The Pre-Con Pack
The Pre-Con Pack™Pack 02 / 06 · Client deliverable
Unpriced bill of quantities · Rev 1

Sixty-eight lines, eleven packages, every line traced

The Unpriced Bill of Quantities is the measured schedule the supply chain prices: 68 line items across eleven packages, each with a quantity, a unit and a specification reference, so every priced return traces back to a clause and forward to an order.

Client
Cushman Workplace
Revision
Rev 1
Lines
68 · 11 packages
Floors
L4 to L6
Prepared by
R. Ashby, BuiltAI
Reference
NG-UPB-001

Illustrative example: fictional project and parties.

68Line items measured
11Packages
£1,257,350Trade works measured
3Floors, L4 to L6
BuiltAI Intelligence Ltd · built-ai.ioNG-UPB-001 · Rev 1
01Structure

Sixty-eight lines, eleven packages

The Unpriced Bill of Quantities is the measured schedule the supply chain prices: 68 line items across eleven packages, each with a quantity, a unit and a specification reference. Because the line count is fixed, a priced return is checked against a schedule, not a supplier's own measure, and every line traces back to a clause and forward to an order.

WP Work package Lines Spec ref
WP-01 Strip-out and demolition 4 SPC-A1
WP-02 Internal partitions and doors 8 SPC-A2
WP-03 Glazed partitions 5 SPC-A2
WP-04 Suspended ceilings and acoustics 5 SPC-A3
WP-05 Joinery, meeting suites and tea points 8 SPC-A4
WP-06 L6 reception joinery, PS 3 SPC-A7
WP-07 Floor finishes 6 SPC-A5
WP-08 Wall finishes and decoration 5 SPC-A6
WP-09 Mechanical services 9 SPC-M1
WP-10 Electrical, lighting and data 12 SPC-M2
WP-11 Workplace AV, PS 3 SPC-X1
Eleven packages 68

The measure is weighted to the services packages, as a Cat-B fit-out is: WP-09 and WP-10 carry twenty-one of the sixty-eight lines between them, reflecting the mechanical and electrical density behind the ceilings. The two provisional-sum packages, WP-06 and WP-11, carry their lines as provisional quantities pending the tenant's reception and AV decisions.

A fixed schedule, not a supplier's take-off

Because the line count is fixed at sixty-eight, every priced return is read against the same schedule. A bidder cannot quietly re-measure the work to a lower quantity, and a line a bidder leaves blank is a compliance flag before it is a price, which is exactly what makes the four returns comparable.

02Sample

Inside the measure

A sample of the measured lines shows the level of definition supplied to the supply chain. Quantities are firm, units are stated, and each line carries its specification reference so a query resolves to a clause rather than a conversation.

Item Description Qty Unit Spec
02.01 Acoustic stud partition, Rw 42 dB 380 sq m A2.01
03.01 Aluminium-framed glazed partition, Rw 42 dB 96 sq m A2.06
04.01 Acoustic tile ceiling, concealed grid 1,420 sq m A3.01
05.01 Meeting-suite feature walls, fluted oak veneer 96 sq m A4.01
07.01 Carpet tile to open plan, all floors 1,280 sq m A5.01
09.01 Fan coil units, supply 21 nr M1.01
09.03 FCU installation, ceiling void 22 nr M1.01
10.01 Sub-mains and floor distribution boards 3 floor M2.01
01.01 Soft strip and removal, all floors 3 floor A1.01
02.03 Single-leaf acoustic doorset, Rw 42 dB 24 nr A2.03
05.03 Tea-point joinery run, solid-surface top 6 nr A4.03
08.01 Emulsion to walls, two coats 4,600 sq m A6.01
09.07 Grilles and diffusers, supply and install 44 nr M1.03
10.05 Recessed luminaires, 420 lux design 168 nr M2.03
03Trace

Every line traces both ways

The Bill sits in the middle of a chain, not at the end of one. Upstream, each line references the specification clause that defines it; downstream, each line resolves to an order once priced. That two-way trace is what lets the Ledger reconcile every commitment to a measured line, and the Green Light gate confirm that no order exists without one.

Clause to line to order

The traceability rule is absolute: every specification clause resolves to a Bill line, every Bill line to an order, and every order back to a package. A commitment with no measured line behind it is flagged at the gate, not discovered on site.

The fourteen lines shown are a sample; the full schedule runs to sixty-eight, and the same discipline applies to every one. A firm quantity, a stated unit and a specification reference on each line is what turns a Bill from a wish list into a contract document the supply chain can be held to.

Reference NG-UPB-001Revision Rev 1Prepared by R. Ashby, BuiltAI