The Bid Room
Bidroom in a Box™Pack 01 / 06 · Client deliverable
Project Delivery Plan · how we deliver

How B99 Malthouse Block gets built

The delivery plan submitted alongside the tender: the project on a page, the objectives and measures, the organisation and CDM duties, the phased method, and the risk position. It shows how the priced scope is turned into a safe, sequenced, quality-assured installation under the Principal Contractor's construction phase plan.

Prepared for
Grimshaw & Bolt Ltd
Site
Kettlewick College, BA22 9KW
Reference
ITT KW-2026-4471
MEP designer
Services Design Solution Ltd
Prepared by
BuiltAI Intelligence Ltd
Revision
Rev 1

Illustrative example: fictional project and parties.

£481,954.33Fixed sub-contract sum
14 weeksOn-site, 6 Jul to 9 Oct 2026
9 Oct 2026Practical Completion
12Inspection and test plans
BuiltAI Intelligence Ltd · built-ai.ioB99-PDP · Rev 1
01On a page

The project on a page

Kettlewick College is a Grade II* listed, operationally live Royal Navy training establishment. The Malthouse Block boiler house serves the principal accommodation via a primary heating circuit and hot-water secondary. The existing plant is end-of-life and is replaced in full, with continuity held throughout by the Principal Contractor's temporary boiler.

Key factPosition
Fixed sub-contract sum£481,954.33, excl. VAT, baseline
Programme14 weeks on-site, 6 July to 9 October 2026
Practical Completion9 October 2026, DLP 12 months
Principal ContractorGrimshaw & Bolt Ltd, CDM 2015
Heat generationThree IDEAL EVO Max 2 boilers, 450 kW cascade
VE savings availableUp to £56,736.86 across six options
02Measures

Objectives and performance measures

The plan targets a safe, continuity-preserving delivery to the fixed sum and the agreed completion date, on a heritage-sensitive live site. Progress is measured weekly against the baseline below, each with a defined source of evidence.

MeasureTargetEvidence
Health and safetyZero RIDDOR; PPE compliance 95% or aboveWeekly supervisor log
ProgrammeWithin 5% of the weekly baselineWeekly Gantt update
Quality95% of hold-points cleared first timeITP register
CommercialFinal Account within sum plus agreed variationsMonthly valuation
Heat continuityZero unscheduled heating or DHW outageEstate incident log
CommissioningAll 54 BMS points and OEM sign-offs before PCCommissioning records
Snagging12 or fewer items at handoverJoint snagging list
03Team

Organisation and CDM duties

BuiltAI fields a defined delivery team, all operating under the Principal Contractor's construction phase plan. The company acts as designer for the Contractor's Design Portion only. The BMS specialist is appointed separately under the Prime Cost Sum at the Principal Contractor's instruction.

RoleResponsibilityCDM duty
DirectorProject sponsor, accountability, variation sign-offDesigner, CDP
Project ManagerDelivery, PC interface, programme, plan custodianSite management
Commercial ManagerValuations, variations, PS and PC Sum, Final Accountnil
Technical LeadCDP design, RFIs, ITPs, designer interfaceDesigner assist
Site SupervisorFull-time supervision, daily H&SOperative supervision
QA/QC and CommissioningITPs, hold-points, BSRIA commissioning managementQuality records
H&S AdviserRAMS, COSHH, RIDDOR liaisonH&S co-ordination

Interface with Grimshaw & Bolt runs through their PM, site manager, commercial manager, H&S manager and the asbestos coordinator who issues the Certificate of Reoccupation.

04Method

Phased method and risk

The works run in ten phases within the on-site window. Heavy plant lifts in through the skylight in a single concentrated operation in Phase 4. Risk is held in a register of 18 items on a five-by-five likelihood and impact matrix; the leading five are shown.

PhaseFocusWindow
P0 to P1Pre-construction, mobilisation, Stage 4a surveysJun to 10 Jul
P2 to P3Strip-out and builders' work20 Jul to 14 Aug
P4Heavy-plant lift-in through the skylight17 to 21 Aug
P5 to P6Mechanical, public health and electrical17 Aug to 18 Sep
P7 to P8BMS install and testing and commissioning14 Sep to 6 Oct
P9 to P10Changeover, handover, then 12-month DLPfrom 5 Oct
Leading risks

Certificate of Reoccupation slipping past 17 July; OEM price validity on the long-lead order; the weather window for the single-day heavy lift; the BMS specialist appointment timing under the PC Sum; and gas-supply verification, now closed by the metered pressure check. Each carries a named mitigation in the register.

Reference B99-PDP · Rev 1Completion 9 October 2026Risks 18 on the register