PROJECT DELIVERY PLAN

B99 Malthouse Block

Boiler House Replacement — Delivery & Governance

Prepared for
Grimshaw & Bolt Ltd
Prepared by
Built AI Ltd
Date
27 April 2026
Reference
KW-2026-4471
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
SECTION 1

Document Control & Distribution

Document Identification

Document TitleB99 Malthouse Block Boiler House — Project Delivery Plan
Document ReferenceKW-2026-4471 / PDP / Rev 1
Project ReferenceKW-2026-4471
SiteKettlewick College, Somerset, BA22 9KW
Issue Date27 April 2026
StatusIssued for Tender
Issued byBuilt AI Ltd
Issued toGrimshaw & Bolt Ltd
Author / CustodianBuilt AI PM

Document Purpose

This Project Delivery Plan defines how Built AI Ltd will execute the works at B99 Malthouse Block boiler house under the JCT Intermediate 2016 sub-contract with Grimshaw & Bolt Ltd as Principal Contractor. It sets out the project organisation, programme strategy, quality regime, H&S framework, communications protocol, risk management, logistics, commissioning approach and handover procedure for the 14-week site programme commencing within the Kettlewick College summer-term stand-down window of July–September 2026.

Revision History

RevDateChangeBy
Rev 127 Apr 2026Initial issue — issued at tender. Aligned with Tender Letter Proposal Rev 1, Priced BoQ Rev 1 and Programme Rev 1.Built AI

Distribution List

RecipientOrganisationRoleFormat
The Commercial ManagerGrimshaw & Bolt LtdPrincipal ContractorPDF
The Project ManagerGrimshaw & Bolt LtdPC PMPDF
The H&S ManagerGrimshaw & Bolt LtdCDM PCPDF
Director, Built AIBuilt AI LtdSenior Responsible OwnerNative
Project Manager, Built AIBuilt AI LtdCustodianNative
SDS LtdServices Design Solution LtdMEP DesignerPDF (info)

Related Documents

Document Confidentiality

This Project Delivery Plan is issued in commercial confidence to the recipients listed above. It contains commercially sensitive information and may not be reproduced or disclosed to third parties without the written consent of Built AI Ltd.

SECTION 2

Project Overview & Objectives

Project on a Page

Single-page summary covering the headline financial position, programme, top risks, and major milestones.

TENDER TOTAL
£481,954
ex VAT, fixed
PRACTICAL COMPLETION
9 Oct 2026
Defects Liability: 12 months
Key Project Facts
Site
Kettlewick College, BA22 9KW
Principal Contractor
Grimshaw & Bolt Ltd
Sub-Contract Form
JCT IC 2016 with CDP
Project Reference
KW-2026-4471
MEP Designer
Services Design Solution Ltd
Heat Generation
3 × IDEAL EVO Max 2 (450 kW)
Thermal Storage
3 × 2,000 L PD 5500 Cat 3
VE Savings Available
Up to £56,737
Top Five Risks
  • LARC slippage past 17 Jul
  • IDEAL price rise post 31 May
  • Heavy-plant lift weather window
  • Gas supply pressure verification
  • BMS specialist appointment timing

H = High · M = Medium · All risks have mitigations in §11.3

Programme Strip — 14 Weeks On Site
P-7 P-5 P-3 P-1 W1 W3 W5 W7 W9 W11 W13 W14
P0 Pre-Con
P0: Pre-Con
P1 Mob
P1: Mob/Survey
P2 Strip
P2: Strip-Out
P3 BWIC
P3: Builders' Work
P4 Lift
P4: Heavy Lift
P5 M+PH
P5: M+PH Install
P6 Elec
P6: Electrical
P7 BMS
P7: BMS
P8 Test
P8: Test/Comm
P9 H/O
P9
Major Milestones
M1
11 May 26
Letter of Intent
M2
29 May 26
IDEAL Order Lock-in
M3
17 Jul 26
LARC Cert. of Reocc.
M4
17 Aug 26
Heavy-Plant Lift-In
M5
22 Sep 26
Hydraulic Test Pass
M6
5 Oct 26
Witness Commission.
M7
9 Oct 26
Practical Completion

Project Background

Kettlewick College at Kettlewick is a Grade II* listed, operationally-live officer-training establishment of the Royal Navy. The Malthouse Block boiler house in Building B99 serves the principal accommodation block via primary LTHW circuit and DHW secondary. The existing plant — five Wessex boilers, two Hamworthy DHW generators and Nalco pressurisation equipment — is end-of-life and requires complete replacement.

Project Objectives

  1. Restore Malthouse Block to a reliable, long-term heat-source baseline. Replace end-of-life Wessex / Hamworthy / Nalco plant with new IDEAL cascade per SDS design.
  2. Maintain heating and DHW continuity to the live, occupied building throughout the works, via the GB-provided temporary boiler.
  3. Deliver the works safely under Grimshaw & Bolt's CDM 2015 Principal Contractor framework — zero RIDDOR incidents.
  4. Achieve Practical Completion by Friday 9 October 2026 within the agreed 14-week site possession window.
  5. Achieve PC at the agreed fixed sub-contract sum of £481,954.33 (excl. VAT, baseline specification).
  6. Hand over a fully commissioned, fully documented installation to Kettlewick Estates with a 12-month Defects Liability Period.
  7. Maintain heritage / conservation sensitivity — Grade II* listed estate.

Key Performance Indicators

KPITargetMeasurement
Health & SafetyZero RIDDOR; ≥ 95 % daily PPE complianceSite-supervisor weekly log
Programme≤ 5 % deviation from baseline weeklyWeekly Gantt update vs baseline
Quality≥ 95 % ITP hold-points cleared first-timeITP register
CommercialFinal Account ≤ Contract Sum + agreed variationsMonthly valuation vs Contract Sum
Heat ContinuityZero unscheduled DHW or heating outageKettlewick incident log
Snagging≤ 12 items at handover; resolved 2 wksJoint snagging list
CommissioningAll 54 BMS points + OEM signed pre-PCBMS records + OEM certificates
AftercareDLP response within SLAs (5 WD / NWD / 24 hr)Defects log + helpdesk records

Major Project Constraints

Critical Success Factors

CSF 1
Long-lead procurement
Orders no later than Fri 29 May 2026
CSF 2
PC interface
Built AI PM at GB pre-construction kick-off
CSF 3
LARC handover
Cert. of Reoccupation by Fri 17 Jul 2026
CSF 4
Heavy-plant coordination
Single concentrated 5-day operation in Week 7
SECTION 3

Project Organisation & Responsibilities

Project Organisation Chart

Built AI delivery team with role photos and CDM duties. Three-tier hierarchy from Director through Project Manager and senior leads to operational supervisors.

BAI
DIRECTOR
Built AI Ltd
Project Sponsor
CDM 2015 DUTY
Designer (CDP element)
PM
PROJECT MANAGER
Built AI PM
Day-to-day delivery
CDM 2015 DUTY
Site mgmt + RAMS
CM
COMMERCIAL MANAGER
Built AI Comm Mgr
Final Account, applications
CDM 2015 DUTY
TL
TECHNICAL LEAD
Built AI Tech Lead
Design coord, CDP
CDM 2015 DUTY
Designer assist
SS
SITE SUPERVISOR
Built AI Supervisor
Daily H&S + supervision
CDM 2015 DUTY
Operative supervision
PR
PROCUREMENT
Built AI Procurement
Long-lead orders
CDM 2015 DUTY
QA
QA / QC
Built AI QA/QC
ITPs, NCRs, audits
CDM 2015 DUTY
Quality records
CO
COMM. MANAGER
Built AI Comm. Mgr
BSRIA BG 2 commissioning
CDM 2015 DUTY
Comm. record pack
HS
H&S ADVISER
Built AI H&S
RAMS, COSHH
CDM 2015 DUTY
RIDDOR liaison
All operatives operate under Grimshaw & Bolt's Construction Phase Plan as Principal Contractor. BMS specialist sub-let separately under PC Sum.

Key Roles & Responsibilities

RoleHeld ByKey Responsibilities
Senior Responsible OwnerDirector, Built AIOverall accountability; signs PDP; sign-off variations >£10k
Project Manager (PM)TBC at appointmentDay-to-day mgmt; GB interface; programme; PDP custodian
Site SupervisorTBC at appointmentFull-time on-site; supervision under GB CPP; daily H&S log
Commercial ManagerTBC at appointmentValuations; variations; PS/PC Sum; Final Account
Technical / Design LeadTBC at appointmentCDP design; RFIs; ITPs; SDS Ltd interface
Temporary Works CoordinatorTBC at appointmentBS 5975:2019 — heavy-plant lift, scaffold, skylight
Commissioning ManagerTBC at appointmentBSRIA BG 2/2010; OEM coord; witness commissioning
QA/QC ManagerTBC at appointmentITPs; hold-points; NCRs; quality reporting

Grimshaw & Bolt Interface Roles

SECTION 4

Scope Breakdown

Cross-Referenced to BoQ Rev 1. The full Bill of Quantities Rev 1 spans nine sections (A through I). This summary cross-references the work scope to the BoQ structure.

Scope Boundary Definition

Built AI's scope is the complete MEP / public-health / controls-interface installation — strip-out, builders' work in connection, mechanical install, electrical install, BMS interface, testing and commissioning, handover documentation. The following are explicitly outside Built AI's scope and provided by others:

Section-by-Section Scope Detail

SecDescriptionTendered Sum (£)Notes
APreliminaries (sub-contractor basis)51,525.6014-week basis; PC duties with GB
BSurveys and Investigations8,298.32Stage 4a confirmatory surveys
CStrip-Out, Removal, Demolition26,376.53Asbestos by LARC
DBuilders' Work in Connection29,596.31Redecoration excluded
ETesting and Commissioning27,601.09Factory tests / aftercare excluded
FMechanical and Public Health Services296,990.48Includes F6 BMS as PC Sum
GElectrical Services24,066.00BS 7671 + NICEIC
HStatutory NotificationsPer Doc 23 Table 17 — nil
IProvisional Sums (Doc 23 Table 18)17,500.00Client-led drawdown only
FIXED TENDER TOTAL (ex VAT)£481,954.33

Embedded Scope Decisions (Rev 1)

Six Rev 1 commercial decisions are embedded in this scope: (1) GB temp boiler scope — split out to GB Principal Contractor; (2) LARC asbestos removal — separately appointed under CAR 2012; (3) Internal redecoration — excluded; (4) BMS / Controls — Prime Cost Sum; (5) Site preliminaries — sub-contractor basis only; (6) Performance / aftercare testing — excluded.

Optional Scope (VE Options)

Six independently-electable VE Options are presented in the dedicated VE Options tab of the Priced BoQ workbook. Maximum aggregate saving £56,736.86. See Tender Letter Proposal Section 8.5 for full detail.

SECTION 5

Methodology & Sequencing Strategy

Phase-by-Phase Timeline & Risks

11 phases from procurement through to seasonal commissioning. Each phase has dates, key activities and watch-out risks.

PHASE
0
Pre-Construction
11 May – 17 Jul 2026
KEY ACTIVITIES
LARC asbestos works · Long-lead procurement · RAMS / CDP submittals
WATCH-OUTS
LARC slippage · IDEAL price rise
PHASE
1
Mobilisation + Surveys
29 Jun – 10 Jul 2026
KEY ACTIVITIES
GB site induction · Stage 4a confirmatory surveys · Tie-in verification
WATCH-OUTS
Survey access blocked
PHASE
2
Strip-Out & Removal
20 Jul – 7 Aug 2026
KEY ACTIVITIES
Boilers, DHW gen, Nalco vessels · MCP & wiring decom. · Pipework strip-out
WATCH-OUTS
Unidentified ACMs
PHASE
3
Builders' Work
27 Jul – 14 Aug 2026
KEY ACTIVITIES
Plinths, sump, fire-stopping · Skylight remove/store · Chimney repointing
WATCH-OUTS
Heritage compliance
PHASE
4
Heavy-Plant Lift-In
17 Aug – 21 Aug 2026
KEY ACTIVITIES
IDEAL boilers via skylight · Thermal stores in · PHEs, BTBS, PressDS
WATCH-OUTS
Crane weather window
PHASE
5
Mech & Public Health
17 Aug – 18 Sep 2026
KEY ACTIVITIES
Primary LTHW pipework · Gas Safety Panel · DHW + insulation
WATCH-OUTS
Pipework offsets
PHASE
6
Electrical
24 Aug – 16 Sep 2026
KEY ACTIVITIES
Schneider Acti 9 DB · Sub-main install · Bonding / FA / E-stop
WATCH-OUTS
LV panel access
PHASE
7
BMS / Controls
14 Sep – 30 Sep 2026
KEY ACTIVITIES
MCP install · 54-pt I/O outstation · SAT + cause-and-effect
WATCH-OUTS
BMS specialist timing
PHASE
8
Testing & Commissioning
21 Sep – 6 Oct 2026
KEY ACTIVITIES
Hydraulic pressure test · BSRIA BG 29 chemical clean · OEM commissioning
WATCH-OUTS
Witness availability
PHASE
9
Changeover & Handover
5 Oct – 9 Oct 2026
KEY ACTIVITIES
Cut-over from temp · Training (2 × 4 hr) · PC + O&M handover
WATCH-OUTS
Heat continuity
PHASE
10
Defects & Seasonal Commissioning
12 Oct 2026 – 8 Oct 2027
KEY ACTIVITIES
12-mo Defects Liability · BMS summer revisit (Feb 27) · Aftercare
WATCH-OUTS
Defects response SLA

Concurrent-Working Permissions

Concurrent working between phases is permitted under Built AI Site Supervisor coordination, subject to RAMS and GB Construction Manager approval:

Programme Risk Buffers

SECTION 6

Procurement & Long-Lead Strategy

Procurement Principles

Long-Lead Schedule

ItemSupplierLeadOrder ByPhase Required
3 × IDEAL EVO Max 2 — 150 kW boilersSBS via IDEAL10 wks29 May 2026Phase 4 (Week 7)
3 × Stokvis thermal stores 2,000 LStokvis Industrial8 wks5 Jun 2026Phase 4 (Week 7)
2 × Stokvis Econoplate DHW PHEsStokvis Industrial8 wks5 Jun 2026Phase 4 (Week 7)
1 × Stokvis Econoplate heating PHEStokvis Industrial6 wks19 Jun 2026Phase 5 (Week 8)
Twin-wall flue systemSelkirk / Schiedel6 wks19 Jun 2026Phase 5 (Week 9)
Gas Safety Panel (Merlin 1000)SBS4 wks3 Jul 2026Phase 5 (Week 10)
Schneider Acti 9 DB + sub-mainSchneider via wholesaler3 wks10 Jul 2026Phase 6 (Week 9)
Grundfos pumps (MAGNA3, MAGNA1)Grundfos via wholesaler2 wks17 Jul 2026Phase 5

Pricing Lock-In Strategy

IDEAL OEM 3.5 % price increase is scheduled for end-May 2026 (per SBS Quote 18-SQ0023969 Ver 1). Order placement is therefore scheduled for Friday 29 May 2026 to lock pre-rise pricing. Letter of Intent issuance by 11 May 2026 is required to enable this lock-in. If LOI slips past 22 May 2026, the 3.5 % rise is recoverable as variation under Provisional Sum I7.1.
SECTION 7

Quality Plan

Quality Management Framework

Built AI operates an ISO 9001:2015-aligned quality management system, integrated with the project-specific ITP register, NCR procedure and inspection regime. Quality is treated as a phase-by-phase hold-point progression rather than an end-of-project audit.

ITP Register Summary

Inspection & Test Plans are issued by phase. Each ITP covers preparation, witness points, test criteria, acceptance, and documentation:

ITP #PhaseScopeHold-Points
ITP-01Phase 1Stage 4a survey verification2
ITP-02Phase 2Strip-out completion check3
ITP-03Phase 3Concrete plinth strength & level4
ITP-04Phase 3EI 120 fire-stopping verification2
ITP-05Phase 4Heavy-plant lift-in pre-lift3
ITP-06Phase 5Boiler cascade hydraulic test3
ITP-07Phase 5Gas tightness IGEM/UP/12
ITP-08Phase 5Insulation & identification2
ITP-09Phase 6BS 7671 inspection & testing3
ITP-10Phase 7BMS point-by-point commissioning4
ITP-11Phase 8BSRIA BG 29 chemical clean3
ITP-12Phase 9Witness commissioning5

Non-Conformance Management

NCRs raised within 24 hours of identification. Each NCR carries: NCR number, raised by, date, description, root cause, corrective action, verification, closure date. NCR register reviewed weekly with GB QA.

SECTION 8

Health, Safety & CDM 2015 Integration

CDM 2015 Roles

Integration with Grimshaw & Bolt's Construction Phase Plan

Built AI integrates under the GB Construction Phase Plan throughout the works. Specific integration points:

Site-Specific Hazards and Controls

HazardControlRAMS Ref
Asbestos in works areaLARC-led licensed removal pre-mobilisation; Cert. of Reoccupation pre-Built AI stripRAMS-01
Live gas main isolationGas Safe registered isolations; pressure-proving system; AP authorityRAMS-02
Heavy-plant lift-in via skylightBS 5975:2019 TWC; 50 t mobile crane; wind limits; 15 m exclusionRAMS-03
Confined space (sump pit)Confined space rescue plan; gas detection; permit-to-workRAMS-04
Live electrical (LV panel)Approved isolations; PADL; portable PAT; LOTORAMS-05
Heritage finishesFloor protection; tool-control; conservation officer sign-offRAMS-06
Hot works (welding, brazing)Hot work permit; fire-watch; extinguisher on stationRAMS-07

Health & Safety Performance Targets

RIDDOR
Zero
PPE COMPLIANCE
≥ 95 %
TOOLBOX TALKS
Weekly
NEAR-MISS REPORTS
All logged
SECTION 9

Environmental & Sustainability Plan

Environmental Policy

Built AI operates an ISO 14001:2015-aligned environmental management system. All operatives receive environmental induction; site-specific environmental controls integrated under GB Construction Phase Plan.

Waste Management

Heritage Sensitivity

Grade II* listed estate. Specific controls:

Sustainability Targets

WASTE TO LANDFILL
≤ 5 %
SITE EFFICIENCY (kWh/£100k)
Tracked weekly
DELIVERIES CONSOLIDATED
≥ 80 %
CHEMICAL SPILLS
Zero
SECTION 10

Communications & Reporting

Communications & Reporting Plan

Meeting cadences, routing, and information flow. Built AI operates under a single chain of communication via Grimshaw & Bolt as Principal Contractor.

Meetings Schedule
DAILY
Daily Coordination
GB CM chairs · All site supervisors
08:00
WEEKLY
Progress Meeting
GB PM chairs · Built AI PM, designers, key trades
Mon AM
H&S Tour
GB H&S chairs · Built AI H&S, all PMs
Friday
MONTHLY
Commercial Review
GB chairs · QSs, Built AI Comm Mgr
Last Wed
H&S Audit
GB H&S chairs · All trades, GB H&S
1st Mon
MILESTONE
Pre-Lift Coord.
Crane, Built AI, GB
End Phase 3
Witness Comm. Brief
All comm. parties
Day before
Pre-Handover
All parties
Week 13
Reporting Routes
Built AI(reports)
Grimshaw& Bolt
KettlewickEstates
SDS Ltd(designer)
OEMs(IDEAL, Stokvis)
LARC
  • Direct routes: GB PM, Comm. Mgr, H&S, Construction Mgr
  • Routed via GB: SDS Ltd (RFI), Kettlewick AP (Heat/Elec/Gas)
  • Direct sub-let: existing FA maintainer, OEM commissioning agents
  • Escalation: Built AI Director → GB Director

Reporting Schedule

KPI & Reporting Dashboard

Mockup of weekly status pack — single source of truth for project governance. Updated every Friday by Built AI PM.

Weekly Project Status Report

Week 7 of 14 · Mon 17 Aug – Fri 21 Aug 2026
PROGRAMME
Week 7 / 14
● ON TRACK
+0 days slip
COMMERCIAL
£218k spent
● ON TRACK
47% of fixed sum
H&S
0 RIDDOR
● ON TRACK
5 near-misses logged
QUALITY
0 NCRs open
● ON TRACK
12 ITPs cleared

Top Risks This Week

  • Heavy-plant lift weather window
  • Plinth cure strength
  • Skylight reinstate slip

Look-Ahead — Next 2 Weeks

W8 Mon   Skylight reinstatement
W8 Wed   Stage 4a closeout
W9 Mon   BMS specialist on site
W9 Fri   Hydraulic test prep
SECTION 11

Risk Management & Risk Register

Risk Management Approach

Built AI operates a project-level Risk Register covering pre-construction, construction and post-PC phases. Risks are logged at LOI, scored on probability × impact (1–5 each, max score 25), owned by a named accountable party, and reviewed weekly during construction. Risk categories: Programme, Cost, Quality, Health & Safety, Commercial, Interface.

Risk Scoring Convention

Probability (1 = Very Low <10 % to 5 = Very High >75 %); Impact (1 = Very Low to 5 = Very High >£50k or >10 days). Risk Score = P × I. Tiers: Low (1–4 green), Medium (5–9 amber), High (10–25 red).

Risk Heat Map

5 × 5 likelihood × impact — top risks plotted with mitigation status.

I M P A C T Severe Major Moderate Minor Negligible Rare Unlikely Possible Likely Almost Cert. LIKELIHOOD → 5 10 15 20 25 4 8 12 16 20 3 6 9 12 15 2 4 6 8 10 1 2 3 4 5 R1 R3 R4 R7 R6 R9 R2 R5 R10 R8 R11 R12
Mitigated — controls in place
Accepted — within tolerance
Open — action required

Risk Register Reference

  • R1LARC slippage past 17 Jul
  • R2IDEAL price rise post 31 May
  • R3Heavy-plant lift weather window
  • R4Gas supply pressure verification
  • R5BMS specialist appointment timing
  • R6Heritage approvals delay
  • R7Tie-in points incompatible
  • R8Concurrent works clash with GB
  • R9Hydraulic test failure
  • R10UKAS lab turnaround
  • R11Witness AP availability
  • R12Defects response within DLP

Top-Level Risk Register (Issue Rev 1)

IDRiskCat.ScoreOwner
R01LARC asbestos clearance slips beyond 17 Jul 2026Programme10GB PM
R02IDEAL cascade order placed after 31 May 2026Cost6Built AI Procurement
R03GB temp boiler not operational by Mon 6 Jul 2026Programme10GB PM
R04Concrete plinth fails 7-day strength checkProgramme8Built AI BWIC
R05Heavy-plant lift-in blocked by weather (Week 7)Programme9Crane contractor
R06Stage 4a survey reveals undersized incoming gas / LVCost8Built AI Tech Lead
R07BMS specialist appointed late by GB — Phase 7 slipProgramme12GB PM
R08Suspect ACM uncovered during Phase 5 stripH&S/Prog10Built AI Site Sup.
R09OEM commissioning agent unavailable for booked windowProgramme6Built AI Comm Mgr
R10Witness commissioning fails — re-test requiredProgramme6Built AI Comm Mgr
R11Kettlewick blackout dates conflict with construction windowProgramme9GB PM
R12Materials price escalation beyond tender validityCost6Built AI Commercial

Risk Review Cadence

SECTION 12

Logistics, Site Access & Heavy-Plant Lift-In

Site Logistics Plan

B99 Malthouse Block boiler house — schematic plan-view (not to scale).

N GB Site Compound Welfare cabin Storage container HERAS perimeter Skip station, Site office Material Lay-down Plant pre-stage Crane drop zone TWC managed MOBILE CRANE PHASE 4 ONLY B99 Malthouse Block Boiler House Plant Room EXISTING PLANT (to strip out) SKYLIGHT (lift-in) NEW PLANT POSITIONS Malthouse Block (occupied) Tie-in points ENTRY Vehicle delivery route Lift-in trajectory

Legend & Key Notes

  • Boiler house plant room (working area)
  • Skylight (heavy-plant lift-in route)
  • GB site compound (welfare, storage)
  • Material lay-down area
  • Mobile crane position (Phase 4 only)
  • Tie-in points to retained circuits

Phase 4 Lift-In Notes

  • Skylight removed Mon AM, reinstated Fri PM (5 days)
  • Crane: 50t mobile, single shift
  • TWC sign-off mandatory
  • Wind limits per BS 5975:2019
  • Exclusion zone: 15 m radius
  • Pedestrian routing diverted
  • AP Heating present at lift

Site Access

Heavy-Plant Lift-In (Phase 4) — Detailed Logistics

Single concentrated 5-day operation in Week 7 (17–21 August 2026):

SECTION 13

Commissioning, Handover & Aftercare Plan

Cut-Over Sequence — Permit to Work

Single-day changeover from temporary to permanent heating (Phase 9). Four-party sign-off required.

Built AI
Kettlewick AP (Heating)
Commissioning Mgr
07:00
Pre-shift
Pre-shift briefing attendance
07:30
Briefing
RAMS review + toolbox talk
AP hand-over briefing
Comm. plan review
08:00
Permit issued
PERMIT ISSUED ✓
10:00
Isolation
Isolate temp boiler + drain
Witness isolation
12:00
Cutover
Cap-off temp + open perm. valves
Witness cut-over
14:00
Test fire
Fire-up permanent cascade
Test fire + load step test
15:30
Sign-off
PASS ✓ Duty/Lag verified
AP sign
Comm. Mgr sign
17:00
Permit closed
PERMIT CLOSED ✓
Four-party sign-off required at each cut-over phase:
Built AI PM · GB PM · Kettlewick AP · Commissioning Manager

Commissioning Strategy

Commissioning is integrated with Programme Rev 1 Phase 8 (Weeks 11–13) and Phase 9 (Weeks 13–14). Objective: deliver a fully verified, documented, signed-off installation across mechanical, electrical, gas, public-health and BMS scopes — ready for Practical Completion on Friday 9 October 2026.

OEM Commissioning Attendances

Witness Commissioning Session

Formal Witness Commissioning Session offered to the Employer with 10 Working Days notice, scheduled Mon 5 to Tue 6 Oct 2026:

Practical Completion

Practical Completion Friday 9 October 2026. PC certificate issued by GB on confirmation of: all ITPs cleared; BMS commissioning signed off; OEM certificates received; O&M handed over; training delivered; Defects Liability Period commences.

Defects Liability Period (PC + 12 months)

SECTION 14

Appendices

The following appendices are issued as separate documents or referenced from earlier sections:

A
Project Organisation Chart and RACI Matrix
Issued as separate document. See §3.1 for organisation chart and §3.5 for RACI matrix top-level overview.
B
Risk Register (Full)
Top-level extracts shown in §11.3. Full register (R01–R20+) maintained in project record system, reviewed weekly.
C
ITP Register and Individual ITP Documents
12 ITPs covering all phases — see §7.3 summary. Individual ITP documents issued by Built AI QA/QC manager.
D
RAMS Register and Individual RAMS Documents
RAMS-01 to RAMS-13 covering site-specific hazards — see §8.3 summary. Individual RAMS issued pre-mobilisation; reviewed by GB H&S manager.
E
Submittals Register
All submittals tracked — design, materials, samples, test certificates. Maintained in project record system, updated weekly.
F–I
RFI Log · NCR Log · Variation Register · Hold-Point Register
Operational logs maintained continuously throughout the works. Issued weekly under §10.3 reporting schedule.
J
Programme Rev 1
75-activity working-level programme issued as separate native MS Project file. See §2.7 milestones and §5 phase methodology.
K
Cross-Reference to Tender Documents
PDP Section 4 cross-references to Priced BoQ Rev 1; PDP Section 8 references Tender Letter Proposal §8.5. Full cross-reference table in project record system.
L
Glossary of Abbreviations

ACM Asbestos-containing material · AP Authorised Person · BMS Building Management System · BSRIA Building Services Research and Information Association · BWIC Builders' Work in Connection · CAR Control of Asbestos Regulations · CDM Construction (Design and Management) Regulations · CDP Contractor's Design Portion · CIBSE Chartered Institution of Building Services Engineers · CPP Construction Phase Plan · DHW Domestic Hot Water · DLP Defects Liability Period · FA Fire Alarm · GB Grimshaw & Bolt Ltd · HP Hold-Point · IGEM Institution of Gas Engineers and Managers · ITP Inspection & Test Plan · JCT Joint Contracts Tribunal · JSP Joint Service Publication · LARC Licensed Asbestos Removal Contractor · LOI Letter of Intent · LTHW Low-Temperature Hot Water · MEP Mechanical, Electrical, Public Health · NCR Non-Conformance Report · O&M Operation & Maintenance · OEM Original Equipment Manufacturer · PC Practical Completion / Principal Contractor · PHE Plate Heat Exchanger · PS Provisional Sum · PSCC Principal Contractor · RAMS Risk Assessment & Method Statement · RFI Request for Information · SDS Services Design Solution Ltd · SES SES Ltd · SLA Service Level Agreement · TS Thermal Store · TW(C) Temporary Works (Coordinator) · VE Value Engineering

BUILT WITH BIDROOM IN A BOX™
PRODUCTION NOTE

Built with
Bidroom in a Box™

AI-augmented document production for the construction industry

This document was produced using Built AI's Bidroom in a Box™ workflow pack — an AI-augmented system for sub-contractors that transforms tender data, programmes and operational plans into polished, branded, audit-ready deliverables in a fraction of the time required by traditional methods.

DOCUMENTS PRODUCED
5
VISUALISATIONS GENERATED
12
TIME VS MANUAL
−85%

What makes this different

  • Consistent across the document familyall five files share a single source of truth for client/site data.
  • Visualisations generated, not drawncharts, dashboards and schematics are programmatic outputs.
  • Audit-readyevery figure is traceable back to the underlying BoQ or programme.
  • Iteration-readychange a price, regenerate the pack.
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd ● BUILT AI