The Bid Room
Bidroom in a Box™Pack 01 / 06 · Client deliverable
Programme · the 14-week work schedule

The B99 Malthouse Block programme

The working-level baseline schedule submitted with the tender. It sets the 14-week construction window, the phase logic, the milestones and hold-points, and the notice periods the other parties depend on. It is aligned to the tender letter, the priced Bill of Quantities and the delivery plan, and integrates with the Principal Contractor's construction phase plan.

Prepared for
Grimshaw & Bolt Ltd
Site
Kettlewick College, Somerset
Reference
ITT KW-2026-4471
Shift pattern
Mon to Fri, single shift
Prepared by
BuiltAI Intelligence Ltd
Revision
Rev 1

Illustrative example: fictional project and parties.

14 weeksOn-site duration
6 Jul 2026Construction start
9 Oct 2026Practical Completion
16Quality hold-points
BuiltAI Intelligence Ltd · built-ai.ioB99-PRG · Rev 1
01Basis

Planning assumptions and basis

The programme runs for 14 weeks on-site, from Monday 6 July to Friday 9 October 2026, within the Kettlewick College summer-term stand-down. Work is single-shift, Monday to Friday, 07:30 to 17:00. The two summer bank holidays are excluded. Long-lead orders are placed on award to hold the quoted pricing and to protect the Phase 4 lift-in date.

AssumptionBasis
Construction window6 July to 9 October 2026, summer stand-down
Working hoursMon to Fri, 07:30 to 17:00, single shift
Bank holidays excluded25 May and 31 August 2026
Enabling works by othersLARC asbestos removal and PC temporary boiler, late June
BMS specialistAppointed under the Prime Cost Sum on PC instruction
Aligned documentsTender letter, priced BoQ and delivery plan, all Rev 1
02Phases

Phase programme

The works run in ten phases across the window, plus the post-completion defects period. Phase 4 is the single concentrated heavy-plant lift-in through the skylight; the mechanical and electrical phases then run in parallel.

PhaseWorkWindow
P0Pre-construction and procurementJune to 17 Jul
P1Mobilisation and Stage 4a surveys29 Jun to 10 Jul
P2Strip-out and removal20 Jul to 7 Aug
P3Builders' work in connection27 Jul to 14 Aug
P4Heavy-plant lift-in17 to 21 Aug
P5Mechanical and public health17 Aug to 18 Sep
P6Electrical services24 Aug to 16 Sep
P7BMS and controls, Prime Cost Sum14 to 30 Sep
P8Testing and commissioning21 Sep to 6 Oct
P9Changeover and handover5 to 9 Oct

Phase 10, the 12-month defects liability period, runs from 12 October 2026, with a seasonal commissioning revisit in February 2027.

03Milestones

Milestones and critical path

Nine milestones anchor the schedule, supported by 16 quality hold-points across the phases. The critical path runs through procurement, the asbestos clearance, the lift-in and commissioning.

RefMilestoneDate
M1Letter of Intent, contract awardearly June 2026
M2Long-lead order placementmid June 2026
M3LARC Certificate of Reoccupation17 Jul 2026
M4Heavy-plant lift-in begins17 Aug 2026
M5Hydraulic pressure test pass22 Sep 2026
M6Witness commissioning session5 Oct 2026
M7Permanent cut-over5 Oct 2026
M8Practical Completion9 Oct 2026
M9Seasonal commissioning revisitFeb 2027
Critical path

Order placement drives the Certificate of Reoccupation, which drives the lift-in, which drives the mechanical, electrical and BMS phases, which drive commissioning, the witness session, cut-over and Practical Completion. A slip on any of these moves the completion date.

04Interfaces

Notice periods and interfaces

The programme depends on notice being given to other parties for their attendances. These are minimum lead times; earlier notice is preferred where it can be given. They are stated here so the Principal Contractor and the Employer can plan the shared hold-points.

TriggerTo whomNotice
IDEAL commissioning attendanceIDEAL4 weeks
Stokvis, Flamco, Arrow attendanceRespective OEM2 weeks
Witness commissioning sessionEmployer and CA10 WD
Shutdown permit-to-workKettlewick AP5 WD
Crane and lifting attendanceCrane contractor2 weeks

The full working-level schedule of 75 activities, across 11 phases with 9 milestones and 16 hold-points, is issued as a native project workbook for direct import.

Reference B99-PRG · Rev 1Completion 9 October 2026Duration 14 weeks on-site

End of pack