The Dispatch Desk
The Dispatch Desk™Stage 06 of 6 · Internal workflow
Defence · performance reporting and deductions defence

Report the period, defend the margin

Rolling the month into the reports the client and the desk actually read - calculated compliance against target, recorded breaches with stated causes and unresolved clock bases flagged for review, and deductions accepted with reasoning or disputed pending review.

Client
Aldgate Borough Council · 42 buildings
Managed by
Sentinel FM Ltd · via BuiltAI
Contract
NEC4 Term Service Contract · £2.4m/year
Scope
Reactive and planned maintenance
Period
1 to 31 May 2026 · Month 18
Reference
ALD-DSP-S06

Illustrative example: fictional project and parties.

97.2%Calculated May SLA · 175/180 · target 95.0%
180Reactive calls, May 2026
£800Deduction exposure · £550 accepted
£250Disputed, still active (TKT-2026-03829)
BuiltAI Intelligence Ltd · built-ai.ioALD-DSP-S06 · Stage 06
01Purpose

Turning the month's tickets into the report

The Dispatch Desk™ carries one ticket from the first call to the closing report. Defence is the last stage: the month's reactive calls are rolled up and compliance is calculated against the contract target. The monthly pack retains the recorded breaches and their stated causes, flags unresolved clock bases for review, and distinguishes accepted deductions from disputed items pending a decision. It produces the pack the client's contract manager reads, from the data the desk used all month.

This period - May 2026, Month 18 - covers 180 reactive calls across 42 buildings, managed by Sentinel FM Ltd via BuiltAI. Planned maintenance ran alongside the reactive book.

02Score

SLA compliance for the period

The illustrative ALD-RCL-M18 register records 175 SLA-met calls out of 180 for May, giving calculated compliance of 97.2% (one decimal place) against the 95.0% target. The disputed ticket remains among the five recorded breaches pending reconciliation and a recorded decision. All eight P1 emergencies were responded to inside the one-hour target.

Calculated SLA · target 95.0%
97.2%
PPM completed · 103 of 108
95.4%
P1 · Emergency8

One-hour response target. 0 breaches.

P2 · Urgent34

Four-hour response target. 2 breaches.

P3 · Routine96

24-hour response target. 3 breaches.

P4 · Planned42

48-hour response target. 0 breaches.

03Register

The five recorded breaches, including one pending clock reconciliation

Every recorded SLA breach in the period, with its stated cause and deduction. Four were accepted with documented reasoning; one is disputed and its response/fix clock reconciliation remains pending.

TicketSitePriBreach and root causeDeductionStatus
TKT-2026-03821Civic OfficesP2Response 4h 22m vs 4hA57 road closure; diversion added 30 minutes to travel£250Accepted
TKT-2026-03829Parkside LibraryP2Client-recorded response 4h 45m vs 4hArrival recorded at 3h 10m; keyholder wait 45 minutes; clock reconciliation pending£250Disputed
TKT-2026-03836Aldgate Central LibraryP3Fix 5d 4h vs 5dSpecialist valve on a 3-day supplier lead time£100Accepted
TKT-2026-03861Borough HallP3Fix 6d vs 5dInitial diagnosis incorrect; a follow-up visit was needed£100Accepted
TKT-2026-03872Riverside Leisure CentreP3Response 26h vs 24hAll engineers committed on P1 and P2 calls; queue delay£100Accepted
Total deduction exposure5 breaches£800£550 accepted · £250 disputed

Site check pending for TKT-2026-03836: this Reporting record lists Aldgate Central Library; the SLA report lists Westfield Community Centre. The P3 timings, £100 accepted deduction and raw site labels are retained; the site has not been reconciled.

04Defence

TKT-2026-03829 - the deduction under defence

One recorded breach is disputed on a keyholder-access basis. The response and fix clock records remain unreconciled, so this example does not establish a compliant response or an accepted reversal.

Ticket
TKT-2026-03829 · P2 urgent · Parkside Library boiler.
Deduction
£250 - the client records the response as 4h 45m, exceeding the four-hour P2 target by 45 minutes.
Defence · pending clock reconciliation
GPS records arrival at 3h 10m from the call and a further 45-minute wait for the keyholder. The quoted Schedule 4, clause 8.3(b) is the stated access-pause basis for review. Those entries do not currently reconcile the client-recorded 4h 45m response or the register's 6h 20m fix with the Defence Pack timeline. Raw times are retained; no final compliance or deduction decision is inferred.
Evidence
GPS arrival timestamp (3h 10m); engineer app status "waiting for keyholder" (3h 10m); caretaker call log (3h 15m no answer, 3h 30m answered); caretaker on site at 3h 55m; photograph of the locked entrance (3h 12m).
Status
Submitted to H. Marsden, Aldgate BC contract manager, on 16 May 2026. Response pending. If accepted, the £250 is reversed; if rejected, it escalates to the NEC4 TSC dispute resolution procedure.
Disputed - response pending

The £250 stays disputed while the clock basis is reconciled and Aldgate BC's response is pending. The other four breaches, £550, are accepted as valid. Together they form the period's £800 deduction exposure; accepted deductions are not successful defences or recovered savings.

05Thread

The threaded ticket, scored and closed

TKT-2026-03847 - the recurring roof-valley leak at Aldgate Central Library, three calls in seven months - ran through all six stages. The register records Met and no deduction, with a works order raised for the permanent repair; the achieved fix-clock basis remains unreconciled.

Response
Met. 1h 24m against the four-hour P2 response target.
Fix
Recorded Met, 6h 36m against the eight-hour target; achieved fix-clock basis unreconciled.
Deduction
Recorded None; retained without an independent fix-compliance conclusion.
Follow-up
WO-2026-00847 raised for the permanent repair to the north-east roof valley, subject to listed-building consent.
Cost
Labour £131.50 and materials £29.60, total £161.10. Cumulative on the roof section across three calls, £366; estimated permanent repair, £1,800.

Response is recorded at 1h 24m against the four-hour target. Dispatch shows 6h 36m as time remaining at the 10:38 arrival, not an achieved fix duration. Raw fix, Met and no-deduction states are retained; no independent fix-compliance conclusion is established.

06Stage gate

The month's reports, and the gate

Defence produces three documents from one dataset. The client sees the SLA report; the desk runs on the weekly report; the disputed deduction travels in its own defence pack.

SLA Performance Report

Monthly compliance against target, by priority, with the breach register and deduction position. Issued to the contract manager.

Weekly Performance Report

The operational cut - open tickets, week-by-week response and first-fix - used to run the desk between monthly reports.

Deductions Defence Pack

The per-breach defence. TKT-2026-03829 travels with its clause basis and evidence chain.

Review required before issue

The checks below are requirements before the monthly pack leaves the desk. TKT-2026-03829's response/fix clock reconciliation remains open in this example; the gate is not shown as complete.

  • Illustrative SLA calculation: 175 recorded SLA-met calls out of 180 gives 97.2%, against the 95.0% target; the disputed ticket remains in the recorded five breaches.
  • Each recorded breach reviewed; unresolved clock bases flagged before issue.
  • Each deduction accepted with reasoning or defended with evidence.
  • Planned maintenance reconciled: 103 of 108 PPM tasks.
Reference ALD-DSP-S06Period May 2026 · Month 18Prepared by Sentinel FM Ltd (via BuiltAI)