The Pre-Con Pack
The Pre-Con Pack™Stage 02 of 5 · Internal workflow
Specification and design intent · specification at 85%

An award becomes a specification the market can price

Fine Print turns the award into a specification the supply chain can price without guessing. Eleven packages, 148 clauses, each traced to a drawing and a standard, with the gaps logged rather than left to assumption. Alongside the what, Design Intent records the why, so the intent survives value engineering.

Client
Cushman Workplace
Architect
Trenholme Architects
M&E consultant
Lambourne Vance Engineers
Stage
02 of 5 · Fine Print
Prepared by
BuiltAI Intelligence Ltd
Reference
NG-PS-001

Illustrative example: fictional project and parties.

11Specification packages
148Specification clauses
85%Specification complete
8of 11 final or final draft
BuiltAI Intelligence Ltd · built-ai.ioNG-PC-S02 · Stage 02
01Spec

Eleven packages, 148 clauses, every one sourced

Fine Print decomposes the award into a specification the supply chain can price without guessing. The eleven work packages resolve into eleven specification packages and 148 clauses, each traced to a drawing and a standard. Four packages are Final and four are Final draft (eight of eleven). The remaining three statuses are SPC-A5 Carpet pending (75%), SPC-A7 Design pending (35%) and SPC-X1 Tenant blocked (25%).

Pkg Specification package Clauses Progress Status
SPC-A1 Demolition and strip-out 12 100% Final
SPC-A2 Internal partitions, doors and glazed screens 22 95% Final draft
SPC-A3 Suspended ceilings and acoustics 9 90% Final draft
SPC-A4 Joinery, meeting suites and tea points 18 100% Final
SPC-A5 Floor finishes 11 75% Carpet pending
SPC-A6 Wall finishes and decoration 8 100% Final
SPC-A7 L6 reception and feature joinery, PS 6 35% Design pending
SPC-M1 Mechanical, supplementary cooling 19 100% Final
SPC-M2 Electrical, lighting, power and data 21 92% Final draft
SPC-M3 Fire detection and compartmentation 14 90% Final draft
SPC-X1 Workplace AV, PS 8 25% Tenant blocked
Eleven packages, 8 of 11 final or final draft 148 85%
02Gaps

The gaps, logged, not assumed

A specification is only as good as its honesty about what is not yet resolved. Three packages have non-final statuses: SPC-A5 is Carpet pending at 75%, SPC-A7 is Design pending at 35% and SPC-X1 is Tenant blocked at 25%. Completeness is tracked by discipline, not just overall, so a single lagging package cannot hide inside a healthy average.

Architectural (A1 to A7)89%
Mechanical (M1)100%
Electrical (M2)92%
Fire (M3)90%
Workplace AV (X1)25%
Two packages block the enquiry

SPC-A7, the L6 reception, and SPC-X1, the workplace AV, are the two provisional sums held for tenant decisions. SPC-A5 is separately recorded as Carpet pending at 75%, so the table shows three non-final statuses.

03Intent

Design intent, and the samples that prove it

Alongside the what, Fine Print records the why. The Design Intent document captures twelve intent items so the reasoning survives value engineering, and the schedule lists six sample records (SMP-01, SMP-02, SMP-04, SMP-05, SMP-07 and SMP-08) plus the full-scale MU-01 mock-up (8 sq m), with the statuses shown in the table.

Ref Sample or mock-up Package For sign-off Status
SMP-01 Joinery oak veneer panel, book-matched, AA-grade SPC-A4 Fri 16 May Approved
SMP-02 Carpet tile, three options in two colourways SPC-A5 Mon 18 May In review
SMP-04 Wall paint scheme, five colours SPC-A6 Wed 14 May Approved
SMP-05 Lighting fittings, three options SPC-M2 Wed 20 May In review
SMP-07 Glazed partition system, Rw 42 dB SPC-A2 Wed 21 May Awaited
SMP-08 Manifestation pattern, three options SPC-A2 Fri 22 May Awaited
MU-01 Meeting-suite mock-up, full scale, 8 sq m A2, A4 Mon 9 Jun Booked
04Approvals

Who signs what, and by when

Ten approval items route to Cushman Workplace, the tenant and the architect, each with a required-by date and a stated consequence if missed. The Project Specification and the Design Intent document both issue on Friday 22 May, which releases the Stage 03 enquiry.

Ref Approval item Routed to Required by Status
AP-01 Joinery oak veneer specification and sample Cushman Workplace Fri 16 May Closed
AP-02 Carpet selection, one of three options Cushman and tenant Mon 18 May Booked
AP-03 L6 reception design intent brief Cushman and Wexley Mon 19 May Booked
AP-04 Workplace AV scope confirmation, RFI NG-014 Wexley IT Tue 20 May Scheduled
AP-06 Glazed partition acoustic spec, 42 dB Cushman and tenant Fri 22 May Expected
AP-09 Project Specification, full document Cushman Workplace Fri 22 May Scheduled
AP-05 Ceiling tile and grid specification, Class A Cushman Workplace Thu 15 May Closed
AP-07 Lighting scene and control philosophy Cushman and tenant Wed 20 May Booked
AP-08 Ironmongery suite and access control Cushman Workplace Thu 21 May Scheduled
AP-10 Design Intent document, 12 items Cushman and Wexley Fri 22 May Scheduled

Approvals are tracked by status as well as by item, so a single slow approver is visible before it becomes a programme risk. Two of the ten, the workplace AV scope and the L6 reception brief, are the tenant-routed items that gate the enquiry release, and both are the ones watched most closely.

Status Items Position
Closed2Signed and logged
Booked3Meeting or review set
Scheduled4Routed with a required-by date
Expected1Awaiting the sample return
All approvals10Two gate the enquiry release
The critical approval

Carpet selection, AP-02, gates the L6 sectional date. A slip in the sample sign-off slips the floor finish that follows the joinery, and with it the tightest sectional completion. It is booked for Monday 18 May.

AP-04, the workplace AV scope, and AP-03, the L6 reception brief, are the two tenant-routed items on the critical path; both are booked ahead of the Friday 22 May specification issue that releases the Stage 03 enquiry.

Reference NG-PC-S02Stage 02 of 5, Fine PrintFeeds Market Day, Stage 03