The Pre-Con Pack
The Pre-Con Pack™Pack 02 / 06 · Client deliverable
Project delivery plan · Rev 1, 14 weeks on site

Fourteen weeks, three phases, three sectional dates

The Project Delivery Plan is what the site team inherits: a 14-week programme in three phases, twelve milestones, the constraints of working in a live building, the commissioning and handover sequence, and the six risks transferred from Pre-Con.

Client
Cushman Workplace
Programme
14 weeks · 3 phases
Possession
Mon 22 Jun 2026
Practical completion
Fri 25 Sep 2026
Prepared by
BuiltAI Intelligence Ltd
Reference
NG-PDP-001

Illustrative example: fictional project and parties.

14Weeks on site
12Milestones
3Sectional completions
6Risks transferred in
BuiltAI Intelligence Ltd · built-ai.ioNG-PDP-001 · Rev 1
01Programme

Fourteen weeks, twelve milestones

The Project Delivery Plan is what the site team inherits: a 14-week programme in three phases, with twelve milestones from site possession on Monday 22 June to practical completion on Friday 25 September. Three of the milestones are contractual sectional dates, each carrying its own liquidated-damages exposure.

MS Milestone Date Week Type
MS-01 Site possession Mon 22 Jun 1 Contractual
MS-02 L6 strip-out complete Fri 26 Jun 1 Operational
MS-03 All floors strip-out complete Fri 10 Jul 3 Operational
MS-04 M&E first-fix complete, all floors Fri 24 Jul 5 Operational
MS-05 Joinery delivery to site, LL-01 Mon 27 Jul 6 Long-lead
MS-06 Switchgear energised, LL-03 Fri 31 Jul 6 Long-lead
MS-07 L6 sectional completion Fri 7 Aug 7 Contractual
MS-08 L5 fit-out and commissioning complete Fri 28 Aug 10 Operational
MS-09 L5 sectional completion Fri 4 Sep 11 Contractual
MS-10 BMS integration with landlord Trend IQ4 Fri 18 Sep 13 Operational
MS-11 O&M documentation issued Wed 23 Sep 14 Operational
MS-12 Practical completion, L4 Fri 25 Sep 14 Contractual
02Live building

Commissioning in an occupied building

Floors 1 to 3 are occupied by other tenants throughout, so the plan is written around the building, not just the floorplate. Noisy works are restricted to 10:00 to 16:00, the shared goods lift runs to a 48-hour booking protocol, and commissioning follows a witnessed sequence with a named responsibility and output at each step.

Step Activity Responsibility Output
C1 M&E testing, dead and live Hartwell Mechanical, Marlow Electrical Test certificates, BS 7671, F-gas
C2 BMS point-to-point, tenant system Hartwell Mechanical Verified BMS point schedule
C3 BMS integration, landlord Trend IQ4 Hartwell and landlord operator Integration sign-off
C4 AV configuration and testing Kinetic AV Room-by-room AV test report
C5 Lighting control commissioning Marlow Electrical Lux survey, scene schedule
C6 Snagging walkdown, per floor BuiltAI site manager Snagging list, target 20 or fewer per floor
C7 O&M documentation issue BuiltAI document control Two hard copies plus digital
C8 Practical completion sign-off BuiltAI, Cushman, Halberd PC certificate
03Risks

Six risks, transferred with mitigations

Six of the eleven risks opened at award transfer to delivery, each with the mitigation carried across rather than restated. The plan also names what feeds the other BuiltAI packs: the financial baseline into the Margin Cockpit, the contract and change position into the Commercial Control Kit, and the asset and reactive data into the Dispatch Desk once the building is live.

Risk Description Mitigation carried across
R-01 Joinery long-lead versus programme Ordered, factory pre-fit in week 6, one-week buffer
R-03 Landlord CHW capacity confirmation Letter of comfort held, fallback temporary cooling
R-05 Sectional LD exposure Float protected, sectional dates tracked weekly
R-07 Noise complaints from L1 to L3 Monitoring installed, hours enforced, 48-hour notice
R-09 Raised floor replacement rate Survey at 13% measured, 2% contingency held
R-11 AV integration with tenant network Platform confirmed, tenant-direct switching excluded
Feeds What the Delivery Plan hands across
Margin CockpitThe financial baseline: budget, committed cost and the headroom held
Commercial Control KitThe contract and change position, sectional dates and LD exposure
Dispatch DeskThe asset register and reactive data, once the building is live

The Delivery Plan is the last Pre-Con document and the first live one: the same figures that closed procurement open the build, so nothing is re-keyed and nothing is lost at the handover.

Reference NG-PDP-001Revision Rev 1, issued Fri 19 Jun 2026Possession to PC 22 Jun to 25 Sep