Pre-Con · Project Delivery Plan (PDP) · Worked example Northgate Chambers - Floors 4-6 Cat-B Fit-Out · Cushman Workplace · NG-2026-0042 · £1.42m
← Pre-Con Pack
BUILTAI
THE PRE-CON PACK™ · CLIENT DELIVERABLE
PDP · Project Delivery Plan

Project Delivery Plan

How this project gets delivered — programme, milestones, logistics, commissioning, risk transfer and the handover from pre-con to the delivery team. The bridge between planning and doing.
Project
Northgate Chambers — Floors 4–6 Cat-B Fit-Out
Reference
NG-PDP-001 · Revision 1
Prepared by
Built AI Ltd · D. Marchetti (Pre-Con Lead)
Issue date
Friday 19 June 2026
Issued to
Cushman Workplace · Halberd Properties · Built AI Delivery Team
Status
Approved — Green Light™ gate passed 19 Jun 2026
built-ai.io · hello@built-ai.io © 2026 Built AI Ltd BUILT AI
01 · PROGRAMME OVERVIEW

14 Weeks On Site — Three Phases

The construction programme runs from site possession on Monday 22 June 2026 to Practical Completion on Friday 25 September 2026. The project is structured as three overlapping phases with sectional completion — L6 (reception floor) completes first, then L5, then L4. This allows the tenant's London-to-Manchester migration to begin in parallel with ongoing works on lower floors.

PHASE 1 — STRIP & STRUCTURE

Demolition & First-Fix

Wk 1–8 · 22 Jun – 14 Aug

Strip-out (phased L6→L5→L4), partition first-fix, M&E first-fix. Concurrent working once L6 strip-out complete. Long-lead deliveries arrive: joinery Wk 8, switchgear Wk 9, raised floor Wk 7.

PHASE 2 — BUILD & CLOSE

Second-Fix & Finishes

Wk 9–14 · 18 Aug – 25 Sep

Ceilings, joinery install, M&E second-fix, lighting, floor finishes, paint, AV install. Sectional completions: L6 Wk 11, L5 Wk 13, L4 Wk 14. Commissioning runs concurrent with finishes.

PHASE 3 — COMMISSION & HAND OVER

Testing, Snagging & Handover

Wk 12–14 · 8 Sep – 25 Sep

M&E commissioning (witnessed), BMS integration with landlord, AV configuration, snagging, O&M documentation, tenant walkdown, handover. PC certificate issued 25 Sep.

02 · KEY MILESTONES

12 Milestones — Contractual & Operational

MSMilestoneDateWeekType
MS-01Site possessionMon 22 JunWk 1Contractual
MS-02L6 strip-out completeFri 26 JunWk 1Operational
MS-03All floors strip-out completeFri 10 JulWk 3Operational
MS-04Joinery delivery to site (LL-01)Mon 17 AugWk 9Long-lead
MS-05Switchgear delivery (LL-03)Mon 24 AugWk 10Long-lead
MS-06L6 M&E commissioning — witnessedFri 28 AugWk 10Operational
MS-07L6 Sectional CompletionFri 7 AugWk 7Contractual
MS-08L5 M&E commissioning — witnessedFri 11 SepWk 12Operational
MS-09L5 Sectional CompletionFri 4 SepWk 11Contractual
MS-10BMS integration with landlord systemFri 18 SepWk 13Operational
MS-11O&M documentation issuedWed 23 SepWk 14Operational
MS-12Practical Completion (L4)Fri 25 SepWk 14Contractual

Sectional completion LDs: £8,500 per working day per section. Tenant move-in scheduled Mon 12 October 2026 (2-week buffer post-PC for cleaning, FF&E install and IT migration).

03 · SITE LOGISTICS & COORDINATION

Operating in a Live Building

Floors 1–3 remain occupied by existing tenants throughout the project. All logistics must work within the constraints of a live, occupied commercial building with a single goods lift and shared loading bay. These constraints are contractual — breach of noise or access protocols triggers the landlord's step-in clause.

WORKING HOURS
07:30–18:00 Mon–Fri. No weekend working without Building Manager approval (14-day notice).
NOISY WORKS
10:00–16:00 Mon–Fri only. Cutting, drilling, impact works. Noise monitoring at L3 ceiling level — max 75 dB LAeq,1hr.
GOODS LIFT
48-hour advance booking via Building Manager. 1,200 kg capacity, 1.6m × 2.4m car. No exclusive use — shared with landlord & existing tenants.
LOADING BAY
Northgate Yard — 30-minute slot booking. Max vehicle: 7.5t rigid. No articulated vehicles. Skip location confirmed (permit obtained).
RISER ACCESS
Coordinated with Building Manager. 2-hour shutdown window per floor for CHW and electrical tie-ins. 7-day notice required.
TENANT NOTIFICATIONS
48-hour advance notice of noisy works per floor. Issued by Built AI Site Manager to Building Manager for cascade to L1–L3 tenants.
FIRE STRATEGY
Existing fire systems maintained in common areas. Temporary detection on L4–L6 during works. Hot-work permits per Built AI RAMS.
WASTE MANAGEMENT
Licensed waste carrier — segregated disposal (plasterboard, metal, timber, general). Duty of care documentation per WP-01 scope.
04 · COMMISSIONING & HANDOVER

Test, Commission, Snag, Hand Over

Commissioning is phased to align with sectional completion. L6 commissions first (Wk 10), L5 next (Wk 12), L4 last (Wk 13–14). Each floor follows a four-step sequence: M&E testing, BMS point-to-point, snagging walkdown, handover sign-off.

StepActivityResponsibilityWitnessOutput
C1M&E testing — dead and liveAtherton Mech / Marlow ElecLambourne VanceTest certificates (BS 7671, F-Gas)
C2BMS point-to-point — tenant systemAtherton Mech (BMS integrator)Lambourne VanceBMS point schedule (verified)
C3BMS integration — landlord Trend IQ4Atherton + Landlord BMS operatorHalberd PropertiesIntegration sign-off
C4AV system configuration & testingVisualis AVWexley IT (N. Bramwell)Room-by-room AV test report
C5Lighting control commissioningMarlow Elec (DALI programmer)Lambourne VanceLux level survey, scene schedule
C6Snagging walkdown — per floorBuilt AI Site ManagerCushman WorkplaceSnagging list (target: ≤20 items/floor)
C7O&M documentation issueBuilt AI Doc Control2× hard copy + digital (PDF + native)
C8Practical Completion sign-offBuilt AI / Cushman / HalberdContract AdministratorPC certificate
05 · TOP DELIVERY RISKS

6 Risks Transferred from Pre-Con to Delivery

These risks were identified during the Pre-Con Pack workflow and are now transferred to the delivery team with mitigations in place. The full risk register (11 items) is maintained in the Stage 05 (Green Light™) internal workflow document.

RiskDescriptionImpactMitigationOwner
R-01Joinery long-lead (10–12 wk) delays programmeHighOrder placed 13 Jun. Factory pre-fit visit Wk 6. Weekly progress photo from Holroyd. Buffer: 1 week built into programme.Pre-Con / Procurement
R-03Landlord CHW capacity — late confirmation delays M&E first-fixMediumLetter of comfort received 18 Apr. Follow-up confirmation due Wk 8. Fallback: temporary cooling if delayed beyond Wk 12.Site Manager / QS
R-05Goods lift availability — shared access limits material delivery throughputMediumAdvance booking protocol (48hr). Bulk deliveries scheduled for early morning (07:30–09:00) before existing tenants' peak. Joinery delivery via external hoist if lift unavailable.Site Manager
R-07Noise complaints from L1–L3 tenants trigger landlord step-inMediumNoise monitoring installed. Restricted hours enforced (10:00–16:00). 48hr advance notification protocol. Building Manager relationship managed weekly.Site Manager
R-09Raised access floor — replacement rate exceeds 15% estimateMediumSurvey complete (14 May) — 13% measured, 2% contingency. If exceeded: Threshold Floors NW confirmed 4-day lead on additional panels. Budget: provisional allowance held.QS
R-11AV integration with tenant London HQ — network config delaysMediumN. Bramwell (Wexley IT) confirmed Zoom Rooms platform 27 May. Network switching tenant-direct (excluded from scope). Pre-config session booked Wk 16.Visualis AV / Wexley IT
06 · CROSS-WORKFLOW HANDOVER

What Feeds the Other Built AI Packs

The Pre-Con Pack outputs don't end at mobilisation. They become the baseline data for three downstream Built AI workflow packs. This section maps what goes where — so the delivery team knows which documents are live inputs to other workflows, not just archived records.

RAMS Factory™
Pack 03 · Red · Site documentation
The DSW scope entries, PDP logistics constraints and Project Specification become the source documents for method statements, risk assessments, lift plans and hot-work permits. The noise restrictions (10:00–16:00), riser shutdown protocol and goods lift constraints all feed directly into RAMS content.
Feeds: NG-DSW-001, NG-PDP-001 §03, NG-PS-001
Commercial Control Kit™
Pack 04 · Green · Entitlement & variation
The Project Specification, DSW exclusions and Unpriced BoQ become the contract baseline against which change is measured. Every exclusion in the DSW is a potential variation trigger. Every specification clause is the "what was agreed" reference point for entitlement narratives.
Feeds: NG-PS-001, NG-DSW-001 (exclusions), NG-UPB-001
Margin Cockpit™
Pack 05 · Purple · Margin tracking
The Unpriced BoQ (with internal pricing) becomes the budget baseline for monthly margin tracking. The procurement tracker from Stage 04 (The Ledger™) feeds committed supplier values. The PDP programme milestones feed the earned-value calculation. Together they give the Margin Cockpit its starting position from day one.
Feeds: NG-UPB-001, Procurement Tracker (Stage 04), NG-PDP-001 §02

Disclaimer: This Project Delivery Plan has been produced by Built AI Ltd and represents the planned delivery approach as at the Green Light™ gate date (19 June 2026). The programme, milestones and logistics are subject to change during construction. Risk mitigations are based on current information and may require adaptation. This document does not replace the contractor's obligations under the building contract (JCT D&B 2016) or under CDM 2015.

BuiltAI
PROJECT DELIVERY PLAN — THE PRE-CON PACK™ COMPLETE

From award to mobilisation. Done.

This is the final deliverable of the Pre-Con Pack. The project now has its specification, its scope, its design intent, its supply chain, its BoQ, and its delivery plan — all source-traced, all cross-referenced, all signed off. The Green Light gate is passed. Site gets the go-ahead.
MILESTONES
12
CONSTRUCTION
14wk
RISKS TRANSFERRED
11
WORKFLOWS FED
3
built-ai.io · The Pre-Con Pack™ · PDP · Project Delivery Plan © 2026 Built AI Ltd · NG-PDP-001 Rev 1