Pre-Con · The Ledger™ - Stage 04 · Worked example Northgate Chambers - Floors 4-6 Cat-B Fit-Out · Cushman Workplace · NG-2026-0042 · £1.42m
← Pre-Con Pack
BUILTAI
THE PRE-CON PACK™ STAGE 04 · THE LEDGER

The Ledger

Every line quantified. Every order committed.
The unpriced Bill of Quantities becomes the financial backbone of the project — every line item traceable to a specification clause, every procurement commitment tracked against budget. This is where pre-construction turns into commitment: orders placed, suppliers locked in, and the gap between target and actual begins to close.
Project
Northgate Chambers — Floors 4–6 Cat-B Fit-Out
Stage opened
Monday 8 June 2026 · Wk 7
Stage target close
Wednesday 17 June 2026 · End Wk 8
Owner
R. Ashby · Built AI QS / S. Okafor · Procurement Lead
Reference
NG-UPB-001 · 11 packages · 68 BoQ line items
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
PRE-CON WORKFLOW 1Day One 2Fine Print 3Market Day
4The Ledger
5Green Light CLIENT DELIVERABLES
PSSpec
DSWScope
DIDesign Intent
SEPEnquiries
UPBBoQ
PDPDelivery Plan
STAGE 04 PROGRESS

Procurement & Commitment Dashboard

End of week 8 snapshot. Orders placed for long-lead items, remaining evaluations completing, procurement tracker live showing commitment against budget.

ORDERS PLACED
7 of 11
4 remaining: WP-06, WP-08, WP-11, WP-01
COMMITTED VALUE
£1.09m
76.9% of contract sum placed
VS BUDGET
−2.4%
£30,470 below target aggregate
BOQ LINE ITEMS
68
across 11 packages · UPB issued
MOCKUP MU-01
Signed off Mon 9 Jun 2026

Commitment vs Contract Sum

£1,418,650
Placed £768,900
Eval £321,250
Pend £67,200
Prelims £161,300
Orders placed (54%)
Evaluating / award imminent (23%)
Pending design / scope lock (5%)
Prelims / OH&P (11%)
Uncommitted float (7%)
UPB
CLIENT DELIVERABLE
Unpriced Bill of Quantities
68-line structured BoQ derived from the 11 work packages, each line traceable to a specification clause. Issued unpriced to Cushman; priced version maintained internally.
NG-UPB-001-Rev1 Issued: Fri 12 Jun 2026
PT
INTERNAL REGISTER
Procurement Tracker — Live
Real-time status of all 11 packages showing enquiry → evaluation → order → manufacture → delivery against the construction programme.
NG-PT-001-Live Updated daily by S. Okafor
UNPRICED BILL OF QUANTITIES

BoQ Extract — Summary by Package

The full BoQ has 68 line items across 11 packages. Below is the summary extract showing each package total with committed value and variance. The full BoQ (NG-UPB-001) is issued to Cushman Workplace as the Unpriced Bill of Quantities client deliverable.

NG-UPB-001 — Unpriced Bill of Quantities (Summary Extract) Rev 1 · 12 Jun 2026
WP Work Package BoQ Lines Target Committed Variance Order Status
WP-01 Strip-out & Demolition 3 floors, phased L6→L5→L4, licensed waste 4 £86,400 £84,200 −£2,200 Ordered
WP-02 Internal Partitions & Doors Stud + acoustic, door sets, ironmongery 8 £198,200 £192,600 −£5,600 Ordered
WP-03 Glazed Partitions Aluminium, fire-rated at compartment, manifestation 5 £64,500 £63,100 −£1,400 Ordered
WP-04 Suspended Ceilings & Acoustics Tile grid, exposed soffit, acoustic access panels 5 £72,800 £71,400 −£1,400 Ordered
WP-05 Joinery — Meeting Suites & Tea Points Fluted oak, tea points, storage, AV channels 8 £148,500 £146,200 −£2,300 Ordered · Holroyd
WP-06 L6 Reception Joinery (PS) Reception desk, feature wall, low-level seating 3 £24,000 Design lock Wk 8 Pending
WP-07 Floor Finishes Carpet tile, vinyl, raised access floor panels 6 £94,300 £91,800 −£2,500 Ordered · Threshold
WP-08 Wall Finishes & Decoration Paint, vinyl, feature finishes, manifestation 5 £42,100 Accent TBC Wk 9 Pending
WP-09 Mechanical Services FCUs, ductwork, condensate, BMS interface 9 £218,400 £211,600 −£6,800 Ordered
WP-10 Electrical, Lighting & Data Sub-mains, lighting, power, Cat6A, BMS 12 £268,150 £262,400 −£5,750 Ordered · Marlow
WP-11 Workplace AV (PS) Displays, video bars, ceiling mics, control 3 £40,000 Returns 12 Jun Evaluating
SUB-TOTAL — TRADE PACKAGES 68 £1,257,350 £1,123,300 −£27,950
PRL Prelims, OH&P, Contingency, Fees, Commissioning £161,300 £161,300 £0 Fixed
CONTRACT SUM TOTAL 68 £1,418,650 £1,284,600 −£27,950 90.5% placed / eval

Net procurement variance of −£27,950 (−2.2% below target aggregate) across the 7 committed packages. This gives the project a pre-mobilisation margin uplift of £27,950 vs the original contract sum analysis. Variance is tracked at BoQ line-item level in the live procurement tracker, not just at package level.

ORDER LOG

Orders Placed — Long-Lead & Critical Path

Seven orders placed covering all long-lead items and the high-value trade packages. Each order card shows the supplier, committed value, variance vs target, order date, and manufacturing milestones.

WP-05 · LL-01 · SEP-05

Holroyd & Sons Joinery Ltd

£146,200
−1.5% vs target
ORDER DATE
Wed 4 Jun 2026
MANUFACTURE
10 wks · Bolton yard
SITE DELIVERY
Wk 16 · 7 Sep
BOND
10% on demand — issued
WP-10 · LL-03 · SEP-10

Marlow Electrical Services Ltd

£262,400
−2.1% vs target
ORDER DATE
Wed 11 Jun 2026
SWITCHGEAR
9 wks via Edmundson
SITE START
Wk 13 · 18 Aug
BOND
10% on demand — issued
WP-07 · LL-04 · SEP-07

Threshold Floors NW Ltd

£91,800
−2.7% vs target
ORDER DATE
Wed 11 Jun 2026
RAISED FLOOR
6 wks · stock confirmed
CARPET DELIVERY
Wk 15 · 1 Sep
BOND
Not required (<£100k)
WP-09 · SEP-09

Atherton Mechanical Services Ltd

£211,600
−3.1% vs target
ORDER DATE
Fri 13 Jun 2026
FCU DELIVERY
5 wks · Daikin stock
SITE START
Wk 12 · 11 Aug
BOND
10% on demand — requested
WP-02 · SEP-02

Ringway Interiors Ltd

£192,600
−2.8% vs target
ORDER DATE
Fri 13 Jun 2026
LEAD TIME
4 wks · material order
SITE START
Wk 11 · 4 Aug
BOND
10% on demand — issued
WP-03 · SEP-03

Optima Systems Ltd

£63,100
−2.2% vs target
ORDER DATE
Mon 15 Jun 2026
LEAD TIME
5 wks · inc. Pyrobel 30
SITE START
Wk 12 · 11 Aug
BOND
Not required (<£100k)
WP-04 · SEP-04

Solebury Ceilings Ltd

£71,400
−1.9% vs target
ORDER DATE
Mon 15 Jun 2026
LEAD TIME
4 wks · acoustic panels spec'd
SITE START
Wk 13 · 18 Aug
BOND
Not required (<£100k)
WP-01 · SEP-01

Clearsite Demolition Ltd — Order pending

£84,200
−2.5% vs target
TARGET ORDER
Wk 11 · 9 Jul
LEAD TIME
2 wks mobilisation
SITE START
Wk 13 · 22 Jul
NOTE
Aligns with site possession

8 of 11 orders committed or pending. WP-06 (L6 reception, £24k PS) — design lock received 16 Jun, enquiry issuing Wk 9. WP-08 (wall finishes accent) — manifestation decision received 14 Jun, combined into main WP-08 order Wk 9. WP-11 (AV, £40k PS) — 4 specialist returns received 12 Jun, evaluation in progress, target order Wk 9.

PROCUREMENT GATE EVENT

Mock-Up MU-01 — Sign-off

Full-scale meeting suite mock-up reviewed at Holroyd's Bolton facility Monday 9 June 2026. This was the procurement gate event — sign-off releases the joinery order for production.

Meeting Suite Mock-Up · MU-01

Holroyd & Sons Bolton Facility · Mon 9 Jun 2026, 10:00–12:30 · Attendees: D. Marchetti, A. Pereira, P. Sandhu (Cushman), G. Trenholme, N. Bramwell (AV)

Review Items

8 m² mock-up comprising glazed partition section, oak veneer feature wall with AV channel, ceiling tile and lighting, door set with ironmongery, and carpet transition.

Oak veneer fluting — profile and grain match Book-matched panels reviewed. Fluting depth 12mm at 40mm centres confirmed. Grain match consistent with SMP-01.
AV cable channel — access and dimensions 80 × 50mm channel with low-level lockable access panel. Confirmed fit for 4× HDMI + 2× Cat6A + power. N. Bramwell approved.
Glazed partition acoustic performance On-site decibel test with conversation at normal volume behind partition. Result: Rw 43 dB measured (spec 42 dB). Privacy acceptable for client meetings.
Door set — seal, closer, ironmongery Solid core veneered door with magnetic seal, brushed brass lever set. Close action reviewed — soft-close. Approved.
Lighting integration — ceiling junction Suspended linear fitting aligned to 1200 × 600 ceiling grid. No visible clash. Fitting height 2.65m — acceptable.
Floor transition — carpet to vinyl Transition strip at door threshold reviewed. Flush aluminium trim — no trip hazard. Approved per DDA compliance.
Manifestation — frosted gradient Applied to mock-up glazing panel. Standing-height privacy effective. Brand team confirmed at acceptable density. Approved.
Joinery-to-wall finish junction Shadow gap 6mm between oak panel and plaster wall. Clean, consistent — no filler, no visible silicone. Approved.
MU-01 SIGNED OFF — 9 Jun 2026, 12:30 All 8 review items approved. No remedial actions. Joinery order released to Holroyd for factory production. Mock-up retained at Bolton as the on-site comparator — delivery to NG site Wk 16 for permanent reference panel install.
Built AI: D. Marchetti Cushman: P. Sandhu Architect: G. Trenholme
STAGE 04 GATE

Stage 04 — Sign-off & Handover to Stage 05

Stage 04 closes when the unpriced BoQ is issued, all long-lead orders are placed, the procurement tracker is live, and commitment vs budget gives a clear picture of the project's financial starting position.

Stage 04 Gate — The Ledger Target close Wed 17 June 2026 · 17:00 · 2 days before site possession
SIGNED OFF
Unpriced BoQ issued — 68 line items NG-UPB-001 Rev 1 issued to Cushman 12 Jun. Traceable to spec clauses, DSW packages and enquiry returns.
7 of 11 orders placed All 4 long-lead items committed. Strip-out order pending (Wk 11 — aligned with possession). 3 packages evaluating / pending.
Committed value 90.5% of contract sum £1,284,600 placed or in evaluation. Net variance −£27,950 (−2.2%) below target. Margin position strong.
Mock-up MU-01 signed off Full-scale meeting suite mock-up approved 9 Jun. All 8 items passed. Joinery released to production.
Procurement tracker live NG-PT-001 updated daily by Procurement Lead. Covers enquiry → order → manufacture → delivery → install tracking.
Risk register updated — end Stage 04 R-02 joinery now green (ordered). R-04 reception now amber (design lock received, enquiry issuing). R-01 AV now amber (returns in, evaluating).
Performance bonds received 4 bonds at 10% received (Holroyd, Marlow, Atherton, Ringway). Below-threshold packages bonded via parent company guarantees where available.
Subcontract documentation issued JCT SBC/Sub 2016 (D&B) sub-contracts issued to all 7 awarded suppliers. Executed copies returned from 5 of 7.
QUANTITY SURVEYOR
R. Ashby
Built AI Commercial
16 Jun 2026, 14:22
PROCUREMENT LEAD
S. Okafor
Built AI Procurement
16 Jun 2026, 15:40
PRE-CON LEAD
D. Marchetti
Built AI Pre-Con Office
17 Jun 2026, 09:08
Handover note to Stage 05 — Green Light Stage 05 opens Wed 17 June 2026. This is the final QA pass before handing the project to the delivery team. Inputs: all 5 client deliverables (PS, DSW, DI, SEP, UPB), plus the live procurement tracker and risk register. The QA gate checks: every specification clause traces to a BoQ line, every BoQ line traces to an order, every order is programme-compliant, and the financial baseline is clean enough for Margin Cockpit to inherit. Three items still need closure: WP-06 reception order (due Wk 9), WP-11 AV order (due Wk 9), WP-08 accent finishes order (due Wk 9). Delivery plan (PDP) drafted alongside Stage 05 QA and issued as the sixth client deliverable at handover.
BuiltAI
THE LEDGER — SNAPSHOT

Orders placed. Budget holding.

A project that enters site with structured procurement — orders placed against like-for-like evaluations, commitment tracked against budget at line-item level, bonds secured, sub-contracts issued — starts construction from a position of financial control. The pre-mobilisation margin uplift of £27,950 is the first result the Margin Cockpit will inherit.

ORDERS PLACED
7
COMMITTED VALUE
£1.09m
VS TARGET
−2.2%
BOQ LINES
68