Bidroom · Roll Call™ - Stage 02 · Worked example B99 Malthouse Block · Grimshaw & Bolt · ITT KW-2026-4471 · £481,954.33
← Bidroom Pack
ILLUSTRATIVE
BIDROOM IN A BOX™ STAGE 02 · TRACEABILITY

Roll Call

Requirements Traceability Matrix
Every requirement called out by name, source-mapped, owner-tagged and accounted for. Nothing missed, nothing assumed.
Project
B99 Malthouse Block Boiler House Replacement
Tender source
Grimshaw & Bolt Ltd ITT (KW-2026-4471)
Roll Call opened
2 April 2026
Last updated
6 April 2026 — closed for review
Reference
RC-2026-117
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
BIDROOM WORKFLOW 1Front Desk
2Roll Call
3Question Time 4Cost Stack 5Last Look CLIENT DELIVERABLES CSSummary TLPTender Letter PDPDelivery Plan BoQPriced BoQ PRGProgramme
COVERAGE AT A GLANCE

Roll Call Status

The 78 requirements extracted from the tender pack, mapped to source documents and owners. Every line accounted for: 90% addressed in the Built AI pack; 9% raised as RFIs to Grimshaw & Bolt and routed to Question Time™; 1% pending QA confirmation.

REQUIREMENTS LOGGED
78
across 7 source documents
SOURCE-MAPPED
100%
every requirement traceable
RESPONDED
70 / 78
90% addressed in pack
RFIs RAISED
7
→ Question Time™ Stage 03
PENDING
1
file size to confirm at QA
WHERE REQUIREMENTS COME FROM

Source Document Breakdown

Distribution of the 78 requirements across the 7 source documents in the tender pack. The G&B ITT and SDS Doc 23 are the primary sources, with British Standards / CIBSE / BSRIA references providing the technical-compliance baseline.

Requirements per source — coloured by status

ITT G&B ITT
38
SDS SDS Doc 23
23
BSI BSI/CIBSE
8
JCT JCT IC
3
SOC SOCOTEC
2
SBS SBS Q18
2
JSP JSP
2
Responded in pack RFI raised Pending

Source × Category coverage

Cell intensity reflects requirement count. Highlights where the bulk of the technical content sits (SDS × Technical) and where statutory references span sources.

COM
PRG
TEC
QAC
HSC
STA
SIT
SUB
Σ
ITT
6
8
1
8
6
·
3
6
38
SDS
·
·
23
·
·
·
·
·
23
BSI
·
·
·
2
·
6
·
·
8
JCT
3
·
·
·
·
·
·
·
3
SOC
·
·
·
·
·
·
2
·
2
SBS
1
·
1
·
·
·
·
·
2
JSP
·
·
·
·
2
·
·
·
2
Σ
10
8
25
10
8
6
5
6
78
Lower count
Higher count
THE MATRIX

Full Requirements Register

78 requirements grouped into 8 categories. Each entry maps a tender clause to the Built AI pack response location, owner, and current status. Click any category to expand. Commercial, Programme and Technical are open by default.

RESPONDED Addressed in pack
RFI Question raised — see Question Time™
PENDING To confirm at Last Look
COM
Commercial
10 requirements · 9 responded · 1 RFI
9 ✓ 1 RFI
ID Source · Ref Requirement Owner Response Location Status
COM-01
ITT
§2.1 p3
Contract form: JCT Intermediate Building Contract 2016 with Contractor's Design Portion Commercial Mgr TLP §8.2 + §8.7 §B RESPONDED
COM-02
ITT
§2.4 p4
Tender validity period: minimum 90 Working Days from submission Commercial Mgr TLP §8.7 §B RESPONDED
COM-03
JCT
cl. 4.6
Retention: 3% of contract sum (moiety at PC, balance at end of DLP) Commercial Mgr TLP §8.7 §B RESPONDED
COM-04
JCT
cl. 4.9
Payment terms: monthly interim valuations; payment within 21 days Commercial Mgr TLP §8.7 §B RESPONDED
COM-05
ITT
§2.6 p5
Insurances: CAR; EL £10m; PL £10m; PI £5m on CDP element Commercial Mgr TLP §8.5 A5.3 + §8.7 §B RESPONDED
COM-06
ITT
§2.7 p5
Performance Bond and/or Parent Company Guarantee — quote separately Commercial Mgr TLP §8.7 §B RESPONDED
COM-07
ITT
§2.8 p6
Liquidated and ascertained damages: £TBC per Working Day, capped 10% of Contract Sum Commercial Mgr TLP §8.7 §B RESPONDED
COM-08
JCT
Sch. 2
Daywork rates per JCT IC 2016 Schedule 2 — Employer-instructed variations only Commercial Mgr TLP §8.7 §B RESPONDED
COM-09
ITT
§2.10 p6
Defects Liability Period: 12 months from Practical Completion Commercial Mgr TLP §8.4 §11.4 RESPONDED
COM-10
SBS
Quote val.
IDEAL Quote validity: order before 31 May 2026 to lock pre-rise pricing (3.5% rise post-31-May) Commercial Mgr TLP §8.5 A5.4 RFI
PRG
Programme
8 requirements · 7 responded · 1 RFI
7 ✓ 1 RFI
ID Source · Ref Requirement Owner Response Location Status
PRG-01
ITT
§3.1 p7
Construction window: within Kettlewick College summer-term stand-down (Jul–Sep 2026) Bid PM PRG Cover RESPONDED
PRG-02
ITT
§3.2 p7
Practical Completion target: Friday 9 October 2026 Bid PM PRG Master Gantt RESPONDED
PRG-03
ITT
§3.3 p7
Heat continuity to Malthouse Block must be maintained throughout works Tech Lead TLP §8.4 §4 + PDP §12 RESPONDED
PRG-04
ITT
§3.4 p8
Working hours: Mon–Fri 07:30–17:00 single shift; weekend / out-of-hours by permit only Bid PM TLP §8.5 A1.2 RESPONDED
PRG-05
ITT
§3.5 p8
Heavy-plant lift-in via skylight: single concentrated 5-day window in Phase 4 Tech Lead PDP §12 + PRG Detailed RESPONDED
PRG-06
ITT
§3.6 p8
OEM commissioning notice: IDEAL 4 weeks; Stokvis/Flamco/Arrow 2 weeks Bid PM PRG Key Interfaces RESPONDED
PRG-07
ITT
§3.7 p9
Witness commissioning notice: 10 Working Days to Employer / CA Bid PM TLP §8.4 §10.4 + PRG RESPONDED
PRG-08
ITT
§3.8 p9
Kettlewick blackout dates within construction window — to confirm Bid PM RFI
TEC
Technical
25 requirements · 22 responded · 3 RFI
22 ✓ 3 RFI
ID Source · Ref Requirement Owner Response Location Status
TEC-01
SDS
Doc 23 §F1
Heat generation: 3 × IDEAL EVO Max 2 — 150 kW boilers in cascade (450 kW combined) Tech Lead TLP §8.3.1 + BoQ F1 RESPONDED
TEC-02
SBS
Q18 §A
IDEAL EVO Max 2 cascade per SBS Quote 18-SQ0023969 Ver 1 Tech Lead TLP §8.3.1 + BoQ F1.1-F1.3 RESPONDED
TEC-03
SDS
Doc 23 §F2
Thermal storage: 3 × 2,000 L PD 5500 Cat 3 vertical thermal stores on 3-vessel frame Tech Lead TLP §8.3.2 + BoQ F2 RESPONDED
TEC-04
SDS
Doc 23 §F3
DHW generation: 2 × Stokvis Econoplate 700 kW PHE skids (N+1 resilience) Tech Lead TLP §8.3.2 + BoQ F3 RESPONDED
TEC-05
SDS
Doc 23 §F4
Heating PHE: 1 × Stokvis Econoplate 250 kW (LTHW secondary) Tech Lead TLP §8.3.2 + BoQ F4 RESPONDED
TEC-06
SDS
Doc 23 §F5
Pumps: Grundfos MAGNA3 D twin-head + MAGNA1 + AP50 sump Tech Lead TLP §8.3.3 + BoQ F5 RESPONDED
TEC-07
SDS
Doc 23 §F6
Pressurisation: 2 × Flamco Flexfiller 225DS digital + expansion vessels Tech Lead TLP §8.3.3 + BoQ F6 RESPONDED
TEC-08
SDS
Doc 23 §F7
Cold water boost: Arrow Valves Boost-A-Break Tank Set, WRAS Cat 5 Tech Lead TLP §8.3.3 + BoQ F7 RESPONDED
TEC-09
SDS
Doc 23 §F8
Flue: twin-wall CE-marked V-band clamped, 4-hr fire-resistance rating Tech Lead TLP §8.3.4 + BoQ F8 RESPONDED
TEC-10
SDS
Doc 23 §F9
Gas Safety Panel: Merlin 1000 with pressure-proving + SBS GSV065 solenoid + leak detection Tech Lead TLP §8.3.4 + BoQ F9 RESPONDED
TEC-11
SDS
Doc 23 §G1
Distribution Board: Schneider Merlin Gerin Acti 9 12-way 125 A TP&N Tech Lead TLP §8.3.6 + BoQ G1 RESPONDED
TEC-12
SDS
Doc 23 §G2
New LV sub-main from Malthouse Block main LV panel — fault level + spare way verified Tech Lead TLP §8.4 §3.4 RFI
TEC-13
SDS
Doc 23 §G3
BS 7671:2018+A2:2022 + NICEIC certification on completion Tech Lead TLP §8.4 §9 + BoQ G RESPONDED
TEC-14
SDS
Doc 23 §F10
BMS: 54-point I/O outstation + cause-and-effect programming Tech Lead TLP §8.3.5 + BoQ F6 (PC Sum) RESPONDED
TEC-15
ITT
§4.6 p11
BMS / Controls scope treatment — fixed price or PC Sum? Commercial Mgr TLP §8.5 A2.6 RFI
TEC-16
SDS
Doc 23 §F11
BSRIA BG 29/2020 chemical clean & dose; Sentinel X100 corrosion inhibitor Tech Lead TLP §8.4 §10.2 + BoQ E2 RESPONDED
TEC-17
SDS
Doc 23 §F12
BS 5422 closed-cell phenolic foam insulation to all primary services Tech Lead TLP §8.4 §7.13 + BoQ F12 RESPONDED
TEC-18
SDS
Doc 23 §F13
Gas tightness IGEM/UP/1 pre-commissioning test Tech Lead TLP §8.4 §10 + BoQ E3 RESPONDED
TEC-19
SDS
Doc 23 §F14
Existing flue void: structural and dimensional adequacy for new flue Tech Lead TLP §8.5 A2.4 + Stage 4a RESPONDED
TEC-20
SDS
Doc 23 §F15
Incoming gas supply pressure: capacity for 450 kW cascade at turndown Tech Lead RFI
TEC-21
SDS
Doc 23 §G4
Fire alarm: cause-and-effect interface via existing FA maintainer Tech Lead TLP §8.4 §9.7 + BoQ G6 RESPONDED
TEC-22
SDS
Doc 23 §G5
Emergency stop button at plant-room entrance; gas solenoid trip + BMS notification Tech Lead TLP §8.4 §9.9 + BoQ G7 RESPONDED
TEC-23
SDS
Doc 23 §G6
Lightning protection bonding to existing where applicable Tech Lead TLP §8.4 §9.8 RESPONDED
TEC-24
SDS
Doc 23 §F16
Builders' work: EI 120 fire-stopping (BS 9999), reinforced-concrete plinths Tech Lead TLP §8.3.7 + BoQ D2-D5 RESPONDED
TEC-25
SDS
Doc 23 §F17
Skylight remove / store / reinstate (5-day window in Phase 4) Tech Lead TLP §8.4 §6.4 + BoQ D3 RESPONDED
QAC
Quality / Commissioning
10 requirements · 10 responded · 0 RFI
10 ✓
ID Source · Ref Requirement Owner Response Location Status
QAC-01
ITT
§5.1 p13
OEM commissioning attendance: IDEAL (2 days), Stokvis (2 days), Flamco (1 day), Arrow (1 day) Bid PM TLP §8.4 §10.3 RESPONDED
QAC-02
ITT
§5.2 p14
Witness commissioning session — Employer / CA attendance Bid PM TLP §8.4 §10.4 + PRG M6 RESPONDED
QAC-03
BSI
BG 2/2010
BSRIA BG 2/2010 commissioning management framework Tech Lead PDP §13 + BoQ E1 RESPONDED
QAC-04
BSI
BG 1/2007
BSRIA BG 1/2007 format O&M manual delivery at PC Bid PM TLP §8.4 §10.7 + BoQ E5 RESPONDED
QAC-05
ITT
§5.4 p14
Inspection & Test Plans (ITPs) issued by phase before commencement QA Lead PDP §7.3 — 12 ITPs RESPONDED
QAC-06
ITT
§5.5 p15
Hydraulic pressure test certificate for primary LTHW circuit Tech Lead TLP §8.4 §10.1 + PRG HP9 RESPONDED
QAC-07
ITT
§5.6 p15
Gas Safe certification for gas pipework + Gas Safety Panel H&S Adviser TLP §8.4 §10 + PRG HP5 RESPONDED
QAC-08
ITT
§5.7 p15
BMS Site Acceptance Testing (SAT) records pack Tech Lead PRG HP8 RESPONDED
QAC-09
ITT
§5.8 p16
Joint handover inspection + snagging list at PC Bid PM TLP §8.4 §11.1 + PRG HP16 RESPONDED
QAC-10
ITT
§5.9 p16
Kettlewick FM team training: 2 × 4hr sessions Bid PM TLP §8.4 §11.3 + PRG HP15 RESPONDED
HSC
H&S / CDM
8 requirements · 8 responded · 0 RFI
8 ✓
ID Source · Ref Requirement Owner Response Location Status
HSC-01
ITT
§6.1 p17
CDM 2015 Principal Contractor: Grimshaw & Bolt Ltd H&S Adviser TLP §8.5 A3.1 + PDP §8 RESPONDED
HSC-02
ITT
§6.2 p17
Built AI as MEP sub-contractor — designer duties for CDP element only H&S Adviser TLP §8.2 + §8.5 A3.1 RESPONDED
HSC-03
ITT
§6.3 p17
Built AI integrates under GB Construction Phase Plan + site rules H&S Adviser PDP §8.2 RESPONDED
HSC-04
ITT
§6.4 p18
RAMS / COSHH submissions before mobilisation H&S Adviser PDP §1 (Doc Control) + Reg RESPONDED
HSC-05
ITT
§6.5 p18
Construction Phase Plan + F10 — discharged by GB as PC H&S Adviser TLP §8.5 A3.1 RESPONDED
HSC-06
JSP
JSP 375
JSP 375 (MOD Health & Safety) — site-specific compliance H&S Adviser TLP §8.5 A6.3 + PDP §8 RESPONDED
HSC-07
JSP
JSP 317
JSP 317 (Gas) — gas-related works compliance H&S Adviser TLP §8.5 A6.3 RESPONDED
HSC-08
ITT
§6.6 p19
Confined space (sump pit) rescue plan H&S Adviser PDP §8.3 RAMS-04 RESPONDED
STA
Statutory / Standards
6 requirements · 6 responded · 0 RFI
6 ✓
ID Source · Ref Requirement Owner Response Location Status
STA-01
BSI
BS 7671
BS 7671:2018+A2:2022 Wiring Regulations + NICEIC certification Tech Lead TLP §8.4 §9 + PRG HP12 RESPONDED
STA-02
BSI
BS 9999
BS 9999 fire safety — EI 120 fire-stopping Tech Lead TLP §8.4 §6.2 + BoQ D2 RESPONDED
STA-03
BSI
BS 5422
BS 5422 thermal insulation specification Tech Lead TLP §8.4 §7.13 + BoQ F12 RESPONDED
STA-04
BSI
IGEM/UP/1
IGEM/UP/1 gas tightness testing H&S Adviser TLP §8.4 §10 + PRG HP11 RESPONDED
STA-05
BSI
BS 5975
BS 5975:2019 — Temporary Works Coordinator (heavy-plant lift) Tech Lead TLP §8.4 §2.3 + PDP §12 RESPONDED
STA-06
BSI
CAR 2012
Control of Asbestos Regulations 2012 — LARC handles ACMs H&S Adviser TLP §8.5 A3.4 + C.1 RESPONDED
SIT
Site / Heritage / Logistics
5 requirements · 3 responded · 2 RFI
3 ✓ 2 RFI
ID Source · Ref Requirement Owner Response Location Status
SIT-01
ITT
§7.1 p20
Grade II* listed estate — heritage-sensitive working approach Tech Lead TLP §8.4 §6 + PDP §9 RESPONDED
SIT-02
ITT
§7.2 p20
Heritage approvals (Listed Building Consent) — already in place? Bid PM RFI
SIT-03
ITT
§7.3 p20
Conservation Officer sign-off on chimney repointing (lime mortar match) Tech Lead TLP §8.4 §6.5 + PDP §9 RESPONDED
SIT-04
SOC
Survey p4-12
Asbestos: ACMs identified — licensed removal by separately-appointed LARC H&S Adviser TLP §8.5 A3.4 + C.1 RESPONDED
SIT-05
SOC
Appendix C-D
SOCOTEC survey appendices C and D — missing from tender pack H&S Adviser RFI
SUB
Submission
6 requirements · 5 responded · 0 RFI · 1 pending
5 ✓ 1
ID Source · Ref Requirement Owner Response Location Status
SUB-01
ITT
§8.1 p22
Submission method: email to G&B Bid Office (single PDF + native xlsx for BoQ) Bid PM PDF compile + native BoQ RESPONDED
SUB-02
ITT
§8.2 p22
Submission deadline: Friday 24 April 2026 17:00 BST Bid PM Last Look QA on 23 Apr RESPONDED
SUB-03
ITT
§8.3 p22
Mandatory documents: Tender Letter, Priced BoQ, Programme, RAMS sample Bid PM CS + TLP + BoQ + PRG RESPONDED
SUB-04
ITT
§8.4 p23
Insurance certificates — current originals attached Commercial Mgr Submission Annex A RESPONDED
SUB-05
ITT
§8.5 p23
Sample RAMS (1 representative work activity) — attached to submission H&S Adviser Submission Annex B RESPONDED
SUB-06
ITT
§8.6 p23
Maximum file size: 50 MB total attachment Bid PM Confirm at Last Look PENDING
NEXT STAGE

Hand-Off to Question Time™

Roll Call complete. Seven RFIs raised during requirement extraction will be carried into the Question Time™ register at Stage 03, joined by any further clarifications identified during scope analysis and pricing.

7 RFIs to Question Time™: COM-10 (IDEAL price-rise window), PRG-08 (Kettlewick blackout dates), TEC-12 (LV supply capacity), TEC-15 (BMS scope — fixed vs PC Sum), TEC-20 (gas supply pressure), SIT-02 (heritage approvals), SIT-05 (SOCOTEC appendices C+D missing).

Roll Call sign-off checks

Question Time™ opens 8 April 2026. All seven RFIs will be drafted, raised to Grimshaw & Bolt within 2 working days, and tracked through to closure or commercial assumption before submission. Target: all RFIs closed or parked by 22 April 2026 — 1 day before Last Look QA.
BIDROOM IN A BOX™
PRODUCTION NOTE

Roll Call · Stage 02

Every requirement called out by name

Roll Call™ is the second stage of the Bidroom in a Box™ workflow. It indexes every page of the tender pack, extracts every requirement, maps each one back to its source document and clause reference, assigns an owner, and records where the response will land in the submission. Open RFIs are routed to Question Time™ at Stage 03; everything else flows into Scope, Cost Stack and the client deliverables.

REQUIREMENTS LOGGED
78
SOURCE-TRACEABILITY
100%
RFIs RAISED EARLY
7