Award intake and setup · award received 27 April 2026

The award clock starts before the ink dries

The day an award lands, the programme is already running. Day One captures the contract, reconciles the tender to the awarded sum, stands up the project workspace, and fixes the long-lead orders that decide whether delivery can take possession on time.

Client
Cushman Workplace
Tenant
Wexley & Crowne LLP
Contract
JCT D&B 2016 · £1.42m
Award date
Mon 27 Apr 2026
Prepared by
BuiltAI Intelligence Ltd
Reference
NG-2026-0042

Illustrative example: fictional project and parties.

£1,418,650Awarded contract sum, excl VAT
11Trade packages to procure
4Long-lead orders on the critical path
11Risks open at award
BuiltAI Intelligence Ltd · built-ai.ioNG-PC-S01 · Stage 01
01Award

Award received, contract captured

Halberd Properties Ltd awarded the Floors 4-6 Cat-B fit-out to BuiltAI on Monday 27 April 2026, acting through workplace agent Cushman Workplace on behalf of the incoming tenant, Wexley & Crowne LLP. BuiltAI is appointed main contractor under JCT Design and Build 2016 with sectional completion and bespoke amendments, and carries the contractor design portion for the workplace AV, partitions and joinery.

Award Intake is the single source of truth for the awarded contract. Every field below is captured once, on day one, and read by every stage that follows, so no downstream document restates a term from memory.

Term Detail
Contract form JCT Design and Build 2016, sectional completion, bespoke amendments
Awarded sum, excl VAT £1,418,650
Liquidated damages £8,500 per working day, per section
LD cap 5% of the awarded sum, £70,932.50
Defects liability 12 months from practical completion
Performance bond 10% on demand, £141,865, within 10 working days of execution
Insurance £5m public liability, £10m professional indemnity
Sectional exposure

Three sectional dates each carry independent liquidated damages of £8,500 per working day. With the L6 date the tightest, the joinery long-lead order in Section 04 becomes the binding constraint on the whole programme.

02Reconcile

Tender to award reconciliation

The awarded sum of £1,418,650 is £28,550 below the £1,447,200 tender: the net of two re-measures, one restructured package and one deletion. The movement is recorded line by line so no scope is assumed carried across.

Movement Item Tendered Awarded Change
Held Strip-out, L4, L5 and L6 £86,400 £86,400 £0
Re-measured Cat-B partitions and doors £238,500 £242,700 +£4,200
Held Joinery, meeting suites and tea points £162,800 £162,800 £0
Restructured Workplace AV £52,000 £40,000 −£12,000
Added L6 reception joinery, provisional sum not tendered £24,000 +£24,000
Removed Move coordination and data migration £18,500 deleted −£18,500
Re-measured M&E supplementary works £284,300 £280,050 −£4,250
Held Finishes and flooring £196,400 £196,400 £0
Held Commissioning and testing £42,300 £42,300 £0
Held Prelims, OH&P and contingency £366,000 £344,000 −£22,000
Contract sum, excl VAT £1,447,200 £1,418,650 −£28,550
03Setup

Workspace, naming and the stakeholder map

Within hours of award the project workspace is stood up: a fixed folder tree, a naming convention keyed to project reference NG-2026-0042, and a document control register that every issued document is logged against. The professional team is captured once, with a single named owner for each thread.

Party Role Organisation
Employer, freeholder Awarding party Halberd Properties Ltd
Employer's agent Client contact Cushman Workplace
Beneficial tenant Incoming occupier Wexley & Crowne LLP
Main contractor, D&B Delivery BuiltAI Intelligence Ltd
Architect Design Trenholme Architects
M&E consultant Design Lambourne Vance Engineers
Contract administrator CA and Principal Designer Hadley Whitfield Surveyors
Fire engineer Cat-B compartmentation Restall Fire Consultancy
One workspace, five owners

The BuiltAI Pre-Con office fields five named individuals: Pre-Con lead D. Marchetti, design manager A. Pereira, quantity surveyor R. Ashby, procurement lead S. Okafor, and the site manager who inherits the pack at handover. Every risk, approval and order below carries one of these names.

04Risk

Long-lead orders and the risks already live

Four items sit on the critical path from day one. The bespoke meeting-suite joinery is the binding constraint: at a 10 to 12 week lead against the L6 sectional date, its order dictates the whole programme. Eleven risks are opened at award, graded by probability and impact, each with a named owner.

Ref Long-lead item Lead Order by Value Owner
LL-01 Meeting-suite joinery, fluted oak, AV channels 10 to 12 weeks Wed 6 May 2026 £148,500 S. Okafor
LL-03 Switchgear and sub-mains, 800A floor boards 9 to 10 weeks Wed 13 May 2026 £56,200 S. Okafor
LL-02 Workplace AV, displays, control, provisional sum 8 to 10 weeks Wed 20 May 2026 £40,000 S. Okafor
LL-04 Raised access floor, replacement panels 6 to 7 weeks Wed 27 May 2026 £38,400 S. Okafor
Ref Risk Prob Impact RAG Owner
R-01 Workplace AV scope unresolved, RFI NG-014, £40k provisional sum exposed High Med Amber D. Marchetti
R-02 Joinery long-lead versus L6 sectional date; post-order change hits cost and time Med High Red S. Okafor
R-03 Landlord sub-main capacity; tenant load exceeds the Cat-A baseline Low High Amber A. Pereira
R-04 L6 reception design undefined; added at award as a £24k provisional sum Med Med Amber A. Pereira
R-05 Sectional LD exposure, £8,500 per day across three sections Low High Amber R. Ashby
R-06 Adjacent occupied floors L1 to L3; noisy works restricted to 10:00 to 16:00 Med Med Amber D. Marchetti
R-07 Raised access floor replacement rate above the surveyed allowance Med Med Amber R. Ashby
R-08 CHW capacity for supplementary cooling to be confirmed by the landlord Low High Amber A. Pereira
R-09 Carpet and finishes selection slipping the L6 sectional date Med Med Amber A. Pereira
R-10 Performance bond and warranties to execute within 10 working days Low Med Green R. Ashby
R-11 AV integration with the tenant network, platform to be confirmed Med Med Amber D. Marchetti

The full register runs to eleven risks, R-01 to R-11. Five are closed inside Pre-Con; six transfer to delivery in the Project Delivery Plan.

One red, nine amber, one green

The single red is R-02, the joinery long-lead against the L6 sectional date, which is why the joinery order is expedited in Market Day ahead of the general enquiry round. Nine risks are amber and actively managed, and only the bond execution is green. The RAG profile is set on day one so the priority order is clear before a single order is placed.

Reference NG-PC-S01Stage 01 of 5, Day OneFeeds Fine Print, Stage 02