Pre-Con · Day One™ - Stage 01 · Worked example Northgate Chambers - Floors 4-6 Cat-B Fit-Out · Cushman Workplace · NG-2026-0042 · £1.42m
← Pre-Con Pack
BUILTAI
THE PRE-CON PACK™ STAGE 01 · DAY ONE

Day One

The project starts here.
The first 48 hours after award decide whether mobilisation is calm or chaotic. Award Intake captures the contract terms, programme anchors, stakeholder map and document control structure — before the first specification line is written.
Project
Northgate Chambers — Floors 4–6 Cat-B Fit-Out
Awarded by
Halberd Properties Ltd · on behalf of Wexley & Crowne LLP
Award date
Monday 27 April 2026
Captured by
Built AI Pre-Con Office
Reference
AI-2026-042 · NG-2026-0042
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
PRE-CON WORKFLOW
1Day One
2Fine Print 3Market Day 4The Ledger 5Green Light CLIENT DELIVERABLES
PSSpec
DSWScope
DIDesign Intent
SEPEnquiries
UPBBoQ
PDPDelivery Plan
PROGRAMME STATUS

Award Clock

Captured at intake. The pre-con window drives every downstream stage and dictates when delivery can take possession of a mobilisation-ready package.

AWARD RECEIVED
27 Apr 2026
Mon, 09:14 BST
PRE-CON WINDOW ENDS
19 Jun 2026
Fri, 17:00 BST · 8 weeks
WORKING DAYS
40 WD
excl. weekends + bank hols
INTERNAL HANDOVER TARGET
17 Jun 2026
Pre-Con QA Gate — 2 day buffer
INTAKE RECORD

Project & Contract Capture

Single source of truth for the awarded contract. Every downstream pre-con output traces back to fields captured here.

Day One — Rev 1
AI-2026-042 · Logged 27 Apr 2026 09:14

01Project Basics

Project Title Northgate Chambers — Floors 4–6 Cat-B Fit-Out
Project Reference NG-2026-0042
Site Address 22 Northgate Street, Manchester, M3 2BP Floors 4, 5 and 6. Building common parts excluded from Cat-B scope.
Net Internal Area 1,640 m² NIA L4 545 m² · L5 545 m² · L6 550 m² (per measured survey 12 Mar 2026)
Awarded Contract Sum £1,418,650.00 excl. VAT · per Contract Sum Analysis Rev 4 issued 22 Apr 2026
Project Type Cat-B office fit-out — legal sector Open-plan with cellular meeting suites, client-facing reception, tea points

02Contracting Parties

Employer Halberd Properties Ltd Building landlord. Acting through their agent Cushman Workplace.
Beneficial Tenant Wexley & Crowne LLP Incoming occupier. Funding the works under Cat-B sub-letting agreement with Halberd.
Built AI Role Main Contractor (Design & Build) Designer for the CDP element (workplace AV, partitions, joinery).
Tenant Representative Cushman Workplace Project monitoring on behalf of Wexley & Crowne. Approves design intent and stage gates.
Contract Form JCT Design & Build 2016 With sectional completion · with bespoke amendments Sch. 2 (incl. liquidated damages and insurance terms)
Contract Administrator Hadley Whitfield Surveyors Independent CA appointed by Halberd Properties.

03Programme Anchors

Award Date Mon 27 Apr 2026 Letter of Intent issued 24 Apr; full contract sealed 1 May.
Pre-Con Window 27 Apr — 19 Jun 2026 8 weeks. Internal target gate 17 Jun (2-day buffer).
Possession of Site Mon 22 Jun 2026 Strip-out to commence Wk 1. L6 first, then L5, L4.
Sectional Completion — L6 Fri 7 Aug 2026 First floor handed over to enable tenant fit-out testing.
Sectional Completion — L5 Fri 4 Sep 2026 Second floor handover.
Practical Completion — L4 + Building Fri 25 Sep 2026 Final section. Triggers DLP commencement.
Tenant Move-In Mon 12 Oct 2026 Hard date — tenant lease commences. LDs apply if missed.
Liquidated Damages £8,500 per working day Per section. Capped at 5% of awarded sum (£70,932.50).
Defects Liability Period 12 months from PC Standard JCT D&B clause 2.35.

04Commercial Terms

Awarded Contract Sum £1,418,650.00 Down from tendered £1,447,200.00 — see reconciliation below.
Provisional Sums £64,000.00 Workplace AV (£40k) · Reception joinery (£24k). To be expended.
Contingency £28,400.00 2.0% client-held. Released against agreed instructions only.
Retention 5% / 2.5% 5% during works, releasing to 2.5% at PC, balance at end of DLP.
Payment Terms Monthly interim · 14 days Application date 22nd of each month. Payment due 14 days post Pay Less Notice deadline.
Variation Mechanism JCT D&B Sch. 5 — Schedule 2 Quotations 14-day quote period. CA instructions form basis of CE entitlement.
PI Insurance Required £5m any one claim Confirmed in place via Sentinel Brokers — cover note Ref SB/2026/0814.
Performance Bond 10% — On Demand £141,865 bond required within 10 working days of contract execution.
SCOPE RECONCILIATION

Tender → Award Reconciliation

What changed between the tender we submitted and the contract we were awarded. Captured before mobilisation so every downstream output uses the awarded scope, not the tendered scope.

As Tendered £1,447,200 Bidroom submission · 14 March 2026

  • = Strip-out — L4, L5, L6 (existing fit-out) Removal of legacy partitions, floor finishes, ceilings, services drops. Make safe and protect.
  • = Cat-B build — partitions, joinery, finishes, AV, FF&E coordination Per tender drawing pack TP-NG-001 to 047 issued 27 Feb 2026.
  • = M&E modifications — supplementary cooling, lighting, power, data Cat-A landlord baseline retained. Tenant-specific augmentation only.
  • ~ Workplace AV — full design, supply & install Tendered as fully designed scope at £52,000.
  • Tenant move-coordination & data migration Tendered at £18,500. Excluded post-tender — moved to tenant-direct contract.
  • = Building services commissioning & T&C Including BCO sign-off, fire alarm reverification, smoke ventilation rebalancing.

As Awarded £1,418,650 Contract sealed · 1 May 2026 · −£28,550 vs tendered

  • = Strip-out — L4, L5, L6 (existing fit-out) Unchanged. Carried at tendered rate.
  • = Cat-B build — partitions, joinery, finishes, AV, FF&E coordination Unchanged scope. Quantities re-measured during PCSA — minor net increase £4,200.
  • = M&E modifications — supplementary cooling, lighting, power, data Unchanged.
  • ~ Workplace AV — provisional sum Restructured as £40,000 provisional sum. Tenant to confirm AV scope post-award (RFI NG-014).
  • Tenant move-coordination & data migration — REMOVED Out of scope. Excluded per CA Letter of Intent dated 24 Apr 2026.
  • + L6 reception joinery — additional provisional sum Added at award. £24,000 prov sum. Final design subject to tenant review.
  • = Building services commissioning & T&C Unchanged.
Movement Item Tendered Awarded Δ
Held Strip-out — L4/L5/L6 £86,400 £86,400 £0
Re-measured Cat-B partitions & doors £238,500 £242,700 +£4,200
Held Joinery — meeting suites & tea points £162,800 £162,800 £0
Restructured Workplace AV £52,000 £40,000 −£12,000
Added L6 reception joinery (PS) £24,000 +£24,000
Removed Move-coordination / data migration £18,500 −£18,500
Re-measured M&E supplementary works £284,300 £280,050 −£4,250
Held Finishes & flooring £196,400 £196,400 £0
Held Commissioning & T&C £42,300 £42,300 £0
Held Prelims, OH&P, contingency £366,000 £344,000 −£22,000
CONTRACT SUM (excl. VAT) £1,447,200 £1,418,650 −£28,550

Net movement of −£28,550 (1.97%) accepted by Built AI commercial team on 24 Apr 2026. Movement is non-margin-eroding: the −£18,500 removal eliminates third-party scope risk; the −£12,000 AV restructure converts fixed scope into a reimbursable provisional sum. Net upside on prelims of £22,000 reflects shorter pre-con duration agreed at award.

DOCUMENT CONTROL

Project Workspace Setup

Folder structure, document control register and naming conventions established before any pre-con output is produced. Every downstream document — specification, scope, BoQ — drops into this structure.

/NG-2026-0042 — Northgate Chambers ├──00_Contract ├──NG-CON-001 — Letter of Intent — 24 Apr 2026.pdf ├──NG-CON-002 — Executed Contract — JCT D&B 2016 — 1 May 2026.pdf ├──NG-CON-003 — Schedule of Amendments Sch. 2.pdf └──NG-CON-004 — Contract Sum Analysis Rev 4.xlsx ├──01_Tender_As-Submitted # sealed; reference only ├──NG-TND-RFI-Register-Final.xlsx ├──NG-TND-Assumption-Register-Final.xlsx └──NG-TND-Bidroom-Outputs-Pack.zip ├──02_Drawings ├──02a_Architect — issued by Trenholme Architects ├──02b_M&E — issued by Lambourne Vance Engineers ├──02c_Structural — landlord-issued, Cat-A baseline └──02d_FF&E_Layouts — Cushman Workplace ├──03_Specifications # produced in Stage 02 ├──04_Scope_of_Works # produced in Stage 03 ├──05_Enquiry_Packages # produced in Stage 03 ├──06_BoQ # produced in Stage 04 ├──07_Procurement_Tracker # produced in Stage 04 ├──08_Programme ├──NG-PRG-001 — Tender Programme — Rev 0.pdf └──NG-PRG-002 — Pre-Con Programme — Rev 1.mpp ├──09_Risk ├──NG-RSK-001 — Project Risk Register — Rev 1.xlsx └──NG-RSK-002 — CDM Pre-Construction Information.pdf ├──10_Stakeholders └──NG-STK-001 — Stakeholder Register — Rev 1.xlsx ├──11_Correspondence ├──11a_Inbound └──11b_Outbound └──99_Archive # superseded revisions held here, never deleted

Naming Convention

All documents follow: NG-{TYPE}-{NNN}-{Title}-Rev{N}-{Date}.{ext}

Inbound Document Index — At Award (Rev 1)

47 documents
REF DOCUMENT REV DATE SOURCE
CON-001 Letter of Intent Halberd Properties → Built AI · grants pre-contract works permission Rev 0 24 Apr 26 Halberd
CON-002 Executed Contract — JCT D&B 2016 Sealed under hand · Schedule 2 amendments included Rev 0 1 May 26 Halberd
CON-003 Contract Sum Analysis Awarded breakdown by package · Rev 4 sealed Rev 4 22 Apr 26 Halberd
CON-004 Schedule of Amendments LD rate, insurance, retention, performance bond, payment terms Rev 1 22 Apr 26 Halberd
DWG-A-01 Architect's Drawing Pack — General Arrangement 14 drawings · L4/5/6 GAs, partition layouts, ceiling plans Rev D 22 Apr 26 Trenholme
DWG-A-02 Architect's Drawing Pack — Joinery & Finishes 11 drawings · meeting suite joinery, tea points, reception Rev C 15 Apr 26 Trenholme
DWG-M-01 M&E Drawing Pack — Mechanical Modifications 8 drawings · supplementary cooling, ductwork modifications, FCU positions Rev B 15 Apr 26 Lambourne Vance
DWG-M-02 M&E Drawing Pack — Electrical & Lighting 7 drawings · small power, data, lighting layouts, lighting control zones Rev B 15 Apr 26 Lambourne Vance
SPC-A-01 Architectural Specification (Outline) NBS-format outline spec · partitions, doors, joinery, finishes Rev B 22 Apr 26 Trenholme
SPC-M-01 M&E Specification (Outline) CIBSE-format spec · supplementary cooling, lighting, small power, data, BMS interface Rev B 22 Apr 26 Lambourne Vance
FFE-01 FF&E Layout — Tenant-Issued 3 layouts · workstation positions, meeting room sizing, reception furniture Rev A 8 Apr 26 Cushman
CDM-PCI Pre-Construction Information (CDM 2015) Existing site hazards, asbestos report, building access, fire strategy Rev 1 15 Apr 26 Halberd
PRG-001 Tender Programme Original tender programme with 8-week pre-con and 14-week construction periods Rev 0 14 Mar 26 Built AI
RFI-LOG Tender RFI Register — As Closed 14 RFIs raised during tender · all closed at award · NG-014 (AV scope) carried forward Rev 4 22 Apr 26 Bidroom
ASM-LOG Assumption Register — Tender Closing 28 assumptions logged at tender · 24 confirmed, 3 retired, 1 carried forward Rev 3 14 Mar 26 Bidroom

Showing 15 of 47 documents indexed at award. Full register held at /NG-2026-0042/00_Contract/Document_Register.xlsx. Every inbound document indexed within 4 working hours of receipt.

PROJECT TEAM

Stakeholder Register

The 18 individuals across nine organisations who hold decision rights over some part of the pre-con scope. Captured at intake, kept live, referenced in every output.

Built AI Project Team 5 individuals

Pre-Con Lead
D. Marchetti
Built AI Ltd · Manchester
PRIMARY
d.marchetti@built-ai.io
+44 7700 904 421
Design Manager
A. Pereira
Built AI Ltd · Manchester
DESIGN
a.pereira@built-ai.io
+44 7700 904 433
Quantity Surveyor
R. Ashby
Built AI Ltd · Manchester
COMMERCIAL
r.ashby@built-ai.io
+44 7700 904 447
Procurement Lead
S. Okafor
Built AI Ltd · Manchester
PROCUREMENT
s.okafor@built-ai.io
+44 7700 904 458
Document Controller
L. Hennessy
Built AI Ltd · Manchester
DOC CONTROL
docs@built-ai.io
+44 7700 904 469

Employer & Tenant Side 5 individuals · 3 organisations

Employer's Project Director
M. Whitfield
Halberd Properties Ltd
EMPLOYER
m.whitfield@halberd.co.uk
+44 161 555 0142
Contract Administrator
J. Pemberton
Hadley Whitfield Surveyors
CA
j.pemberton@hwsurveyors.co.uk
+44 161 555 0287
Tenant Workplace Director
F. Crowne-Hewitt
Wexley & Crowne LLP
TENANT
f.crownehewitt@wexleycrowne.com
+44 20 7100 4400
Tenant Project Manager
P. Sandhu
Cushman Workplace
TENANT REP
p.sandhu@cushman-workplace.com
+44 20 7100 5132
Tenant IT & AV Lead
N. Bramwell
Wexley & Crowne LLP
TENANT IT
n.bramwell@wexleycrowne.com
+44 20 7100 4421

Designers & Specialists 8 individuals · 4 organisations

Architect — Lead Designer
G. Trenholme
Trenholme Architects
ARCH
g.trenholme@trenholme.studio
+44 161 555 0334
Architect — Project Architect
K. Yusuf
Trenholme Architects
ARCH
k.yusuf@trenholme.studio
+44 161 555 0341
M&E Engineer — Lead
H. Lambourne
Lambourne Vance Engineers
M&E
h.lambourne@lvance.co.uk
+44 161 555 0418
M&E Engineer — Project
B. Vance
Lambourne Vance Engineers
M&E
b.vance@lvance.co.uk
+44 161 555 0421
Principal Designer (CDM)
J. Pemberton
Hadley Whitfield Surveyors
CDM PD
j.pemberton@hwsurveyors.co.uk
+44 161 555 0287
Building Control Officer
T. Asare
Manchester City Council
BCO
bco.asare@manchester.gov.uk
+44 161 234 5141
Fire Engineer (Cat-A baseline)
D. Restall
Restall Fire Consultancy
FIRE
d.restall@restall.fire
+44 7900 415 002
Building Manager (operations)
C. Iqbal
Halberd Properties — On-site
FACILITIES
c.iqbal@halberd.co.uk
+44 7900 415 028

Communication protocol: technical queries route Built AI Design Manager → Architect or M&E Lead. Commercial queries route QS → Contract Administrator. Tenant approvals always via Cushman Workplace, never direct to Wexley & Crowne. Building access matters route via Building Manager during pre-con; transition to site-based PM at mobilisation.

CONSTRAINTS

Programme & Site Constraints

The non-negotiables. Every package, enquiry and BoQ line later in the workflow has to respect what's here.

Project Programme — High-Level View

27 April 2026 — 12 October 2026 (24 weeks total)

PRE-CON · 8 wks
CONSTRUCTION · 14 wks (sectional)
HANDOVER
27 Apr
11 May
25 May
22 Jun
27 Jul
4 Sep
12 Oct
SITE WORKING HOURS
07:30 — 18:00
Mon-Fri only. No weekend working without 5 WD notice + supplementary security cover.
NOISY WORKS RESTRICTION
10:00 — 16:00
Adjacent floors L1-L3 occupied. Drilling, cutting, demolition outside this window prohibited.
DELIVERY ACCESS
Goods Lift — Booked Slots
3-tonne capacity. Goods entry via Northgate Yard. Lift bookings via Building Manager — 48hr notice.
FLOOR-BY-FLOOR SEQUENCE
L6 → L5 → L4
Strip-out and build sequenced top-down. Concurrent working allowed once L6 first-fix complete.
ASBESTOS STATUS
Survey Clear
Refurbishment & Demolition Survey (May 2024). No ACMs in scope areas. Re-inspection if hidden voids opened.
FIRE STRATEGY
Building-wide — Restall
Compartmentation per Cat-A baseline. Tenant Cat-B alterations subject to fire engineer sign-off.
REF Long-lead Item Typical Lead Order-by Date Est. Value Owner
LL-01 Bespoke meeting suite joinery — fluted oak veneer, integrated AV cabling channels, full-height feature walls (L5 & L6) 10–12 weeks Wed 6 May 2026 £148,500 Pre-Con
LL-02 Workplace AV equipment — 14× displays, 6× video bars, ceiling mics, control system. Subject to RFI NG-014 closure. 8–10 weeks Wed 20 May 2026 £40,000 PS Tenant + Pre-Con
LL-03 Switchgear & sub-mains — 800A floor distribution boards, supplementary metering. Subject to landlord sub-main upgrade. 9–10 weeks Wed 13 May 2026 £56,200 Pre-Con
LL-04 Raised access flooring — replacement panels, tenant-specific cable management. Long-lead due to spec changes. 6–7 weeks Wed 27 May 2026 £38,400 Pre-Con

Order-by dates work back from the construction sequence with one week's float. Joinery (LL-01) is the binding constraint — slipping the order pushes L6 sectional handover and triggers LDs at £8,500/day per missed section.

RISK SNAPSHOT

Initial Risk Register — At Award

Eleven risks identified at intake. The register is live for the duration of the pre-con window — re-rated weekly, owner-tracked, escalated if RAG moves red.

REF Risk PROB IMP RAG Owner Mitigation
R-01
AV scope unresolved (RFI NG-014)
Tenant has not confirmed final AV requirement. £40k provisional sum at risk of overrun.
H M A D. Marchetti
+ Cushman
Workshop scheduled wk 2 with Wexley IT (N. Bramwell) and AV specialist. Target close: 15 May.
R-02
Joinery long-lead vs L6 sectional date
10-12wk joinery lead means order must be placed by 6 May. Any spec change post-order triggers cost & programme impact.
M H R S. Okafor Spec finalisation prioritised in Stage 02. Joinery enquiry pack issued wk 1. Sample sign-off wk 3.
R-03
Landlord sub-main capacity
Tenant electrical load exceeds Cat-A baseline. Landlord supplementary supply required — confirmed but not yet commissioned.
L H A A. Pereira
+ Lambourne Vance
Letter of comfort received from Halberd 18 Apr. M&E enquiry conditional on sub-main delivery confirmed wk 4.
R-04
Reception joinery design TBC
L6 reception added at award as £24k provisional sum. No design issued. Late design risks programme slip.
M M A A. Pereira Design intent workshop scheduled wk 2 with Trenholme + Cushman. Sample by wk 5. Manufacture by wk 7.
R-05
Sectional completion penalty exposure
£8,500/day LDs × 3 sections. Capped at 5% (£70,932). Schedule float minimal post-construction-start.
L H A R. Ashby Programme float review wk 4. Procurement tracker live by end Stage 04. Float test in Stage 05 QA gate.
R-06
Adjacent tenant occupancy — noise complaints
L1-L3 occupied by other tenants. Noisy works restricted to 10:00-16:00. Strip-out/concrete cutting risks complaints.
M M A D. Marchetti
+ Building Mgr
Site logistics plan wk 4. Tenant notification protocol agreed with Building Manager. Noise monitoring during demolition.
R-07
Supplementary cooling — plant access
FCU positions require ceiling plenum access. Some areas conflict with structural beams — re-design may be needed.
L M G A. Pereira
+ Lambourne Vance
Coordinated drawings expected wk 2. Site survey confirmation by Built AI M&E coordinator wk 3.
R-08
Tenant FF&E delivery sequencing
Tenant-direct FF&E delivery (workstations, soft seating) must integrate with Cat-B finishes programme.
M L G D. Marchetti
+ Cushman
Joint programme review with Cushman wk 5. Tenant deliveries to align with sectional handover dates.
R-09
Performance bond delivery
10% bond required within 10 WD of contract execution. Sentinel Brokers confirmed but not yet issued.
L L G R. Ashby Bond instruction sent to Sentinel 28 Apr. Issue confirmed for 7 May. CA notified.
R-10
CDM Principal Designer alignment
PD role held by Hadley Whitfield (also CA). Risk of conflict in dual role on design-related entitlement queries.
L M G A. Pereira Role boundaries agreed in writing wk 1. PD reports route distinct from CA correspondence.
R-11
Building Control approval timing
Cat-B alterations subject to BCO inspection. Inspection slots tighten in late summer — risk to L4 PC if missed.
L M G A. Pereira BCO pre-application meeting booked wk 3. Inspection schedule pre-agreed by end Stage 02.
RED RISKS
1
Joinery long-lead vs sectional date — actively mitigated wk 1.
AMBER RISKS
5
Owner-allocated. Closure target by end Stage 03.
GREEN RISKS
5
Tracked but no immediate action.
REVIEW CADENCE
Weekly
Pre-Con Lead chairs Friday 16:00. Notes circulate by 17:00.
STAGE 01 GATE

Day One — Sign-off & Handover to Stage 02

Intake stage closes when the contract, programme, stakeholders, document control, risk register and tender reconciliation are all complete. Sign-off triggers Stage 02 (Specification & Design Intent).

Stage 01 Gate — Day One Internal QA gate · all items complete · ready for Stage 02
SIGNED OFF
Contract & commercial terms captured Awarded sum, prov sums, contingency, retention, payment terms, LDs, bond, insurance — all logged.
Tender → award reconciliation completed Net movement of −£28,550 reconciled and accepted by Built AI commercial team.
Document control structure live 11-folder workspace established. 47 inbound documents indexed. Naming convention published.
Stakeholder register issued 18 individuals across 9 organisations. Communication protocol agreed.
Programme anchors confirmed Award, possession, sectional dates, PC, tenant move-in. LD exposure quantified.
Site constraints documented Working hours, noisy works restrictions, delivery access, fire strategy, asbestos status.
Long-lead items flagged 4 long-lead items identified with order-by dates. Joinery flagged as critical path.
Initial risk register produced 11 risks logged. 1 red, 5 amber, 5 green. Owners allocated. Weekly review cadence agreed.
PRE-CON LEAD
D. Marchetti
Built AI Pre-Con Office
28 Apr 2026, 16:42
DESIGN MANAGER
A. Pereira
Built AI Design
29 Apr 2026, 09:18
QUANTITY SURVEYOR
R. Ashby
Built AI Commercial
29 Apr 2026, 11:04
Handover note to Stage 02 — Fine Print Stage 02 to begin 30 April. Inputs: awarded contract pack, drawings (architect & M&E), outline specifications (NBS/CIBSE), tender RFI register, assumption register. Priority items: (1) close RFI NG-014 — workplace AV scope; (2) confirm joinery specification ahead of 6 May order-by date; (3) progress reception joinery design intent for Cushman approval by wk 5. Three open amber risks (R-01, R-04, R-05) tracked into Stage 02. Joinery long-lead (R-02 — red) escalated to weekly Pre-Con Lead review until order placed.
BuiltAI
DAY ONE — SNAPSHOT

Award captured. Pre-con can begin.

A project that starts with a structured intake reaches site mobilisation with a clean document trail, an aligned team, and a procurement schedule that respects the programme. Stage 01 is the foundation everything else stands on.

DOCUMENTS INDEXED
47
STAKEHOLDERS LOGGED
18
RISKS IDENTIFIED
11
DAYS FROM AWARD
2
built-ai.io · Pre-Con Pack™ · Stage 01 of 5 © 2026 Built AI Ltd · NG-2026-0042 · Rev 1