Pre-Con · Detailed Scope of Works (DSW) · Worked example Northgate Chambers - Floors 4-6 Cat-B Fit-Out · Cushman Workplace · NG-2026-0042 · £1.42m
← Pre-Con Pack
BUILTAI
THE PRE-CON PACK™ · CLIENT DELIVERABLE
DSW · Detailed Scope of Works

Detailed Scope of Works

Eleven trade-led work packages — each with scope, exclusions, assumptions, interfaces and programme constraints. The contractual scope record that backs every supplier order.
Project
Northgate Chambers — Floors 4–6 Cat-B Fit-Out
Reference
NG-DSW-001 · Revision 2
Prepared by
Built AI Ltd · Pre-Con Office
Issue date
Friday 6 June 2026
Issued to
Cushman Workplace (on behalf of Halberd Properties & Wexley & Crowne LLP)
Status
Issued — Rev 2 incorporates Cushman comments on Rev 1
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
Document Control
RevDateDescriptionPreparedReviewed
Rev 128 May 2026Issued to Cushman Workplace — 11 packages completeS. OkaforD. Marchetti
Rev 26 Jun 2026Incorporates Cushman comments (30 May) — minor scope clarifications WP-06, WP-11S. OkaforD. Marchetti
SCOPE SUMMARY

Eleven Work Packages — £1,418,650

The awarded contract sum decomposed into eleven trade-led work packages. Each package has a full DSW entry below with inclusions, exclusions, assumptions, interface boundaries, programme constraints and drawings referenced.

WPWork PackageTarget ValueSpec SourceStatus
WP-01Strip-out & DemolitionExisting partitions, ceilings, finishes · phased L6→L5→L4£86,400SPC-A1Ordered
WP-02Internal Partitions & DoorsStud, acoustic Rw 42 dB, door sets, ironmongery£198,200SPC-A2Ordered
WP-03Glazed PartitionsAluminium-framed, fire-rated at compartment, manifestation£64,500SPC-A2Ordered
WP-04Suspended Ceilings & AcousticsAcoustic tile, exposed soffit, FCU access panels£72,800SPC-A3Ordered
WP-05Joinery — Meeting Suites & Tea PointsFluted oak veneer, AV channels, tea point cabinetry, storage£148,500SPC-A4Ordered
WP-06L6 Reception Joinery (PS)Reception desk, feature wall, low-level seating£24,000SPC-A7Ordered
WP-07Floor FinishesCarpet tile, vinyl, raised access floor replacement£94,300SPC-A5Ordered
WP-08Wall Finishes & DecorationPaint, vinyl, feature finishes, manifestation£42,100SPC-A6Ordered
WP-09Mechanical ServicesFCUs, ductwork, condensate, BMS interface£218,400SPC-M1Ordered
WP-10Electrical, Lighting & DataSub-mains, lighting, power, Cat6A, BMS, control£268,150SPC-M2Ordered
WP-11Workplace AV (PS)Displays, video bars, ceiling mics, control system£40,000SPC-X1Ordered
TRADE PACKAGES SUB-TOTAL£1,257,35011 packages · 100% ordered
Plus: Prelims, OH&P, contingency, fees, commissioning£161,300
CONTRACT SUM (excl. VAT)£1,418,650
WORK PACKAGE 01
Strip-out & Demolition
Specification: SPC-A1 · 12 clauses · Supplier: Clearsite Demolition Ltd
£84,200
COMMITTED VALUE
Inclusions
  • Removal of all existing stud partitions, glazed screens & door sets across L4, L5, L6.
  • Removal of all existing suspended ceiling systems — grid, tiles, hangers, perimeter trims.
  • Removal of existing floor finishes — carpet tiles, vinyl, adhesive residues. Raised access floor panels retained where serviceable (estimated 85% retention).
  • Removal of existing secondary M&E drops — lighting, power, data outlets, FCU pipework connections. Coordinated isolation with M&E subcontractor prior to strip-out.
  • Existing tea point installations — removal of base/wall units, worktops, appliances, plumbing connections. Cap and make safe.
  • Waste segregation & disposal via licensed waste carrier. Duty of care documentation.
  • Photographic record — before, during, after per floor. Submitted to Built AI Doc Control within 48 hours of completion per floor.
Exclusions
  • Cat-A base-build services, risers, structural walls — protected in situ. Not part of strip-out scope.
  • Asbestos removal — R&D survey clear (May 2024). If ACMs found in concealed voids, stop work and notify Built AI immediately. Licensed asbestos removal is a separate instruction.
  • Structural alterations — no cutting of structural slabs, beams or columns.
  • Landlord plant areas & riser internals — excluded from scope.
Assumptions
  • Goods lift available in booked slots — supplier to coordinate via Building Manager (48hr notice).
  • Noisy works restricted to 10:00–16:00 Mon–Fri (adjacent tenants L1–L3).
  • All existing services isolated prior to strip-out commencement — coordination with incoming M&E subcontractor.
  • Skip location: Northgate Yard — permit obtained by Built AI.
Interfaces
Predecessor: site possession (22 Jun). Successor: WP-02 partitions, WP-09 mechanical first-fix, WP-10 electrical first-fix — all await strip-out completion per floor. Adjacent: Building Manager (lift bookings, tenant notifications), M&E subcontractor (isolation), landlord (riser protection).
Programme
Duration: 3 weeks. Sequence: L6 Wk 1, L5 Wk 2, L4 Wk 3. Concurrent working begins Wk 4 once L6 strip-out complete — partitions and M&E first-fix can start on L6 while L5/L4 strip-out continues.
WORK PACKAGE 02
Internal Partitions & Doors
Specification: SPC-A2 · 22 clauses · Supplier: Ringway Interiors Ltd
£192,600
COMMITTED VALUE
Inclusions
  • Metal stud partition system — 92mm C-section studs at 600mm centres, twin-layer 15mm acoustic plasterboard each side, 75mm mineral wool infill (45 kg/m³). Rw 42 dB to meeting suites.
  • General partitions — single-layer plasterboard each side, 50mm mineral wool, standard stud. Office-to-corridor, storage, service risers.
  • Door sets — meeting suites — 44mm solid core, European oak veneer (matching SPC-A4), shadow-gap frame, brushed brass ironmongery, magnetic seal, concealed closer.
  • Door sets — general — 44mm solid core, painted finish, standard ironmongery per schedule.
  • Fire-stopping at all partition-to-slab junctions, service penetrations and compartment-line interfaces. Intumescent mastic and fire-rated batts.
  • Plaster skim coat, tape & joint — to Level 4 finish (BS EN 13914-2) for paint receipt.
  • Service zones — coordinated with WP-10 electrical for back-box and conduit positioning within stud wall zone. Drawing coordination per DWG-A-01 Rev D.
Exclusions
  • Glazed partitions — separate package WP-03 (Optima Systems).
  • Paint finish to plasterboard surfaces — by WP-08 (wall finishes).
  • Joinery feature walls adjacent to partitions — by WP-05. Partition to provide backing structure only.
  • Electrical back-boxes and wiring within stud zone — by WP-10. Partition contractor to leave service zones accessible until M&E first-fix complete.
  • Ceiling-to-partition junction detail above suspended ceiling line — by WP-04 ceiling contractor.
Assumptions
  • Strip-out complete per floor before partitions commence on that floor.
  • Floor levels confirmed ±5mm (survey 14 May 2026).
  • Soffit heights confirmed per floor (survey 14 May 2026). L4/L5: 3,450mm slab-to-slab; L6: 3,600mm.
  • M&E coordination drawings issued before partition set-out (DWG-M-01 Rev C, DWG-M-02 Rev B).
Interfaces
Predecessor: WP-01 strip-out (per floor). Successor: WP-04 ceilings (grid hung from soffit, abutting partition head), WP-05 joinery (feature walls fixed to partition backing), WP-08 paint (to plasterboard surfaces). Concurrent: WP-10 electrical first-fix within stud zones (coordinated access protocol — partitions one side, electrician other side, then close).
Programme
Duration: 4 weeks (2 wks first-fix stud + 1 wk boarding + 1 wk tape/joint/doors). Sequence: follows strip-out per floor. L6 partitions start Wk 4, L5 Wk 5, L4 Wk 6. Material order: 4-week lead — order placed 13 Jun for Wk 11 delivery.
WORK PACKAGE 09
Mechanical Services
Specification: SPC-M1 · 19 clauses · Supplier: Atherton Mechanical Services Ltd
£211,600
COMMITTED VALUE
Inclusions
  • Fan coil units — supply & install — 22× Daikin FWF-C (3.5kW cooling / 4.0kW heating), ceiling-void mounted. 1× slim-line variant on L5 per CC-01.
  • Ductwork modifications — tenant supplementary supply/return ductwork from landlord AHU connections. Insulated galvanised ductwork per DW/172.
  • CHW pipework connections — tenant FCU connections to landlord chilled water loop at each floor riser. Isolation valves, strainers, flexible connections.
  • Condensate routing — condensate from all FCUs to nearest waste stack. Insulated MUPVC pipework, trapped and accessible.
  • Controls & BMS interface — BACnet/IP gateway per floor, integration with landlord Trend IQ4 BMS. Local thermostats with occupancy override.
  • Commissioning — flow balancing, FCU commissioning, BMS point-to-point testing. Commissioning report issued to CA.
  • O&M documentation — as-installed drawings, equipment schedules, maintenance manuals, spare parts list.
Exclusions
  • Landlord chilled water system upgrades — landlord responsibility. Confirmed in place by Halberd Properties (letter 18 Apr).
  • Electrical supply to FCUs — by WP-10 (local isolators, power feeds, controls wiring from floor distribution boards).
  • Ceiling access panels above FCU positions — by WP-04 (acoustic-rated panels per CC-05 resolution).
  • Tea point plumbing — domestic hot/cold water and waste for tea points. Included as a minor-works addition to mechanical scope (daywork rate basis).
  • Fire suppression or sprinkler modifications — not triggered by tenant Cat-B scope (confirmed with Restall fire engineer).
Assumptions
  • Landlord chilled water available at riser connection point at or before Wk 12.
  • Riser access coordinated with Building Manager — 2-hour shutdown window per floor for CHW tie-in.
  • Ceiling void access available before ceiling grid install — coordinate with WP-04.
  • BMS outstation cabinet locations confirmed on landlord's riser drawings (received 22 Apr).
Interfaces
Predecessor: WP-01 strip-out (ceiling void clearance), WP-02 partitions (first-fix stud to create FCU zones). Successor: WP-04 ceilings (close ceiling after M&E tested above grid), WP-10 electrical (FCU power feeds). Adjacent: WP-05 joinery (condensate routing behind tea point cabinetry), Building Manager (riser shutdowns).
Programme
Duration: 6 weeks first-fix, 2 weeks second-fix/commissioning. FCU delivery: 5-week lead (Daikin stock) — order placed 13 Jun, delivery Wk 12. Commissioning: Wk 18–19, witnessed by Lambourne Vance. BMS integration: Wk 19, attended by landlord BMS operator.
REMAINING PACKAGES

8 Additional Work Packages

Work packages WP-03, WP-04, WP-05, WP-06, WP-07, WP-08, WP-10 and WP-11 follow the same structure as above — full inclusions, exclusions, assumptions, interfaces and programme constraints. WP-05 (Joinery) is shown in full in the Stage 03 (Market Day™) internal workflow document. Below is the summary scope for each.

WP-03 · Glazed Partitions · £63,100 · Optima Systems
Full DSW in document
Aluminium-framed single-glazed screens (12mm acoustic laminated glass, Rw 42 dB system), fire-rated section at L6 compartment line (6 m² Pyrobel 30), manifestation (frosted gradient), door integration. Excludes stud partitions (WP-02), painting (WP-08). 5-week lead, site start Wk 12.
WP-04 · Suspended Ceilings & Acoustics · £71,400 · Solebury Ceilings
Full DSW in document
1200 × 600 acoustic tile grid (Class A absorption), exposed soffit treatment in collaboration zones, acoustic-rated FCU access panels (Knauf Aquapanel per CC-05). Excludes M&E services above grid (WP-09, WP-10), lighting fittings (WP-10). 4-week lead, site start Wk 13.
WP-05 · Joinery — Meeting Suites & Tea Points · £146,200 · Holroyd & Sons
Full DSW in Stage 03
Fluted European oak veneer feature walls (96 m²), AV cable channels (80 × 50mm), tea point cabinetry (Corian worktops), full-height storage walls. Excludes reception desk (WP-06), AV equipment (WP-11), electrical first-fix (WP-10), floor finishes (WP-07). 10-week manufacture, site delivery Wk 16. Mock-up MU-01 signed off 9 Jun.
WP-06 · L6 Reception Joinery (PS) · £23,200 · Holroyd & Sons
Full DSW in document
Reception desk, branded feature wall, low-level seating. Provisional sum item (£24k → ordered £23,200). Design intent confirmed Wk 5 (DI-09). Specification locked 16 Jun. Excludes AV (WP-11), electrical (WP-10), floor finishes (WP-07). 6-week lead, ordered Wk 9.
WP-07 · Floor Finishes · £91,800 · Threshold Floors NW
Full DSW in document
Carpet tile (Milliken Laylines), vinyl to tea points (Forbo Sarlon), raised access floor replacement panels (15%). Excludes joinery base (WP-05), wall finishes (WP-08). Carpet stock confirmed, 6-week lead for raised floor, site install Wk 15–17.
WP-08 · Wall Finishes & Decoration · £41,200 · Bramhall Decorating
Full DSW in document
Paint scheme (Dulux Trade matt, 5-colour palette per SMP-04), vinyl wall covering to tea points, feature wall finishes, manifestation application (frosted gradient per SMP-08). Excludes plasterboard & tape/joint (WP-02), joinery surfaces (WP-05). 2-week lead, site start Wk 14.
WP-10 · Electrical, Lighting & Data · £262,400 · Marlow Electrical Services
Full DSW in document
Sub-mains & distribution (Schneider Prisma P), lighting (3 zones: Whitecroft linear / downlights / Bocci pendants), small power, Cat6A data (48 floor boxes), lighting control (DALI), BMS interface. Excludes FCU power feeds coordination (WP-09 isolators), AV cabling (WP-11). Switchgear LL-03: 9-week lead via Edmundson, site start Wk 13.
WP-11 · Workplace AV (PS) · £38,400 · Visualis AV Ltd
Full DSW in document
14× displays (Samsung QB55R), 6× video bars (Poly Studio X50), ceiling mics (Shure MXA920), control system (Crestron Flex). Provisional sum (£40k → ordered £38,400). RFI NG-014 closed 27 May. Excludes cabling infrastructure within joinery (WP-05), power feeds (WP-10), network switching (tenant IT direct). 8-week lead, site install Wk 17–18.
INTERFACE MATRIX

Package-to-Package Dependencies

Which packages depend on which. Read across: the row package requires the column package to be complete (or partially complete) before it can start. P = predecessor (must complete first). = concurrent interface (coordinate access).

WP-01WP-02WP-03WP-04WP-05WP-07WP-08WP-09WP-10
WP-02 PartitionsP
WP-03 GlazedPP
WP-04 CeilingsPP
WP-05 JoineryPPP
WP-07 FloorsPPPP
WP-08 PaintPP
WP-09 MechP
WP-10 ElecP
WP-11 AVPP

WP-06 (L6 Reception) and WP-08 accent finishes omitted for clarity — both follow the same dependency chain as WP-05 joinery. The critical path runs: WP-01 → WP-02 → WP-09/WP-10 (concurrent) → WP-04 → WP-05 → WP-07 → commission → handover.

Disclaimer: This Detailed Scope of Works has been produced by Built AI Ltd using AI-assisted workflow tools applied to the awarded contract documents, project specification (NG-PS-001), and supplier enquiry returns. All scope definitions, exclusions and assumptions are derived from source documents and are subject to review by the project team. This document does not replace competent review by qualified commercial and technical staff. Final scope decisions remain with the Employer, Contract Administrator and contractor's project team.

BuiltAI
DETAILED SCOPE OF WORKS — COMPLETE

11 packages. Every boundary defined.

Every work package has its scope, its exclusions, its assumptions and its interface boundaries documented before the first supplier sets foot on site. When a scope query arises mid-project, the answer is here — not in someone's memory.
WORK PACKAGES
11
TRADE VALUE
£1.26m
INTERFACES MAPPED
34
EXCLUSIONS LOGGED
47
built-ai.io · The Pre-Con Pack™ · DSW · Detailed Scope of Works © 2026 Built AI Ltd · NG-DSW-001 Rev 2