The Bid Room
Bidroom in a Box™Pack 01 / 06 · Client deliverable
Tender Letter Proposal · the formal submission

Our formal tender for B99 Malthouse Block

The formal tender submission to Grimshaw & Bolt Ltd: the cover letter, the technical and commercial position, the scope of works with a responsibility matrix, and the schedule of assumptions, clarifications and exclusions. This document governs the commercial interpretation of the bid and reconciles to the priced Bill of Quantities.

Prepared for
Grimshaw & Bolt Ltd
Attention
Grimshaw & Bolt bid office
Reference
ITT KW-2026-4471
Sub-contract
JCT Intermediate 2016 with CDP
Prepared by
BuiltAI Intelligence Ltd
Revision
Rev 1

Illustrative example: fictional project and parties.

£481,954.33Fixed tender sum, excl. VAT
6VE options offered
£56,737Maximum VE saving
90 WDTender validity
BuiltAI Intelligence Ltd · built-ai.ioB99-TLP · Rev 1
01Submission

Cover letter and executive summary

We are pleased to submit our tender for the replacement of the heat source and associated mechanical, electrical, public-health and controls infrastructure at the B99 Malthouse Block boiler house, Kettlewick College. This submission is made to Grimshaw & Bolt Ltd as Principal Contractor, acting on behalf of Kettlewick Estates as Employer, under a JCT Intermediate 2016 sub-contract with Contractor's Design Portion.

The offer, in short

A fixed tender sum of £481,954.33, excluding VAT, held for 90 working days and for 12 months from order placement. The BMS and controls package (Section F6) is carried as a Prime Cost Sum for a specialist appointed on instruction. Preliminaries are priced on a sub-contractor basis, on the footing that site establishment, welfare and the construction phase plan sit with the Principal Contractor.

Six value-engineering options are offered separately, for a maximum aggregate saving of £56,736.86, taking the net sum to £425,217.47 if all are accepted.

02Scope

Scope of works and responsibilities

BuiltAI delivers the complete MEP, public-health and controls-interface installation. Scope-boundary risk sits with the Principal Contractor under the sub-contract. The matrix below sets responsibility across the key interfaces; R is responsible, A accountable, C consulted, I informed.

ActivityBuiltAIGrimshaw & BoltOthers
Mechanical, PH and electrical installR, AInil
Contractor's Design Portion, CDP elementR, ACSDS designer, C
Licensed asbestos removalCALARC, R
Temporary heating continuityC, interface onlyR, Anil
BMS and controls, Prime Cost SumC, interface onlyABMS specialist, R
Site establishment and CPPIR, Anil
Witness commissioningRCEmployer and CA, A

BuiltAI provides the hydraulic, electrical and BMS interface points to the temporary-boiler and BMS-specialist scopes; execution of those scopes sits with the parties shown.

03Commercial

Commercial position and value engineering

The tender is a fixed lump sum at the baseline specification. Daywork, where instructed, is priced per the JCT Intermediate 2016 daywork schedule. The six value-engineering options are alternatives to the baseline, each electable individually or in combination, and are held in the priced BoQ workbook.

PositionValue
Fixed tender sum, baseline, excl. VAT£481,954.33
Provisional sums within the sum, Section I£17,500.00
BMS Prime Cost Sum within Section F£18,000.00
Maximum VE saving, six options−£56,736.86
Net sum if all VE accepted£425,217.47

Retention is 3%, moiety at Practical Completion and balance at the end of the defects liability period. Payment is by monthly interim valuation at 21 days. Insurances are CAR, EL £10m, PL £10m and PI £5m on the CDP element.

04Qualifications

Assumptions, clarifications and exclusions

This schedule takes precedence over the scope narrative for commercial interpretation. The three clarifications are the queries that could not be closed at tender stage, priced to a stated assumption and reserved here.

TypeItem and position
AssumptionBaseline specification priced; six VE options offered separately
AssumptionPreliminaries on a sub-contractor basis; PC provides site establishment, welfare and CPP
AssumptionBMS and controls carried as a Prime Cost Sum, drawn down on PC instruction
ClarificationBond and PCG: no bond below £500k assumed; PCG at 10% to PC plus 12 months
ClarificationLiquidated damages: rate to be agreed pre-contract; priced to a working assumption
ClarificationOEM price escalation beyond validity recoverable via Provisional Sum I7.1
ExclusionLicensed asbestos removal and four-stage clearance, by a separate contractor
ExclusionTemporary heating and DHW continuity, provided by the Principal Contractor
ExclusionInternal redecoration, planning and heritage consents, upstream LV alterations
Reference B99-TLP · Rev 1Tender sum £481,954.33Reconciles priced BoQ Rev 1

Up next

PDP · Project Delivery Plan Back to the Bidroom Pack page