Pre-Con · Supplier Enquiry Pack (SEP) · Worked example Northgate Chambers - Floors 4-6 Cat-B Fit-Out · Cushman Workplace · NG-2026-0042 · £1.42m
← Pre-Con Pack
BUILTAI
SUPPLIER ENQUIRY PACK · NG-SEP-09-Rev1
Work Package 09 · Mechanical Services

Mechanical Services — Supplementary Cooling, Ductwork & Controls

Structured enquiry for the supply, install and commissioning of tenant supplementary mechanical services across Floors 4–6 at Northgate Chambers, Manchester.
ISSUED BY
Built AI Ltd
ENQUIRY DATE
26 May 2026
RETURN BY
3 Jun 2026 17:00
RECIPIENTS
3 invited suppliers
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
01

Project Context & Programme

Built AI Ltd has been awarded as Main Contractor (Design & Build) for the Cat-B fit-out of Floors 4, 5 and 6 at Northgate Chambers, 22 Northgate Street, Manchester M3 2BP. The project has a sectional completion structure with liquidated damages of £8,500 per working day per section.

The total NIA is 1,640 m² across three floors. The Cat-A landlord base-build services (including chilled water primary loop, AHU, riser infrastructure and BMS backbone) are retained. This mechanical package covers tenant supplementary cooling and controls only.

EMPLOYER
Halberd Properties Ltd
TENANT
Wexley & Crowne LLP (legal sector)
SITE POSSESSION
Mon 22 June 2026
L6 SECTIONAL COMPLETION
Fri 7 August 2026
L5 SECTIONAL COMPLETION
Fri 4 September 2026
PRACTICAL COMPLETION (L4)
Fri 25 September 2026
02

Detailed Scope of Works

Supply, install, test and commission the following mechanical services across Floors 4, 5 and 6:

Inclusions

Exclusions

Assumptions

03

Drawings & Specifications Referenced

The following drawings and specification documents are issued with this enquiry and form part of the scope definition. Supplier to confirm receipt and review of all documents listed.

RefTitleRevDateIssued by
DWG-M-01Mechanical Modifications — FCU positions, ductwork routing, condensate (8 sheets)Rev C8 May 26Lambourne Vance
SPC-M-01M&E Specification — Mechanical sections §T10, §T31 (19 clauses)Rev B22 Apr 26Lambourne Vance
NG-PS-001Project Specification — Section SPC-M1 (extract)Rev 122 May 26Built AI
NG-DSW-001Detailed Scope of Works — WP-09 entry (extract)Rev 128 May 26Built AI
DWG-A-01General Arrangement — L4/5/6 (partition layout for FCU zone context)Rev D22 Apr 26Trenholme Architects
HP-BMS-2024Halberd Properties BMS Access Policyv32024Halberd Properties
04

Programme Constraints & Sequencing

The mechanical package sits on the critical path. First-fix must begin once strip-out is complete per floor and stud partitions are sufficient to define FCU zones. Second-fix and commissioning must complete before ceiling grid closure and before sectional handover.

FIRST-FIX START
Week 12 · Mon 11 Aug 2026
FIRST-FIX DURATION
6 weeks (2 wks per floor)
SECOND-FIX & COMMISSION
Weeks 18–19 · Sep 2026
FCU DELIVERY REQUIRED
Week 12 · Daikin 5-week lead
RISER SHUTDOWN WINDOW
2 hrs per floor · Building Mgr
WITNESS TESTING
Lambourne Vance · Wk 18–19

Tenderers should confirm their ability to meet the above programme in their return. Any programme constraints, lead-time concerns or resource limitations must be declared. Built AI reserves the right to reject returns where programme compliance cannot be demonstrated.

05

Return Requirements — Priced BoQ Template

Returns must be submitted using the priced BoQ template below. Lump-sum quotations will not be evaluated. The template structures pricing under fixed line items so returns can be compared like-for-like across all tenderers.

ItemDescriptionQtyUnitRateTotal
09.01 Fan coil units — supplyDaikin FWF-C 3.5kW (or approved equiv.) — supply only, delivered to site 21nr£/nr£
09.02 Fan coil unit — slim variant — supplyDaikin FWF-C Slim 2.8kW (or approved equiv.) — L5 position per CC-01 1nr£/nr£
09.03 FCU installation — ceiling void mountingInstall, connect (CHW + condensate + controls), test. Per unit. 22nr£/nr£
09.04 Ductwork modifications — supply & installGalvanised ductwork per DW/172, insulated. Per floor. 3floor£/floor£
09.05 CHW pipework — riser to FCU connectionsCopper pipework, insulated, inc. isolation valves, strainers, flexibles. Per floor. 3floor£/floor£
09.06 Condensate pipework — FCU to waste stackInsulated MUPVC, trapped. Per floor. 3floor£/floor£
09.07 Grilles & diffusers — supply & installFCU discharge grilles, return air grilles. Colour to match ceiling. 44nr£/nr£
09.08 BMS interface — BACnet/IP gatewayGateway per floor, integration with Trend IQ4, local thermostats. Per floor. 3floor£/floor£
09.09 Commissioning — flow balance & FCUFull commissioning inc. witnessed testing. Commissioning report. 1sum££
09.10 O&M documentationAs-installed drawings, schedules, manuals, BMS point schedule. 2× hard + digital. 1sum££
09.11 Preliminaries, attendance & supervisionSite supervision, welfare contribution, site set-up, CSCS, induction attendance. 1sum££
09.12 Day rate — skilled mechanical operativeFor measured variations and minor works. 8-hour day. day£/dayRate only

In addition to BoQ pricing, returns must include: (a) confirmation of FCU manufacturer and model; (b) BMS integration experience — name 2 projects with Trend IQ4 or BACnet integration; (c) confirmed programme compliance with dates above; (d) site supervision CV; (e) two contactable references for similar M&E fit-out projects (£150k+ value); (f) evidence of BESA or equivalent membership; (g) current employer's liability, public liability and PI insurance certificates.

06

Commercial Terms

The successful tenderer will be appointed under the following terms:

SUB-CONTRACT FORM
JCT SBC/Sub 2016 (D&B)
PAYMENT
Monthly interim · 28 days from valuation
RETENTION
5% during works · 2.5% at PC · 0% at DLP end
PERFORMANCE BOND
10% on demand (if award > £100k)
PI INSURANCE
£2m any one claim (design liability)
DEFECTS LIABILITY
12 months from Practical Completion
VARIATIONS
Measured against BoQ rates + agreed day rate
HEALTH & SAFETY
CDM 2015 compliant · CSCS required · site-specific induction
07

Submission Instructions

Return your completed tender by:

Tuesday 3 June 2026 · 17:00 BST

Late returns will not be evaluated. Partial returns will be evaluated on the information provided but may be disadvantaged in the assessment.

Submit to:

Subject line: SEP-09 Mechanical Return — [Your Company Name]

Your return must include:

  • Completed priced BoQ (Excel template — all 12 line items)
  • Confirmation of FCU manufacturer and model
  • Programme showing compliance with dates in Section 04
  • BMS integration experience (2 project references with Trend / BACnet)
  • Site supervision CV
  • Two contactable references (M&E fit-out, £150k+)
  • BESA membership or equivalent trade body evidence
  • Insurance certificates (EL, PL, PI)
  • Any qualifications, exclusions or assumptions (clearly listed)

Note: This enquiry does not constitute an offer or commitment to award. Built AI Ltd reserves the right to award to any tenderer, to re-tender, or to not award at all. All information in this document is confidential and is provided solely for the purpose of tendering for this work package. Recipients must not disclose the contents to third parties without written consent from Built AI Ltd.

BuiltAI
SUPPLIER ENQUIRY PACK — WP-09 MECHANICAL
This is one of eleven structured enquiry packs issued during the Pre-Con Pack™ Stage 03 (Market Day™) process. Every enquiry follows the same seven-section format — project context, detailed scope, drawings, programme, priced BoQ template, commercial terms, submission instructions — so returns can be evaluated like-for-like across all tenderers.