Every compensation event, in one register
The live register of every compensation event on this project - detected, classified, notified, valued, and agreed or in progress. The single source of truth from which the notice tracker, variation narratives, valuations and monthly submissions are derived.
- Project
- Crestfield Distribution Centre, Warrington
- Contract
- NEC4 ECC Option A · £3,814,200
- Reference
- CRE-CEL-001 · Period 7
- Reporting date
- Friday 22 May 2026
- Prepared by
- BuiltAI Intelligence Ltd · J. Navarro
- Issued to
- Kelbrook Construction Ltd · Alder Cost Consultants (PM)
Illustrative example: fictional project and parties.
The change event register - all 14 events
Captures every compensation event from contract commencement (3 November 2025) to the reporting date (22 May 2026). This is the single register from which every downstream commercial document is derived. Status: 8 agreed, 4 submitted, 2 in prep, 0 time-barred.
| CE | Description | Clause | Source | Notified | Value | Prog. | Status |
|---|---|---|---|---|---|---|---|
| CE-001 | Additional fire-rated cable penetration seals - 14 at compartment walls | § 60.1(1) | PMI-012 | 19 Nov | £8,200 | Nil | Agreed |
| CE-002 | Revised BMS point schedule - 34 additional points | § 60.1(1) | PMI-018 | 4 Dec | £14,600 | Nil | Agreed |
| CE-003 | Late access to HV substation - 3-week delay | § 60.1(5) | Site rec. | 13 Dec | £41,800 | +3 wks | Agreed |
| CE-004 | Unmapped gas main in cable-trench zone - diversion | § 60.1(12) | Site rec. | 9 Jan | £22,400 | +1 wk | Agreed |
| CE-005 | PM stop instruction - archaeological find, Zone C, 6 days | § 60.1(3) | PMI-024 | 15 Jan | £16,800 | +1 wk | Agreed |
| CE-006 | EV charging upgrade - 12 points, 22kW AC to 50kW DC | § 60.1(1) | PMI-031 | 3 Feb | £38,200 | Nil | Agreed |
| CE-007 | Late issue of revised ventilation design (Rev C) - near-miss on notice | § 60.1(5) | Prog. | 11 Apr | £18,400 | +2 wks | Agreed |
| CE-008 | Additional external lighting columns - 8 to the car park extension | § 60.1(1) | PMI-036 | 7 Mar | £25,800 | Nil | Agreed |
| CE-009 | HV switchgear design change - 11kV to 33kV per revised DNO agreement | § 60.1(1) | PMI-047 | 26 Mar | £43,039 | +1.5 wks | Submitted |
| CE-010 | Concealed asbestos in riser duct - diversion and licensed removal | § 60.1(12) | Site rec. | 9 Apr | £12,400 | +0.5 wk | Submitted |
| CE-011 | Late power-on date from DNO - 4-week delay to permanent connection | § 60.1(5) | DNO ltr. | 15 Apr | £18,200 | +4 wks | Submitted |
| CE-012 | Additional emergency lighting to mezzanine - 16 fittings, fire officer | § 60.1(1) | PMI-052 | 23 Apr | £7,800 | Nil | Submitted |
| CE-013 | Fire alarm panel relocation - structural clash, relocate 4m | § 60.1(1) | PMI-055 | 7 May | £12,200 | Nil | In prep |
| CE-014 | Late landlord BMS integration spec - affects commissioning | § 60.1(5) | Prog. | 13 May | £20,600 | TBC | In prep |
| Total - 14 compensation events | £300,439 | Agreed: £186,200 | |||||
Selected updates and prior history
Recorded updates for review against Period 6 (24 April 2026). The rows show full event values, not value changes; CE-008's agreement predates the review window.
| Movement | CE | Detail | Event value |
|---|---|---|---|
| Agreed | CE-007 | Late ventilation design - agreed by the PM on 19 May at submitted value | £18,400 |
| Agreed pre-window | CE-008 | External lighting columns - agreed by the PM on 10 Apr at submitted value | £25,800 |
| Submitted | CE-012 | Emergency lighting to mezzanine - quotation submitted 14 May | £7,800 |
| New | CE-013 | Fire alarm panel relocation - detected 6 May, notified 7 May | £12,200 |
| New | CE-014 | Late BMS integration spec - detected 12 May, notified 13 May | £20,600 |
| Recorded pipeline difference (£215,639 to £300,439) - basis unreconciled | +£84,800 | ||
The five full event values total £84,800, including prior history and status changes; only two events are new (£32,800). Previous values or revaluations are not supplied, so these rows do not establish £84,800 pipeline growth.
Where the change comes from
The largest source of change is PM instructions changing Scope (clause 60.1(1)) - 7 events totalling £149,839. The second is late employer provision (clause 60.1(5)) - 4 events totalling £99,000. This pattern is typical where the employer's design is still evolving mid-construction. The data feeds the monthly commercial review and the risk discussion with Kelbrook Construction.