notice.

Exit provisions

Either party may terminate with 30 days' written notice. On termination, Built AI will complete any in-progress deliverables, return all client data within 30 days, issue a certificate of data destruction, and provide a final governance summary. No penalty for early termination. Templates and outputs produced during the engagement remain the client's property.