Bidroom · Programme (PRG) · Worked example B99 Malthouse Block · Grimshaw & Bolt · ITT KW-2026-4471 · £481,954.33
← Bidroom Pack
ILLUSTRATIVE
PROGRAMME / WORK SCHEDULE — REV 1

B99 Malthouse Block

Boiler House Replacement — 14-Week Construction Programme

Prepared for
Grimshaw & Bolt Ltd
Prepared by
Built AI Ltd
Date
27 April 2026
Reference
KW-2026-4471
START
6 Jul 2026
Mon, Week 1
PRACTICAL COMPLETION
9 Oct 2026
Fri, Week 14
DURATION
14 weeks
Mon–Fri single shift
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
PROGRAMME OVERVIEW

Planning Assumptions & Basis

This Programme Rev 1 is the working-level baseline for the 14-week construction window at B99 Malthouse Block boiler house. It is aligned with the Tender Letter Proposal Rev 1, Priced BoQ Rev 1 (£481,954.33 baseline) and Project Delivery Plan Rev 1.

Working Assumptions

Cross-Reference

PHASE-LEVEL VIEW

Master Gantt Chart

Phase-level rolled-up Gantt for client / stakeholder presentation. Construction window highlighted; Phase 10 (Defects Liability + Seasonal Commissioning) extends through to October 2027 and is shown separately in the Detailed Programme.

14-Week Construction Programme

Mon 6 Jul → Fri 9 Oct 2026
11 May
25 May
8 Jun
22 Jun
W1 · 6 Jul
W4 · 27 Jul
W7 · 17 Aug
W10 · 7 Sep
PC · 9 Oct
P0 · Pre-Construction
11 May – 17 Jul
P1 · Mobilisation + Stage 4a
29 Jun – 10 Jul
P2 · Strip-Out & Removal
20 Jul – 07 Aug
P3 · Builders' Work
27 Jul – 14 Aug
P4 · Heavy-Plant Lift-In
17 Aug – 21 Aug
P5 · Mech & Public Health
17 Aug – 18 Sep
P6 · Electrical
24 Aug – 16 Sep
P7 · BMS / Controls (PC Sum)
14 Sep – 30 Sep
P8 · Testing & Commissioning
21 Sep – 06 Oct
P9 · Changeover & Handover
05 Oct – 09 Oct
Major Milestones
M1 · ◆
11 May 26
Letter of Intent
M2 · ◆
29 May 26
IDEAL Order Lock-in
M3 · ◆
17 Jul 26
LARC Cert. of Reocc.
M4 · ◆
17 Aug 26
Heavy-Plant Lift-In
M5 · ◆
22 Sep 26
Hydraulic Test Pass
M6 · ◆
5 Oct 26
Witness Commission.
M7 · ◆
5 Oct 26
Permanent Cut-Over
M8 · ◆
9 Oct 26
PRACTICAL COMPLETION
M9 · ◆
1 Feb 27
Seasonal Commission.
Critical path: M2 (IDEAL order, 29 May) → M3 (LARC Cert. of Reocc., 17 Jul) → M4 (Heavy-plant lift-in, 17 Aug) → P5/P6 mech/electrical → P7 BMS → P8 commissioning → M6 (witness comm., 5 Oct) → M7 (cut-over, 5 Oct) → M8 (PC, 9 Oct).
75-ACTIVITY WORKING-LEVEL PROGRAMME

Detailed Programme

Working-level activity Gantt with logic, dates, predecessors and resources. Each phase below contains its full activity list. Phases 0–2 are open by default; click any phase to expand or collapse.

Milestone
Hold-Point (inspect-and-approve)
FS Finish-to-Start logic
FF Finish-to-Finish logic
PHASE 0
PRE-CONSTRUCTION
10 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
0.1 Letter of Intent / contract award (precedence to Built AI) 1 11 May 26 11 May 26 Grimshaw & Bolt / Client
0.2 Pre-construction submittals — RAMS, COSHH, CDP design 9 12 May 26 22 May 26 0.1 FS Built AI PM
0.3 IDEAL EVO Max 2 cascade order placement (pre 31-May to lock pricing) 1 29 May 26 29 May 26 0.2 FS Built AI Procurement
0.4 Stokvis DHW (×2) + heating PHE order placement 1 29 May 26 29 May 26 0.2 FS Built AI Procurement
0.5 Thermal store (×3) order placement 1 29 May 26 29 May 26 0.2 FS Built AI Procurement
0.6 Twin-wall flue 4-hr FR system order placement 1 29 May 26 29 May 26 0.2 FS Built AI Procurement
0.7 Albion Valves take-off order via SBS Cambridge 1 29 May 26 29 May 26 0.2 FS Built AI Procurement
0.8 LARC asbestos removal works (GB-coordinated, precedence-only) 15 29 Jun 26 17 Jul 26 LARC (by others)
0.9 GB temporary boiler installation + commissioning (GB-led) 10 29 Jun 26 10 Jul 26 Grimshaw & Bolt
0.10 MILESTONE: Cert of Reoccupation issued by LARC 17 Jul 26 17 Jul 26 0.8 FF LARC / GB
PHASE 1
MOBILISATION
3 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
1.1 GB-administered site induction + RAMS submission 1 29 Jun 26 29 Jun 26 0.2 FS Built AI site team
1.2 Site setup integration with GB PC establishment 2 30 Jun 26 01 Jul 26 1.1 FS Built AI Site Supervisor
1.3 Stage 4a confirmatory surveys (dimensional, gas, LV, flue, B2 Risk-Tracker) 5 06 Jul 26 10 Jul 26 1.2 FS Built AI PM + Eng
PHASE 2
STRIP-OUT
7 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
2.1 Hydraulic isolation, drain-down + cap-off retained tie-ins 2 20 Jul 26 21 Jul 26 0.10 FS, 0.9 FS Built AI Mech
2.2 Remove 5 × Wessex atmospheric cast-iron boilers 5 22 Jul 26 28 Jul 26 2.1 FS Built AI Mech (×3)
2.3 Remove 2 × Hamworthy DR-LP 60 G + DR-LA 95 G DHW generators 2 29 Jul 26 30 Jul 26 2.2 FS Built AI Mech (×2)
2.4 Remove 2 × Nalco buffer / dosing vessels 1 31 Jul 26 31 Jul 26 2.3 FS Built AI Mech (×2)
2.5 Remove existing MCP and associated control wiring 1 03 Aug 26 03 Aug 26 2.4 FS Built AI Elec
2.6 Strip-out redundant pipework, valves, supports, insulation 4 04 Aug 26 07 Aug 26 2.5 FS Built AI Mech (×3)
2.7 Disposal via GB waste route (run-time activity) 15 20 Jul 26 07 Aug 26 2.1 SS GB / Built AI
PHASE 3
BUILDERS' WORK
7 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
3.1 Penetrations + EI 120 fire-stopping (BS 9999) 5 27 Jul 26 31 Jul 26 2.2 SS Built AI BWIC
3.2 New concrete plinth formation × 6 (cascade, 3-vessel TS, DHW PHEs, htg PHE, PressDS, BTBS) 5 03 Aug 26 07 Aug 26 2.6 SS Built AI BWIC
3.3 Skylight remove + store (preparation for lift-in) 1 10 Aug 26 10 Aug 26 3.2 FS Built AI BWIC
3.4 Sump pit formation (400 × 400 × 300 mm, ductile-iron grate) 2 11 Aug 26 12 Aug 26 3.3 FS Built AI BWIC
3.5 Chimney top repointing (lime mortar, scaffold-dependent) 3 10 Aug 26 12 Aug 26 3.2 FS Built AI BWIC
3.6 Services diversion below skylight zone 1 13 Aug 26 13 Aug 26 3.4 FS Built AI Mech
3.7 Plinth concrete cure to lift-in strength 2 13 Aug 26 14 Aug 26 3.2 FS -
PHASE 4
LIFT-IN
6 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
4.1 Lift-in IDEAL EVO Max 2 cascade (×3 boilers + cascade kit) 1 17 Aug 26 17 Aug 26 3.3 FS, 3.7 FS Crane + Built AI Mech
4.2 Lift-in 3 × 2,000 L vertical thermal stores + steel support frame 1 18 Aug 26 18 Aug 26 4.1 FS Crane + Built AI Mech
4.3 Lift-in 2 × Stokvis Econoplate 700 kW DHW PHE skids 1 19 Aug 26 19 Aug 26 4.2 FS Crane + Built AI Mech
4.4 Lift-in Stokvis 250 kW heating PHE skid + Flamco PressDS units (×2) 1 20 Aug 26 20 Aug 26 4.3 FS Crane + Built AI Mech
4.5 Lift-in Arrow Valves Boost-A-Break Tank Set 1 21 Aug 26 21 Aug 26 4.4 FS Built AI Mech
4.6 Skylight reinstate + EPDM gasket + lead flashings + hose test 1 21 Aug 26 21 Aug 26 4.5 FS Built AI BWIC
PHASE 5
MECH & PH
10 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
5.1 Primary LTHW pipework — header to thermal store + boiler interconnect 15 17 Aug 26 04 Sep 26 4.1 SS Built AI Mech (×4)
5.2 DHW primary, secondary + recirculation pipework 12 24 Aug 26 09 Sep 26 5.1 SS, 4.3 FS Built AI Mech (×3)
5.3 Gas pipework (BS EN 10255) + Gas Safety Panel installation 9 24 Aug 26 04 Sep 26 5.1 SS Built AI Gas Safe
5.4 Twin-wall 4-hr FR flue installation + smoke test 10 17 Aug 26 28 Aug 26 4.1 FS Specialist flue contractor
5.5 Pump installation — Grundfos MAGNA3 D / MAGNA1 / AP50 5 07 Sep 26 11 Sep 26 5.1 FS Built AI Mech (×2)
5.6 Pressurisation units + expansion vessels (425L × 2 + 110L × 3) 3 07 Sep 26 09 Sep 26 5.1 FS Built AI Mech (×2)
5.7 Cold-water booster (BTBS) tie-in + WRAS Cat 5 backflow prevention 2 10 Sep 26 11 Sep 26 5.2 FS Built AI Mech
5.8 Albion valve schedule install (butterflies, strainers, NRVs, comm sets) 12 24 Aug 26 09 Sep 26 5.1 SS Built AI Mech (×2)
5.9 Insulation (F7 series) — 40mm phenolic foam + valve jackets 5 14 Sep 26 18 Sep 26 5.1 FS, 5.2 FS, 5.3 FS, 5.8 FS Built AI Insulation Sub
5.10 Condensate neutralisation + PH drainage to sump 4 01 Sep 26 04 Sep 26 3.4 FS Built AI Mech
PHASE 6
ELECTRICAL
8 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
6.1 Sub-main installation from Malthouse Block main LV panel 3 24 Aug 26 26 Aug 26 4.1 FS Built AI Elec (×2)
6.2 Schneider Acti 9 12-Way 125 A TP&N DB installation 2 27 Aug 26 28 Aug 26 6.1 FS Built AI Elec
6.3 Containment (tray/basket/conduit) + cabling + terminations 9 01 Sep 26 11 Sep 26 6.2 FS Built AI Elec (×3)
6.4 Final connections to plant (G4 series, 1 hr per item refined) 3 14 Sep 26 16 Sep 26 5.5 FS, 5.6 FS, 6.3 FS Built AI Elec
6.5 LED task + BS 5266 emergency lighting installation 4 01 Sep 26 04 Sep 26 6.2 FS Built AI Elec
6.6 Bonding + earthing per BS 7671 Section 544 2 14 Sep 26 15 Sep 26 6.3 FS Built AI Elec
6.7 Apollo addressable fire-alarm loop extension (sub-let to existing maintainer) 3 07 Sep 26 09 Sep 26 6.3 SS Existing FA maintainer (sub-let)
6.8 Latching E-stop + small power + spurs 2 07 Sep 26 08 Sep 26 6.3 SS Built AI Elec
PHASE 7
BMS (PC SUM)
5 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
7.1 MCP enclosure installation 2 14 Sep 26 15 Sep 26 6.4 FS BMS Specialist (PC Sum)
7.2 BMS outstation install (54-point I/O — 32 AI + 3 AO + 14 DI + 5 DO) 3 16 Sep 26 18 Sep 26 7.1 FS BMS Specialist (PC Sum)
7.3 Field sensors (PT1000 pockets, DP, external) + control valve install 3 21 Sep 26 23 Sep 26 7.2 FS BMS Specialist (PC Sum)
7.4 BMS programming + Satchwell head-end integration 5 21 Sep 26 25 Sep 26 7.2 FS BMS Specialist (PC Sum)
7.5 BMS Site Acceptance Testing + cause-and-effect verification 3 28 Sep 26 30 Sep 26 7.4 FS, 7.3 FS BMS Specialist (PC Sum)
PHASE 8
TESTING & COMMISSIONING
9 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
8.1 Hydraulic pressure test (1.5 × WP, 2 hr hold) 2 21 Sep 26 22 Sep 26 5.9 FS Built AI Mech
8.2 BSRIA BG 29/2020 chemical clean, flush + dose (with UKAS lab samples) 6 23 Sep 26 30 Sep 26 8.1 FS Built AI + UKAS Lab
8.3 Gas tightness + purge per IGEM/UP/1 2 21 Sep 26 22 Sep 26 5.3 FS Built AI Gas Safe
8.4 Electrical inspection + test per BS 7671 Part 6 3 21 Sep 26 23 Sep 26 6.4 FS, 6.6 FS Built AI NICEIC
8.5 OEM commissioning — IDEAL agent attendance (4 wk notice required) 2 28 Sep 26 29 Sep 26 8.2 FS IDEAL OEM
8.6 OEM commissioning — Stokvis agent attendance 2 29 Sep 26 30 Sep 26 8.2 FS Stokvis OEM
8.7 OEM commissioning — Flamco + Arrow agents 1 01 Oct 26 01 Oct 26 8.5 FS Flamco / Arrow OEM
8.8 Hydraulic balancing via FODRVs + commissioning sets 2 01 Oct 26 02 Oct 26 8.5 FS Built AI Comm Mgr
8.9 Witness commissioning session (10 WD notice) 2 05 Oct 26 06 Oct 26 8.8 FS, 7.5 FS Employer + Built AI
PHASE 9
HANDOVER
7 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
9.1 Cut-over from GB temp boiler to new permanent cascade 1 05 Oct 26 05 Oct 26 8.9 SS Built AI + GB
9.2 GB de-mobilises temporary boiler plant (GB-led) 3 06 Oct 26 08 Oct 26 9.1 FS Grimshaw & Bolt
9.3 As-built documentation pack (CAD + PDF) 4 05 Oct 26 08 Oct 26 8.9 SS Built AI PM
9.4 BSRIA BG 1/2007 O&M manuals — final issue 2 07 Oct 26 08 Oct 26 9.3 SS Built AI PM
9.5 Kettlewick College Estates training (2 × 4-hour sessions) 2 07 Oct 26 08 Oct 26 8.9 FS Built AI PM + Comm
9.6 Joint handover inspection + snagging 1 09 Oct 26 09 Oct 26 9.4 FS, 9.5 FS Employer + GB + Built AI
9.7 MILESTONE: PRACTICAL COMPLETION 09 Oct 26 09 Oct 26 9.6 FS Employer / GB
PHASE 10
POST-PC
2 activities
ID Activity Dur (WD) Start Finish Pred. Resource MS / HP
10.1 Defects Liability Period (12 months from PC) 260 12 Oct 26 08 Oct 27 9.7 FS Built AI / Employer
10.2 BMS summer / seasonal commissioning revisit 1 01 Feb 27 01 Feb 27 9.7 FS BMS Specialist (PC Sum)
CRITICAL DEPENDENCIES

Key Interfaces & Notice Periods

Single-page register of milestones, hold-points, and critical interfaces with other parties. All notice periods are minimum lead times — earlier notification preferred where possible.

1. Major Milestones
IDDescriptionDateResponsibleNoticeDeliverable
M1Letter of Intent / Contract Award11 May 26GB / ClientTriggers procurement
M2IDEAL Cascade Order Placement29 May 26Built AI ProcurementLocks pre-31-May IDEAL price
M3Cert. of Reoccupation issued by LARC17 Jul 26LARC (by others)Confirm at week-ofPre-condition for strip-out
M4Heavy-Plant Lift-In begins17 Aug 26Built AI Mech + Crane2 wks crane bookingPlant in position
M5Hydraulic Pressure Test complete22 Sep 26Built AI MechPressure-test certificate
M6Witness Commissioning Session5 Oct 26Employer + Built AI10 WDWitness sign-off
M7Cut-over to new permanent cascade5 Oct 26Built AI + GB APPermit-to-WorkHeat continuity confirmed
M8PRACTICAL COMPLETION9 Oct 26Employer / GBPC Certificate; DLP commences
M9Seasonal commissioning revisit1 Feb 27BMS Specialist (PC Sum)Seasonal report to Employer
2. Quality Hold-Points (Inspect-and-Approve)
RefDescriptionDateResponsibleNoticeDeliverable
HP1Stage 4a confirmatory survey verification report10 Jul 26Built AI PM + EngVerification report to CA
HP2Plinth concrete cure to lift-in strength14 Aug 26Built AI BWIC7-day cure testConcrete-strength record
HP3Skylight reinstate hose test21 Aug 26Built AI BWICHose-test record
HP4LV sub-main installation — AP Electrical attendance26 Aug 26Built AI Elec + AP1 wkAP sign-off
HP5Gas pipework — Gas Safe certification4 Sep 26Built AI Gas SafeGas Safe certificate
HP6Flue smoke test28 Aug 26Specialist flue contractorSmoke-test report
HP7Apollo fire alarm cause-and-effect witness test9 Sep 26Existing FA maintainer1 wkC&E witness sign-off
HP8BMS Site Acceptance Testing30 Sep 26BMS Specialist (PC Sum)SAT records pack
HP9Hydraulic pressure test22 Sep 26Built AI MechPressure-test certificate
HP10Chemical clean + UKAS lab samples30 Sep 26Built AI + UKAS LabPre/post sample analysis
HP11Gas tightness + purge per IGEM/UP/122 Sep 26Built AI Gas SafeGas Safe purge record
HP12Electrical inspection + test (BS 7671 Pt 6)23 Sep 26Built AI NICEICEIC + Schedule of Test Results
HP13OEM commissioning — IDEAL28 Sep 26IDEAL OEM4 weeksCascade commissioning record
HP14OEM commissioning — Stokvis29 Sep 26Stokvis OEM2 weeksPHE duty/flow/temp report
HP15Kettlewick Estates training (2 × 4 hr)7 Oct 26Built AI PM + Comm1 wkTraining records + video
HP16Joint handover inspection + snagging9 Oct 26Employer + GB + Built AI1 wkSnagging list
3. Critical Interfaces with Other Parties
RefInterfaceWindowOther PartyBuilt AI ActionRisk if Slipped
I1GB Construction Phase Plan + Site RulesPre-mobilisationGrimshaw & Bolt (PC)Issue Built AI RAMS / COSHH / CDP designCannot mobilise to site
I2GB-coordinated LARC asbestos works29 Jun – 17 Jul 26GB / LARCConfirm Cert. of Reoccupation timingStrip-out cannot start
I3GB-led temporary boiler installation29 Jun – 10 Jul 26Grimshaw & BoltDefine hydraulic / electrical / BMS interface pointsNo heat continuity
I4AP Heating Shutdown Permit-to-WorkEach cut-overKettlewick APSubmit permit 5 WD pre-shutdownCannot disconnect existing
I5AP Electrical sub-main attendance26 Aug 26Kettlewick AP1 wk notice; co-ordinate isolationLV install delayed
I6BMS Specialist appointment (PC Sum)Pre-Week 10GB / SpecialistProvide interface points + design infoBMS slip pushes commissioning
I7Existing FA maintainer (cause & effect)9 Sep 26Existing FA contractorSub-let; coordinate witness testFA integration not certified
I8OEM commissioning agentsWeeks 12–13IDEAL / Stokvis / Flamco / ArrowBook attendances 2–4 wks aheadWitness commissioning slips
I9Witness commissioning — Employer5–6 Oct 26Employer / CA10 WD noticePC at risk
I10GB de-mobilisation of temp boiler6–8 Oct 26Grimshaw & BoltCoordinate cut-over sequencingPermanent plant cannot run live

Notice Periods — Quick Reference

TriggerNoticeTo WhomSource
IDEAL OEM commissioning attendance4 weeksIDEAL CommercialTender §8.4 §10.3
Stokvis / Flamco / Arrow OEM attendance2 weeksRespective OEMTender §8.4 §10.3
Witness commissioning session10 WDEmployer / CATender §8.4 §10.4
Shutdown Permit-to-Work5 WDKettlewick APKettlewick Safety Rules
Crane / lifting attendance (lift-in)2 weeksCrane contractorIndustry standard
Existing FA maintainer (C&E witness)1 weekMaintainer's officeSub-let agreement
BMS specialist appointment (PC Sum)Pre-Week 10Grimshaw & BoltPC Sum drawdown
FOR PROJECT TOOLS

MS Project Import

The full programme is also issued as native MS Project import data via the source workbook. Use the MS Project Import tab in the Excel workbook for direct import into MS Project, P6 Primavera, Asta Powerproject, or any project tool that accepts native MS Project field columns.

How to Import into MS Project

Native MS Project field structure — direct import compatible

1

Open MS Project

File → Open → Select the source .xlsx workbook

2

Choose Sheet

Select the MS Project Import tab when prompted

3

Map Fields

MS Project auto-maps the native field column headers below

4

Import & Verify

Schedule recalculates from logic; review against milestones and PC date

Native MS Project Fields Provided

ID
Task Name
Outline Level
WBS
Duration
Start
Finish
Predecessors
Resource Names
Milestone
Notes
Compatibility: This data is also compatible with Asta Powerproject, Oracle P6 Primavera, Smartsheet, Microsoft Planner and any tool that accepts MS Project XML or CSV import. For non-MS-Project tools, export the workbook tab to CSV first.

Programme Statistics

PHASES
11
P0 to P10
ACTIVITIES
75
Working level
MILESTONES
9
M1 to M9
HOLD-POINTS
16
HP1 to HP16
BUILT WITH BIDROOM IN A BOX™
PRODUCTION NOTE

Built with
Bidroom in a Box™

AI-augmented document production for the construction industry

This document was produced using Built AI's Bidroom in a Box™ workflow pack — an AI-augmented system for sub-contractors that transforms tender data, programmes and operational plans into polished, branded, audit-ready deliverables in a fraction of the time required by traditional methods.

DOCUMENTS PRODUCED
5
VISUALISATIONS GENERATED
12
TIME VS MANUAL
−85%

What makes this different

  • Consistent across the document familyall five files share a single source of truth for client/site data.
  • Visualisations generated, not drawncharts, dashboards and schematics are programmatic outputs.
  • Audit-readyevery figure is traceable back to the underlying BoQ or programme.
  • Iteration-readychange a price, regenerate the pack.
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd ● BUILT AI
Part of the Bidroom in a Box™ pack:
CS TLP PDP BoQ PRG
End of pack
Back to the Bidroom Pack