Dispatch Desk · Defence - Stage 06 (period roll-up + DDP defence) · Worked example Aldgate Borough Council · 42 buildings · 180 calls/mo · TKT-2026-03847 threaded · May 2026 (Month 18) · SLA 96.7% · DDP defended £800
← Dispatch Desk
Pack 06 / 09 · The Dispatch Desk™
THE DISPATCH DESK™STAGE 06 · THE SCORE

The Score

Performance Reporting & Deductions Defence
The monthly score. SLA performance measured, breaches root-caused, deductions defended or accepted. The report that keeps the contract healthy — and protects your margin when the client's QS comes looking.
Client
Aldgate Borough Council · 42 sites
Contract
NEC4 TSC · £2.4m/year
Period
Month 18 · May 2026
built-ai.io© 2026 Built AI LtdBUILT AI
DD WORKFLOW1The Bell2The Triage3The Brief4The Roll5The Stamp
6The Score
SLA PERFORMANCE — MAY 2026

96.7% Overall — 175 of 180 Within SLA

Monthly SLA performance across all 4 priority levels for the Aldgate Borough Council contract. Contract target is 95% — exceeded by 1.7 percentage points. 5 breaches, all root-caused, all documented.

P1 EMERGENCY
100%
8/8 met · 0 breaches
Target: 2hr/4hr
P2 URGENT
94.1%
32/34 met · 2 breaches
Target: 4hr/8hr
P3 ROUTINE
96.9%
93/96 met · 3 breaches
Target: 24hr/5d
P4 PLANNED
100%
42/42 met · 0 breaches
Target: 48hr/20d
96.7%
OVERALL COMPLIANCE
95.0%
CONTRACT TARGET
+1.7pp
ABOVE TARGET
5
TOTAL BREACHES
BREACH ANALYSIS

5 Breaches — Root Causes Documented

TicketSitePriBreach TypeRoot CauseDeductionStatus
TKT-03821Civic OfficesP2Response (4h22m vs 4h)A57 road closure — diversion added 30 mins to travel£250Accepted
TKT-03829Parkside LibraryP2Response (4h45m vs 4h)Engineer on site at 3h10m — keyholder 45 mins late£250Defending
TKT-03836Aldgate CCP3Fix (5d 4h vs 5d)Parts delay — specialist valve 3-day lead time from supplier£100Accepted
TKT-03861Borough HallP3Fix (6d vs 5d)Initial diagnosis incorrect — follow-up visit needed£100Accepted
TKT-03872Riverside LeisureP3Response (26h vs 24h)All engineers committed on P1/P2 calls — queue delay£100Accepted
TOTAL DEDUCTION EXPOSURE£800

Accepted: £550 (4 breaches). Defending: £250 (TKT-03829 — keyholder delay, defence pack submitted 16 May).

DEDUCTIONS DEFENCE — TKT-03829

Keyholder Delay — Defence in Progress

TKT-2026-03829 Deduction Defence

DEDUCTION
£250 — P2 response breach (4h45m vs 4h target)
DEFENCE
Keyholder delay. Engineer D. Okonkwo arrived at Parkside Library at 3h10m after call receipt — within the 4hr response target. However, the caretaker (keyholder) did not arrive until 45 minutes later. The SLA response clock should start from the point access was available, not from call receipt, per Contract Schedule 4, clause 8.3(b): "where access is dependent on a third party, the SLA clock pauses until access is provided."
EVIDENCE
Engineer GPS arrival timestamp (3h10m) · Engineer app log showing "waiting for keyholder" status at 3h10m · Caretaker arrival logged at 3h55m (45-min wait) · Call log to caretaker at 3h15m (no answer) · Second call at 3h30m (answered, confirmed en route) · Photo of locked building entrance at 3h12m
STATUS
Submitted to H. Marsden (Aldgate BC contract manager) 16 May. Response pending. If accepted: £250 deduction reversed. If rejected: escalation to NEC4 TSC dispute resolution procedure.
TKT-2026-03847 — FINAL SLA RECORD

Library Roof Leak — Scored and Closed

TKT-2026-03847 SLA Performance Record

RESPONSE SLA
MET — Target: 4 hours. Actual: 1hr 24mins. Engineer on site at 10:38 (call received 09:14).
FIX SLA
MET — Target: 8 hours. Actual: 3hr 36mins. Temporary repair completed and water ingress stopped by 12:50.
DEDUCTION
NONE — both response and fix SLA met. No deduction exposure.
FOLLOW-UP
WO-2026-00847 raised for permanent lead flashing replacement. Subject to listed building consent. Tracked in follow-up register — target completion: 8 weeks from consent.
EVIDENCE CHAIN
Complete: call recording (09:14) → ticket created (09:14) → triage P2 confirmed (09:16) → dispatch to D. Okonkwo (09:18) → acknowledge (09:22) → en route (10:12) → arrival GPS (10:38) → 6 photos uploaded → diagnosis recorded → completion record → customer signature (13:12) → SLA timestamps verified → ticket closed (13:15).
TOTAL COST
Labour: £131.50 · Materials: £29.60 · Total: £161.10. Cumulative cost on this roof section (3 calls): £531.10. Estimated permanent repair: £1,800.
STAGE 06 GATE — THE SCORE

Scored. Defended. Cycle Complete.

SLA compliance calculated per priority level
Each breach root-caused and documented
Deductions accepted with reasoning or defended with evidence
Defence packs compiled with evidence chains from earlier stages
Follow-up works orders tracked in register
Evidence chain verified for every ticket
Monthly performance report compiled for client
TKT-03847 thread closed — complete from Bell to Score

The Dispatch Desk cycle is complete. The bell rang. The score settled. Every ticket between — captured, classified, dispatched, completed, evidenced and reported. The monthly pack goes to Aldgate BC's contract manager with the same data the internal team uses — no surprises.

THE DISPATCH DESK™ — COMPLETE

The bell rings. The score settles. Every ticket between.

Six stages. One ticket tracked from intake to performance report. 180 calls, 42 sites, 4 priority levels. 96.7% SLA compliance. 1 deduction defended. Every timestamp evidenced, every diagnosis documented, every follow-up tracked. That's what dispatch looks like when it's systematised.
CALLS
180
SLA MET
96.7%
DEFENDED
£250
FIRST FIX
78%
built-ai.io · The Dispatch Desk™ · The Score™ · Stage 06 © 2026 Built AI Ltd