Bidroom · Last Look™ - Stage 05 · Worked example B99 Malthouse Block · Grimshaw & Bolt · ITT KW-2026-4471 · £481,954.33
← Bidroom Pack
ILLUSTRATIVE · INTERNAL
BIDROOM IN A BOX™ STAGE 05 · SUBMISSION QA

Last Look

Pre-Submission QA Checklist
The final pass before the door. Every box ticked, every signature captured, every figure reconciled. The Bidroom workflow's last gate before the pack hits the client's inbox.
Project
B99 Malthouse Block Boiler House Replacement
Submission
Friday 24 April 2026 · 17:00 BST → Grimshaw & Bolt Ltd Bid Office
Last Look opened
23 April 2026 · 09:00
Last Look closed
23 April 2026 · 16:30 — Bid PM submission authorised
Reference
LL-2026-117
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
BIDROOM WORKFLOW 1Front Desk 2Roll Call 3Question Time 4Cost Stack
5Last Look
CLIENT DELIVERABLES CSSummary TLPTender Letter PDPDelivery Plan BoQPriced BoQ PRGProgramme
SUBMISSION READINESS

Ready for the Door

Last Look is the master gate. It runs across the four prior Bidroom stages plus the five client deliverables to confirm everything reconciles, every requirement is responded, every figure ties up, every approval is in place. Status at sign-off (23 April 2026, 16:30):

READY TO SUBMIT
All 62 checks passed · 6 sign-offs recorded · 0 open RFIs
SUBMISSION DEADLINE
24 Apr 2026 17:00
Fri · 24h 30m to deadline at sign-off
FINAL TENDER TOTAL
£481,954.33
excl. VAT · baseline · 90 WD validity
TOTAL CHECKS
62
across 9 categories
PASS
62
100% gate complete
FAIL
0
no blockers
WARN
0
no flags
SIGN-OFFS
6
all roles signed
CROSS-PACK RECONCILIATION

Numbers That Must Match

Ten critical figures that appear in multiple deliverables — the tender total, programme dates, validity periods, VE savings, contract terms. Every one verified across all sources. Zero deltas.

Cross-Pack Reconciliation

10 critical figures verified across all 5 client deliverables.
All match — zero deltas.

FigureValueVerified AcrossStatus
Fixed Tender Total (excl. VAT) £481,954.33 CS Hero · TLP §8.7 §B · BoQ Section Summary · Cost Stack™ ✓ MATCH
Tender Validity 90 Working Days CS · TLP §8.7 §B ✓ MATCH
Practical Completion Date Fri 9 October 2026 CS · TLP §8.4 §1.4 · PDP §12 · PRG Cover ✓ MATCH
Construction Window 14 weeks CS · TLP §8.4 §1 · PDP §12 · PRG Master Gantt ✓ MATCH
Construction Start Date Mon 6 July 2026 TLP §8.4 §1.4 · PDP §12 · PRG Cover ✓ MATCH
Defects Liability Period 12 months from PC CS · TLP §8.4 §11.4 · PDP §13 ✓ MATCH
Total VE Saving (if all 6) £56,736.86 BoQ VE Options · TLP §8.7 §C ✓ MATCH
Tender Total if all VE accepted £425,217.47 BoQ VE summary · TLP §8.7 §C ✓ MATCH
BMS PC Sum (RFI-04) £18,000 Question Time RFI-04 · BoQ F6 · TLP §8.5 A2.6 ✓ MATCH
Provisional Sums Total £17,500 BoQ Section I · TLP §8.5 D · Cost Stack PSM layer ✓ MATCH
MASTER CHECKLIST

62 Checks Across 9 Categories

The Last Look master checklist. Each item has a defined owner, an evidence location (where in the pack it's confirmed), and a timestamp. Pack, Scope and Commercial sections are open by default — the rest collapse to show summary counts. All 62 items pass at submission gate.

PASS Check confirmed with evidence
8/8 ✓ Category fully passed
📦
Deliverables Pack
8 / 8 checks passed · All five client deliverables present, named, dated, branded, and indexed for submission.
8/8 ✓
ID Check Evidence Location Confirmed By Timestamp Status
PACK-01 Client Summary (CS) Rev 1 drafted and reviewed CS Rev 1 — 13 pp Bid PM 23 Apr 09:14 PASS
PACK-02 Tender Letter Proposal (TLP) Rev 1 drafted and reviewed TLP Rev 1 — 35 pp Bid PM 23 Apr 09:18 PASS
PACK-03 Project Delivery Plan (PDP) Rev 1 drafted and reviewed PDP Rev 1 — 44 pp Tech Lead 23 Apr 09:22 PASS
PACK-04 Priced Bill of Quantities (BoQ) Rev 1 drafted and reconciled BoQ Rev 1 — 39 pp + xlsx Commercial Mgr 23 Apr 09:26 PASS
PACK-05 Programme (PRG) Rev 1 drafted with master Gantt and detailed activities PRG Rev 1 — 11 pp + xlsx Bid PM 23 Apr 09:30 PASS
PACK-06 Document family identifiers consistent across all 5 files (KW-2026-4471) All cover sheets QA Lead 23 Apr 10:15 PASS
PACK-07 File naming convention applied: B99_Malthouse_Block_<Type>_Rev1_BuiltAI.<ext> File system check Bid Admin 23 Apr 10:20 PASS
PACK-08 Annexes attached: Insurance certs, RAMS sample, PCG draft Annexes A, B, C Bid Admin 23 Apr 10:24 PASS
📋
Scope & Methodology
7 / 7 checks passed · Scope structured per discipline. Inclusions, exclusions, and assumptions explicit. CDP element clearly identified.
7/7 ✓
ID Check Evidence Location Confirmed By Timestamp Status
SCOPE-01 Scope structured per discipline (Mech, PH, Electrical, Controls, BWIC) TLP §8.4 + BoQ Sections F-G-H Tech Lead 23 Apr 10:32 PASS
SCOPE-02 Inclusions explicitly stated (TLP §8.5 A — 18 items) TLP §8.5 A1.1–A6.3 Tech Lead 23 Apr 10:38 PASS
SCOPE-03 Exclusions explicitly stated (TLP §8.5 B — 14 items) TLP §8.5 B1.1–B5.4 Tech Lead 23 Apr 10:42 PASS
SCOPE-04 Assumptions explicitly stated (TLP §8.5 C — 11 items) TLP §8.5 C1.1–C4.3 Tech Lead 23 Apr 10:48 PASS
SCOPE-05 CDP element clearly identified (flue, BMS controls, TWC) TLP §8.2 + PDP §4 Tech Lead 23 Apr 10:52 PASS
SCOPE-06 Methodology documented per phase (Phases 0–10) PDP §12 + PRG Detailed Tech Lead 23 Apr 10:58 PASS
SCOPE-07 6 VE options independently structured and priced BoQ VE Options tab Commercial Mgr 23 Apr 11:04 PASS
£
Commercial Position
10 / 10 checks passed · Tender total reconciles across all docs. Validity, insurances, payment terms, contract form, daywork basis all stated.
10/10 ✓
ID Check Evidence Location Confirmed By Timestamp Status
COMM-01 Fixed Tender Total reconciles: CS = TLP = BoQ Section Summary = £481,954.33 3-way reconciliation Commercial Mgr 23 Apr 11:14 PASS
COMM-02 Tender Validity stated as 90 Working Days (CS + TLP §8.7 §B) TLP §8.7 §B / CS Commercial Mgr 23 Apr 11:18 PASS
COMM-03 Insurance levels stated (CAR £5m, EL £10m, PL £10m, PI £10m on CDP) TLP §8.5 A5.3 + Annex A Commercial Mgr 23 Apr 11:22 PASS
COMM-04 Payment terms stated: monthly interim, 21 days, 3% retention TLP §8.7 §B Commercial Mgr 23 Apr 11:24 PASS
COMM-05 Contract form referenced: JCT IC 2016 with CDP TLP §8.2 + §8.7 §B Commercial Mgr 23 Apr 11:28 PASS
COMM-06 Daywork rates basis confirmed: JCT IC 2016 Schedule 2 TLP §8.7 §B + RFI-12 closed Commercial Mgr 23 Apr 11:32 PASS
COMM-07 VE Options total saving stated: £56,736.86 if all six accepted BoQ VE + TLP §8.7 §C Commercial Mgr 23 Apr 11:36 PASS
COMM-08 Provisional Sums clearly identified: BoQ Section I = £17,500 (Doc 23 Table 18) BoQ I1.1–I7.1 + TLP §8.5 D Commercial Mgr 23 Apr 11:40 PASS
COMM-09 PARKED RFIs reflected in TLP §8.5 ACE schedule (RFI-13 PCG, 14 LADs, 16 escalation) TLP §8.5 A5.6 + C Commercial Mgr 23 Apr 11:48 PASS
COMM-10 PCG draft attached (10% of Contract Sum, duration to PC + 12 months) Submission Annex C Commercial Mgr 23 Apr 11:52 PASS
📅
Programme Integrity
7 / 7 checks passed · Practical Completion date consistent. Phasing aligned to BoQ. Milestones, hold-points and critical path identified.
7/7 ✓
ID Check Evidence Location Confirmed By Timestamp Status
PROG-01 Practical Completion date consistent: Friday 9 October 2026 (CS = TLP = PDP = PRG) 4-way reconciliation Bid PM 23 Apr 12:04 PASS
PROG-02 Construction window: 14 weeks (CS = TLP = PDP = PRG) 4-way reconciliation Bid PM 23 Apr 12:06 PASS
PROG-03 Construction start: Mon 6 July 2026 (Kettlewick summer-term stand-down) PRG Cover + PDP §12 Bid PM 23 Apr 12:08 PASS
PROG-04 Phasing aligned to BoQ structure (Phases 0–10 mapped to BoQ Sections A–I) PRG Detailed × BoQ Bid PM 23 Apr 12:14 PASS
PROG-05 9 milestones identified (M1–M9) with notice periods PRG Key Interfaces + PDP §13 Bid PM 23 Apr 12:18 PASS
PROG-06 16 hold-points identified (HP1–HP16) with responsible parties PRG Key Interfaces Bid PM 23 Apr 12:20 PASS
PROG-07 Critical path identified: M2 → M3 → M4 → P5/P6 → P7 → P8 → M6 → M7 → M8 PRG Master Gantt callout Bid PM 23 Apr 12:24 PASS
Risk & H&S
6 / 6 checks passed · Risk register populated. Heat-map shown. CDM 2015 duties clear. Asbestos approach documented. F10 confirmed.
6/6 ✓
ID Check Evidence Location Confirmed By Timestamp Status
RISK-01 Risk register populated (PDP §11 — 18 risks) PDP §11 register Tech Lead 23 Apr 12:38 PASS
RISK-02 Heat-map shown (5×5 likelihood × impact) PDP §11 heat-map Tech Lead 23 Apr 12:42 PASS
RISK-03 CDM 2015 duties clear: G&B as PC, Built AI as MEP sub-contractor (designer for CDP only) TLP §8.5 A3.1 + PDP §8 H&S Adviser 23 Apr 12:46 PASS
RISK-04 Asbestos approach documented: separately-appointed LARC; CAR 2012 designer duties recorded TLP §8.5 C.1 + PDP §8.3 H&S Adviser 23 Apr 12:50 PASS
RISK-05 RAMS sample attached (1 representative work activity — boiler lift-in) Submission Annex B H&S Adviser 23 Apr 12:54 PASS
RISK-06 F10 filing confirmed by GB (ref F10/2026/3392, filed 14 Apr 2026) RFI-17 closed H&S Adviser 23 Apr 12:58 PASS
?
RFIs & Clarifications
5 / 5 checks passed · All 19 RFIs closed or formally parked. Parked items reflected in TLP §8.5 ACE schedule. Source mapping complete.
5/5 ✓
ID Check Evidence Location Confirmed By Timestamp Status
RFI-01 19 RFIs raised across the bid window (7 from Roll Call + 12 standalone) Question Time™ register Bid PM 23 Apr 13:14 PASS
RFI-02 16 RFIs CLOSED with response received from Grimshaw & Bolt Question Time™ register Bid PM 23 Apr 13:16 PASS
RFI-03 3 RFIs PARKED as commercial assumptions (RFI-13 PCG, RFI-14 LADs, RFI-16 escalation) TLP §8.5 ACE + Question Time Commercial Mgr 23 Apr 13:18 PASS
RFI-04 0 RFIs OPEN at submission gate Question Time™ register QA Lead 23 Apr 13:20 PASS
RFI-05 Source mapping in Roll Call complete: 78 requirements traced to source documents Roll Call™ matrix Tech Lead 23 Apr 13:24 PASS
🧮
Pricing Build-Up
8 / 8 checks passed · Cost Stack reconciles to BoQ. Layer mix documented. Risk pot allocated. OH&P at line-item level.
8/8 ✓
ID Check Evidence Location Confirmed By Timestamp Status
PRICE-01 Cost Stack reconciles to BoQ Rev 1 (delta £0.00) Cost Stack™ reconciliation Commercial Mgr 23 Apr 13:38 PASS
PRICE-02 8 cost layers documented with traceable working Cost Stack™ layer detail Commercial Mgr 23 Apr 13:42 PASS
PRICE-03 Material rates verified against OEM quotes (SBS, Stokvis, Flamco, Arrow) Cost Stack F1.1, F4.1, F6.1, F7.1 Estimator 23 Apr 13:46 PASS
PRICE-04 Labour rates current — Built AI Mar 2026 rate card applied Cost Stack labour rates Estimator 23 Apr 13:48 PASS
PRICE-05 Sub-let allowances: 3 quotes received and mid-quote priced (LARC, crane, FA) Cost Stack C7.1, A6.3, G6 Estimator 23 Apr 13:52 PASS
PRICE-06 Risk pot £8,050 allocated against 6 named risks (not flat %) Cost Stack Risk Strategy panel Commercial Mgr 23 Apr 13:56 PASS
PRICE-07 OH&P 8% applied at line-item level (not bottom-loaded) Cost Stack methodology Commercial Mgr 23 Apr 14:00 PASS
PRICE-08 6 VE options independently priced (max saving £56,736.86) BoQ VE Options + TLP §8.7 §C Commercial Mgr 23 Apr 14:04 PASS
Format & Compliance
6 / 6 checks passed · File sizes within limit. PDF + native xlsx. Page layout consistent. Metadata cleaned. Confidential markings present.
6/6 ✓
ID Check Evidence Location Confirmed By Timestamp Status
FORMAT-01 Total submission size 38.4 MB (within ITT §8.6 50 MB limit) File system check Bid Admin 23 Apr 14:18 PASS
FORMAT-02 Submission format: single PDF (5 deliverables) + native xlsx (BoQ) Submission package Bid Admin 23 Apr 14:22 PASS
FORMAT-03 Document branding consistent (Built AI navy/amber + Bidroom-in-a-Box markings) All 5 deliverable covers QA Lead 23 Apr 14:26 PASS
FORMAT-04 Page numbering, headers, footers consistent across pack Page-by-page check QA Lead 23 Apr 14:32 PASS
FORMAT-05 Metadata cleaned (author = Built AI Ltd, no draft revisions, no track changes) PDF + xlsx properties Bid Admin 23 Apr 14:36 PASS
FORMAT-06 ILLUSTRATIVE marking on every page; no unredacted sensitive data Watermark check QA Lead 23 Apr 14:40 PASS
Sign-Off & Approvals
5 / 5 checks passed · All required Built AI sign-offs in place. Bid Director final approval recorded.
5/5 ✓
ID Check Evidence Location Confirmed By Timestamp Status
SIGN-01 Bid Director final approval recorded Approval record Bid Director 23 Apr 16:14 PASS
SIGN-02 Tech Lead sign-off on technical scope and CDP element Approval record Tech Lead 23 Apr 16:18 PASS
SIGN-03 Commercial Manager sign-off on pricing, terms, validity Approval record Commercial Mgr 23 Apr 16:22 PASS
SIGN-04 QA Lead sign-off on Last Look master checklist completion Last Look closure QA Lead 23 Apr 16:26 PASS
SIGN-05 Bid PM final review and submission authorisation Submission authorisation Bid PM 23 Apr 16:30 PASS
FINAL APPROVALS

Bid Team Sign-Off

Six required approvals captured before submission. Each role-holder signs off on their domain — technical scope, commercial position, QA closure, submission authorisation. The Bid Director's sign-off is the final commercial gate.

BID DIRECTOR
A. Senior Director
Final approval to submit; commercial position; win-strategy
SIGNED 23 Apr 2026 16:14
TECH LEAD
C. Tech Lead
Technical scope, CDP element, design assumptions
SIGNED 23 Apr 2026 16:18
COMMERCIAL MGR
D. Commercial Mgr
Pricing, terms, validity, contract caveats
SIGNED 23 Apr 2026 16:22
QA LEAD
E. QA Lead
Last Look master checklist closure
SIGNED 23 Apr 2026 16:26
BID PM
B. Project Manager
Bid coordination, submission authorisation
SIGNED 23 Apr 2026 16:30
BID ADMIN
F. Bid Admin
Submission package upload + transmission
SIGNED 24 Apr 2026 14:42
Submission authorised: All six approvals captured between 16:14 and 16:30 BST on 23 April 2026. Bid Admin scheduled for 14:42 BST on 24 April 2026 to upload to G&B Bid Office portal — well within the 17:00 deadline.
OUT THE DOOR

Submission Package

SUBMITTED TO GRIMSHAW & BOLT BID OFFICE
Friday 24 April 2026 · 14:42 BST
SUBMISSION PACKAGE
  • B99_Malthouse_Block_Client_Summary_Rev1_BuiltAI.pdf (1.4 MB · 13 pp)
  • B99_Malthouse_Block_Tender_Letter_Proposal_Rev1_BuiltAI.pdf (4.2 MB · 35 pp)
  • B99_Malthouse_Block_Project_Delivery_Plan_Rev1_BuiltAI.pdf (5.8 MB · 44 pp)
  • B99_Malthouse_Block_Priced_BoQ_Rev1_Client_BuiltAI.pdf (12.4 MB · 39 pp)
  • B99_Malthouse_Block_Priced_BoQ_Rev1_Client_BuiltAI.xlsx (1.8 MB · 4 sheets)
  • B99_Malthouse_Block_Programme_Rev1_BuiltAI.pdf (3.4 MB · 11 pp)
  • B99_Malthouse_Block_Programme_Rev1_BuiltAI.xlsx (980 kB · 5 sheets)
  • Annex A — Insurance certificates (4.2 MB)
  • Annex B — RAMS sample, boiler lift-in (2.8 MB)
  • Annex C — PCG draft on G&B form (1.4 MB)
TRANSMISSION DETAILS
  • Total package size: 38.4 MB (within 50 MB limit)
  • Recipient: bids@grimshaw-bolt.co.uk + Jamie Hartley (Senior PM)
  • cc: hello@built-ai.io (audit copy)
  • Subject: B99 Malthouse Block — Built AI Tender Submission Rev 1
  • Read receipt: requested
  • Transmission method: G&B SFTP (preferred) + email backup
  • Confirmation logged at: 14:42 BST · 24 Apr 2026
  • Read receipt acknowledged: 14:51 BST
WORKFLOW COMPLETE

Bidroom in a Box™ Loop Closed

Last Look closes the Bidroom workflow. Across 22 working days (1 April → 24 April 2026), 17 working days of bid window, the workflow has produced 5 audit-ready client deliverables, processed 78 source-traced requirements, closed 19 RFIs, layered an £481,954.33 priced BoQ across 8 cost layers, and walked it through 62 final QA checks.

If awarded, Bidroom hands the project across to the Built AI delivery workflows. The same source-of-truth that powered the bid now powers the build:
→ DELIVERY

RAMS Factory™

Tender scope and methodology become the seed for site-ready Risk Assessments and Method Statements. Inclusions in TLP §8.4 → activity index in RAMS Factory.

→ COMMERCIAL

Commercial Control Kit™

Bidroom assumptions, exclusions and parked RFIs become the entitlement defence layer. Variation traceability against the recorded TLP §8.5 ACE schedule.

→ MARGIN

Operational Margin Cockpit™

Cost Stack layers become the actuals-vs-priced tracker. Risk pot drawdown, OH&P erosion, sub-let margin variance — all visible as the project runs.

Bidroom workflow summary

5 stages · 1 source-of-truth · 5 client deliverables · ~50% time vs traditional manual production:

STAGE 01 · INTAKEFront Desk™
1 Apr · 4 hrs to BID decision
STAGE 02 · TRACEABILITYRoll Call™
2-6 Apr · 78 reqs, 100% mapped
STAGE 03 · CLARIFICATIONSQuestion Time™
8-22 Apr · 19 RFIs, 0 open
STAGE 04 · PRICINGCost Stack™
10-22 Apr · 8 layers, £481,954
STAGE 05 · QALast Look™
23 Apr · 62/62 pass · SUBMITTED
BIDROOM IN A BOX™
PRODUCTION NOTE

Last Look · Stage 05

Every box ticked. Every signature captured. Out the door.

Last Look™ is the fifth and final stage of the Bidroom in a Box™ workflow. It runs the master pre-submission checklist across the four prior Bidroom stages plus all five client deliverables — confirming reconciliation, completeness, traceability, format compliance, and approval. Without Last Look, the workflow doesn't end. With Last Look, the bid leaves the building with confidence.

CHECKS COMPLETED
62
CROSS-PACK MATCHES
10
SIGN-OFFS
6