The Pre-Con Pack™Stage 05 of 5 · Internal workflow
Pre-mobilisation QA gate · passed, 52 of 52 checks

Nothing mobilises until the gate says so

Green Light is the pre-mobilisation QA gate. Fifty-two checks across six domains, from document completeness to financial baseline, each with a single owner. The gate does not create work; it catches the work that was quietly incomplete. Northgate Chambers passed 52 of 52 with zero blockers.

Client
Cushman Workplace
Result
Passed, 0 blockers
Site possession
Mon 22 Jun 2026
Stage
05 of 5 · Green Light
Prepared by
BuiltAI Intelligence Ltd
Reference
NG-PC-S05

Illustrative example: fictional project and parties.

52 / 52QA checks passed
0Blockers at the gate
6Deliverables issued
6Risks transferred to delivery
BuiltAI Intelligence Ltd · built-ai.ioNG-PC-S05 · Stage 05
01Gate

Fifty-two checks, six domains, zero blockers

Green Light is the pre-mobilisation QA gate. It does not create work; it catches the work that was quietly incomplete before the site team inherits it. Fifty-two checks run across six domains, each with a single named owner, and mobilisation is authorised only when every check passes. Northgate Chambers passed 52 of 52 with zero blockers.

Document completeness10 / 10
Clause to order traceability8 / 8
Procurement and supply chain10 / 10
Risk closure8 / 8
Financial baseline8 / 8
Handover readiness8 / 8
02Issued

Six deliverables, statuses recorded

Six client deliverables are listed for handover. The status table records three as Issued, one as Signed off, one as Returned and one as Priced; it does not assert a sign-off for every row.

Ref Deliverable Issued Status
NG-PS-001 Project Specification, Rev 1 Fri 22 May Issued
NG-DSW-001 Detailed Scope of Works, Rev 2 Sat 6 Jun Issued
NG-DI-001 Design Intent, Rev 1 Fri 22 May Signed off
NG-SEP-09 Supplier Enquiry Pack, WP-09 w/c 25 May Returned
NG-UPB-001 Unpriced Bill of Quantities, Rev 1 Fri 22 May Priced
NG-PDP-001 Project Delivery Plan, Rev 1 Fri 19 Jun Issued
03Baseline

A clean baseline for Margin Cockpit

The gate hands the Margin Cockpit a financial baseline that reconciles end to end. The contract sum of £1,418,650 is fully accounted: £1,229,000 of trade committed, £28,350 held in contingency, and £161,300 of prelims and project costs fixed. Four performance bonds at 10% are received, and the sectional liquidated-damages exposure is recorded so it can be tracked from day one of delivery.

Baseline item Position
Contract sum, excl VAT £1,418,650
Trade committed £1,229,000
Held in contingency, CSR-001 £28,350
Prelims and project costs £161,300
Sectional LD exposure £8,500 per day, cap £70,932.50
Target margin, inherited 8.2%
Margin at handover 10.3%
04Handover

Risks closed or owned, pack handed over

Of the eleven risks opened at award, five are closed inside Pre-Con and six transfer to delivery in the Project Delivery Plan, each with an owner and a mitigation carried across. The 14-week programme, NG-PRG-003, is issued with the three sectional dates confirmed, and the pack is signed over to the site team.

Ref Risk transferred to delivery Carried as Owner
R-01Joinery long-lead versus programmeOrdered, factory pre-fit, one-week bufferS. Okafor
R-03Landlord CHW capacity confirmationLetter of comfort held, fallback coolingA. Pereira
R-05Sectional LD exposureFloat protected, dates tracked weeklyR. Ashby
R-07Noise to occupied floors L1 to L3Hours enforced, 48-hour noticeD. Marchetti
R-09Raised floor replacement rateSurvey at 13%, 2% contingency heldR. Ashby
R-11AV integration with tenant networkPlatform confirmed, direct switching excludedA. Pereira

Five of the eleven risks opened at award are closed inside Pre-Con; the six above transfer to delivery with the mitigation carried across rather than restated. Each has a single named owner on the site team, so nothing opened at award is handed over without one, and the Project Delivery Plan reopens this list on day one of the build.

Handover signed

The Pre-Con pack is handed to delivery with every document traced, every order placed or ring-fenced, and the financial baseline clean. What the Margin Cockpit, the Commercial Control Kit and the Dispatch Desk read downstream all starts here, at the gate.

Reference NG-PC-S05Stage 05 of 5, Green LightFeeds Delivery and Margin Cockpit