Complete maintenance history for Aldgate Central Library roof (NE section). 3 calls in 7 months, escalating costs, root-cause analysis, and permanent repair recommendation.
Complete maintenance history for the northeast roof section. 3 reactive calls in 7 months, escalating in severity. Pattern: temporary repairs failing, root cause unresolved, costs accumulating.
| Ticket | Date | Fault | Action | Engineer | Cost | Outcome |
|---|---|---|---|---|---|---|
| TKT-01204 | 14 Oct 25 | Minor leak, NE corner | Temporary felt patch externally | S. Ahmed | £120 | Temp fix |
| TKT-02891 | 22 Jan 26 | Leak recurrence after heavy rain | Silicone sealant to flashing lap joint | D. Okonkwo | £85 | Temp fix |
| TKT-03847 | 13 May 26 | Active ingress — saturated tiles, pooling | Flashing tape ext. + ceiling tiles int. | D. Okonkwo | £161 | Temp fix |
Ref: ALD-AHR-LIB001-ROOF-NE · Period: May 2026