The Bid Room
Bidroom in a Box™Stage 04 of 5 · Internal workflow
STAGE 04 · Cost Stack™ · internal pricing build-up, not client-facing

Every line built from the ground up

Cost Stack is the master pricing model. It builds each priced line from its component layers, materials, labour, plant, sub-let, preliminaries, provisional sums, risk and overhead, then reconciles the layers to the Bill of Quantities. Risk and margin are applied at line level, never bottom-loaded, so every rate is defensible at QS review and at variation.

Project
B99 Malthouse Block · 14 weeks
Reference
ITT KW-2026-4471
Opened
5 May 2026
Closed for review
13 May 2026
Lead estimator
Iola Rees-Brown
Reconciliation
Delta £0.00 to BoQ

Illustrative example: fictional project and parties.

£481,954Tender total, excl. VAT
84Priced lines built up
8Cost layers
6VE options priced
BuiltAI Intelligence Ltd · built-ai.ioB99-CST-04 · Stage 04
01The stack

The tender total, layer by layer

The £481,954.33 baseline total resolves into eight cost layers. Materials dominate, driven by the IDEAL cascade and the Stokvis plate-heat-exchanger skids. Overhead and profit is the last layer applied, at line level.

LayerWhat it coversValueShare
MaterialsBoilers, stores, PHEs, pipework, valves, cable, insulation£245,68051.0%
LabourIn-house operatives at all-in rates£81,94017.0%
Plant and toolsMEWP, mobile tower, lighting, consumables£13,7202.8%
Sub-letLARC asbestos, BMS Prime Cost Sum, crane, fire-alarm£41,8508.7%
Site preliminariesBuiltAI prelims share on a sub-contractor basis£35,2607.3%
Provisional sumsSection I, client-led drawdown only£17,5003.6%
Risk potContingency against named risks, not a flat rate£8,0501.7%
Overhead and profitRecovery applied at line level£37,9547.9%
Fixed tender total, excl. VAT£481,954.33100%
Materials51.0%
Labour17.0%
Sub-let8.7%
Overhead and profit7.9%

Layer values are shown to the nearest pound; the priced total is the exact £481,954.33.

02By section

How the layers land across the sections

The same money reads a second way, as the eight priced BoQ sections. Section F, mechanical and public health, carries almost two thirds of the total and is material-led. Strip-out is sub-let-heavy because the licensed asbestos removal sits there. Preliminaries are labour and plant. The two views reconcile to the same £481,954.33.

SecPackageLayer characterTotal
APreliminariesLabour and plant led£51,526
BSurveysLabour led£8,298
CStrip-outSub-let led, LARC asbestos£26,377
DBuilders' workLabour and materials£29,596
ETesting and commissioningLabour led£27,601
FMechanical and public healthMaterial led, includes BMS PC Sum£296,990
GElectricalMaterial and labour£24,066
IProvisional sumsClient-led drawdown£17,500
Eight priced sections£481,954.33

Section H, statutory notifications, prices to nil on this contract; the Principal Contractor discharges the F10 and construction phase plan.

03Method

Representative build-ups

Five of the 84 priced lines, each carried from direct cost through a named risk allowance and a line-level overhead uplift to the final tender line total. Rates use the March 2026 all-in labour card: engineer £58, fitter £52, electrician £56 per hour.

RefLine itemRiskOH&PLine total
F1.1IDEAL EVO Max 2 boiler, supply and install4.0%7.5%£28,340.18
C7.1LARC asbestos removal, thermal residue5.0%6.0%£11,817.83
A6.3Mobile crane and lifting rig, lift-in8.0%7.0%£9,579.92
F12.5Phenolic insulation to primary pipework, 65 LM3.0%8.0%£3,326.63
G1.1Schneider Acti 9 distribution board and connection3.0%8.0%£3,276.02
Pricing rule

Risk and overhead sit on each line, not in a general margin at the bottom. That keeps every rate independently defensible at QS review and at variation negotiation under JCT Intermediate 2016, with no hidden loading in inflated rates.

04Risk

The risk pot, allocated not smeared

The £8,050 risk pot is 1.7% of the total, allocated against six specific identified risks rather than a flat percentage on everything. Risks that transfer cleanly through a Provisional Sum are kept out of the pot to avoid double-counting, so escalation and instructed variations are handled elsewhere.

Named riskAllowance
Phase 4 lift-in weather window£2,400
Asbestos underfinds during strip-out£1,800
Existing-condition verification surveys£1,500
OEM lead-time slip£1,200
Commissioning re-attendance£800
BMS interface clarification£350
Risk pot, six named risks£8,050
05VE options

Six value-engineering options, priced in full

Each option is a costed alternative to the baseline specification, built up on the same March 2026 rate card as the tender, so every figure is a real delta and not a headline discount. Any option may be elected on its own or in combination, subject to written sign-off. Accepting all six takes the fixed tender from £481,954.33 to £425,217.47, a maximum saving of £56,736.86.

RefAlternative to baselineSaving
VE 1Thermal store consolidation, one 6,000 L for three 2,000 L£9,122.00
VE 2DHW PHE consolidation, one for two 700 kW, foregoing N+1£24,200.00
VE 3Flue fire rating, 3-hour for 4-hour£3,000.00
VE 4DHW PHE supplier substitution, per PHE£9,401.42
VE 5Heating PHE format, bare exchanger for packaged£6,590.00
VE 6Cold-water booster substitution£4,423.44
Maximum saving, all six accepted£56,736.86
VE 2 DHW PHE consolidation42.7%
VE 4 DHW PHE supplier substitution16.6%
VE 1 thermal store consolidation16.1%
VE 5 heating PHE format11.6%

Shares are each option against the £56,736.86 on offer. The plate-heat-exchanger options carry most of the saving. VE 4 is quoted at the conservative single-exchanger figure, and if VE 2 is rejected and the paired exchangers are retained the VE 4 saving doubles, because two exchangers are then in scope.

Client-led decision

Value engineering is offered, never assumed. Each option is held as a separate priced line so the baseline total is never eroded silently, and a saving is only taken when the client elects it in writing. VE 2 carries a resilience trade-off, since foregoing N+1 removes the standby duty on the domestic hot water exchangers.

Reference B99-CST-04Reconciles £481,954.33, delta £0.00Next Last Look, Stage 05