The Pre-Con Pack
The Pre-Con Pack™Stage 04 of 5 · Internal workflow
BoQ and procurement tracker · commitments live

Every order, every commitment, one reconciled position

The Ledger is the live procurement position: the Bill of Quantities priced back through returns, orders placed against the critical path, and every commitment reconciled to the trade budget. Nine packages awarded, two provisional sums held for a tenant decision, and the position is under budget.

Client
Cushman Workplace
Trade budget
£1,257,350
Committed
£1,229,000 · 2.3% under
Stage
04 of 5 · The Ledger
Prepared by
BuiltAI Intelligence Ltd
Reference
NG-UPB-001

Illustrative example: fictional project and parties.

£1,229,000Trade committed, recommended
−£28,350Under budget, 2.3%
9of 11 packages awarded
68BoQ lines tracked
BuiltAI Intelligence Ltd · built-ai.ioNG-PC-S04 · Stage 04
01Commit

The Bill of Quantities, priced back by package

The Ledger is the live procurement position: the Unpriced Bill of Quantities priced back through returns, and every commitment reconciled to the £1,257,350 trade budget. Nine packages are awarded at recommended prices, two provisional sums are held for a tenant decision, and the committed position is £28,350, or 2.3%, under budget.

WP Work package Lines Budget Committed Variance Status
WP-01 Strip-out and demolition 4 £86,400 £82,100 −£4,300 Ordered
WP-02 Internal partitions and doors 8 £198,200 £194,800 −£3,400 Ordered
WP-03 Glazed partitions 5 £64,500 £62,800 −£1,700 Ordered
WP-04 Suspended ceilings and acoustics 5 £72,800 £71,200 −£1,600 Ordered
WP-05 Joinery, meeting suites and tea points 8 £148,500 £146,200 −£2,300 Ordered
WP-06 L6 reception joinery, PS 3 £24,000 £23,800 −£200 Held, design lock
WP-07 Floor finishes 6 £94,300 £91,600 −£2,700 Ordered
WP-08 Wall finishes and decoration 5 £42,100 £41,400 −£700 Ordered
WP-09 Mechanical services 9 £218,400 £211,800 −£6,600 Ordered
WP-10 Electrical, lighting and data 12 £268,150 £264,800 −£3,350 Ordered
WP-11 Workplace AV, PS 3 £40,000 £38,500 −£1,500 Held, RFI NG-014
Trade packages £1,257,350 £1,229,000 −£28,350 9 awarded
02Orders

Orders placed against the critical path

The long-lead orders are placed first, each against the sectional date it protects rather than the general programme. The joinery and switchgear orders are already committed; the raised floor follows once the replacement-panel survey confirms the quantity.

Ref Order Supplier Value Status
LL-01 Meeting-suite joinery, WP-05 Ashworth Joinery £146,200 Ordered
LL-03 Switchgear and sub-mains, WP-10 Marlow Electrical £56,200 Ordered
WP-09 Mechanical services Hartwell Mechanical £211,800 Ordered
LL-04 Raised access floor, WP-07 Pennine Flooring £38,400 Survey stage
Where the saving sits

The £28,350 the trade packages came in under budget is carried to project contingency, reference CSR-001, not released. It is the buffer against the two provisional sums, the L6 reception and the workplace AV, that are still to be fixed.

03Provisional

Two provisional sums, one mock-up gate

Two packages remain provisional at the ledger stage, and both wait on a tenant decision rather than on the supply chain. The meeting-suite mock-up MU-01 is the gate that releases the joinery-adjacent scope: signed off, it confirms the fluted-oak specification, the AV channel detail and the lighting before the wider order is committed.

WP-06 · L6 receptionHeld for design lock in week 8. Provisional sum, no design issued at award.£24,000
WP-11 · workplace AVHeld on RFI NG-014. Tenant AV platform to be confirmed.£40,000
MU-01 · mock-upFull-scale meeting suite. Sign-off gate for the WP-05 order.8 sq m
04Reconcile

One reconciled position into the gate

The Ledger reconciles top to bottom before it hands to Green Light. The committed trade position, the saving held in contingency, and the fixed prelims add back to the £1,418,650 contract sum, so the pre-mobilisation gate inherits a single number it can trust rather than a spread of running totals.

Position Value
Trade committed, 9 awarded plus 2 provisional £1,229,000
Trade saving held, CSR-001 £28,350
Trade budget £1,257,350
Prelims, OH&P, contingency, fees, commissioning £161,300
Contract sum, excl VAT £1,418,650

The committed position splits into firm orders and held provisional sums, so the gate can see what is already contracted and what still turns on a tenant decision. Nine packages are ordered at firm prices; two are carried at their recommended figures pending the reception design lock and the AV platform confirmation.

Commitment Value Basis
Ordered, nine packages£1,166,700Firm orders placed
Held, two provisional sums£62,300At recommended, tenant decision
Trade committed£1,229,0009 awarded plus 2 provisional

Each provisional sum is held with an owner and a gate rather than left open, so a late tenant decision shows as a tracked exposure rather than a silent slip. The meeting-suite mock-up is the release gate for the joinery-adjacent scope, and RFI NG-014 is the release gate for the workplace AV.

Ref Decision needed Owner Gate
WP-06L6 reception design lockCushman and WexleyWeek 8
WP-11Workplace AV platform, RFI NG-014Wexley ITOrder-by held
MU-01Meeting-suite mock-up sign-offCushmanMon 9 Jun
Margin CockpitThe financial baseline and the trade saving held in contingency£1,418,650
Commercial Control KitThe contract, change position and sectional dates from day one11 packages
Dispatch DeskThe asset register and reactive data, once the building is liveat PC

Read top to bottom, the Ledger is one reconciled statement rather than a stack of running totals: the firm orders, the saving held in contingency, the two open tenant decisions and the downstream handovers all resolve to the same £1,418,650 contract sum. That is what lets Green Light open on a single trusted number, and the Margin Cockpit begin delivery without re-keying a figure from a spreadsheet. Nothing here is a forecast: every figure is a placed order, a signed contract term or a logged decision, which is what makes the position safe to build on.

What the gate inherits

Green Light reads this position, not the individual orders. Every commitment traces to a measured Bill line, the £28,350 saving is ring-fenced in contingency rather than released, and the two provisional sums are the only open items carried into the gate review.

Reference NG-PC-S04Stage 04 of 5, The LedgerFeeds Green Light, Stage 05