Commercial Control · Notice Tracker (NT) · Worked example Crestfield Distribution Centre - Phase 2 M&E · NEC4 ECC Option A · CE-009 threaded · Period 7 · £3.81m
← CCK Pack
COMMERCIAL CONTROL KIT™ · CLIENT DELIVERABLE
NT · Notice Tracker

Notice Tracker

Every notice window tracked. Every deadline visible. Every response logged. The contract-aware tracker that ensures no entitlement is lost to a missed clock.
Project
Crestfield Distribution Centre — Phase 2 M&E Infrastructure
Reference
CRE-NT-001 · Period 7
Prepared by
Built AI Ltd · J. Navarro
Reporting date
Friday 22 May 2026
built-ai.io Pack 04 / 09 · Commercial Control Kit™ · © 2026 Built AI Ltd BUILT AI
NEC4 NOTICE WINDOWS

Four Deadlines per Compensation Event

Each compensation event triggers up to four contractual notice windows. Missing any one can weaken or destroy the entitlement. This tracker monitors all four simultaneously across all 14 active CEs.

61.3

CE Notification

8 weeks

From awareness. Miss it = time-barred.

61.4

PM Response

1 week

PM must respond to notification.

62.3

Quotation

3 weeks

Contractor submits quotation.

62.6

Deemed Acceptance

2 weeks

PM must respond or quotation accepted.

COMPLETE NOTICE RECORD

14 CEs — Every Date Logged

CEAwareEW61.3 Notified61.3 Expiry61.4 PM Resp62.3 Quote Req62.3 Quote Sub62.6 PM Due62.6 PM DecisionNotice
CE-00118 Nov18 Nov19 Nov14 Jan24 Nov ✓24 Nov10 Dec24 Dec18 Dec ✓OK
CE-0023 Dec3 Dec4 Dec28 Jan9 Dec ✓9 Dec23 Dec6 Jan8 Jan ✓OK
CE-00312 Dec12 Dec13 Dec6 Feb18 Dec ✓18 Dec9 Jan23 Jan22 Jan ✓OK
CE-0048 Jan8 Jan9 Jan5 Mar15 Jan ✓15 Jan3 Feb17 Feb14 Feb ✓OK
CE-00514 Jan14 Jan15 Jan11 Mar21 Jan ✓21 Jan6 Feb20 Feb19 Feb ✓OK
CE-0062 Feb2 Feb3 Feb30 Mar10 Feb ✓10 Feb27 Feb13 Mar12 Mar ✓OK
CE-00718 Feb11 Apr15 Apr16 Apr ✓16 Apr6 May20 May19 May ✓Near
CE-0086 Mar6 Mar7 Mar1 May13 Mar ✓13 Mar28 Mar11 Apr10 Apr ✓OK
CE-00924 Mar25 Mar26 Mar19 May28 Mar ✓28 Mar8 Apr22 Aprpending62.6
CE-0108 Apr8 Apr9 Apr4 Jun15 Apr ✓15 Apr1 May15 MaypendingDue
CE-01114 Apr14 Apr15 Apr10 Jun22 Apr ✓22 Apr8 May22 MaypendingDue
CE-01222 Apr22 Apr23 Apr18 Jun29 Apr ✓29 Apr14 May28 MaypendingDue
CE-0136 May6 May7 May1 Jul13 May ✓13 MayOK
CE-01412 May12 May13 May7 JulpendingOK
Active watch items: CE-009 — clause 62.6 deemed acceptance potentially triggered (PM response overdue since 22 Apr). Position reserved but cooperative response provided 14 May. CE-010, CE-011, CE-012 — PM responses due 15 May, 22 May, 28 May respectively. CE-014 — PM response to notification due 20 May.
NOTICE PERFORMANCE

Notification Discipline — Month 7

1.4
AVG DAYS TO NOTIFY
Target: <3 days
13/14
EARLY WARNINGS ISSUED
CE-007 missed (corrected)
0
TIME-BARRED
Zero entitlement lost
1
DEEMED ACCEPTANCE
CE-009 — position reserved

Disclaimer: This Notice Tracker is produced by Built AI Ltd for internal commercial management. Dates are recorded from Built AI's records and correspondence logs. Any discrepancy with the PM's records should be raised immediately with J. Navarro (Commercial Lead).

NOTICE TRACKER — PERIOD 7

Every window tracked. Zero lapsed.

14 compensation events. 56 notice windows monitored. 1 near-miss caught. 1 deemed acceptance documented. Zero entitlement lost to a missed clock.
built-ai.io · Commercial Control Kit™ · NT · Notice Tracker Pack 04 / 09 · Commercial Control Kit™ · © 2026 Built AI Ltd · CRE-NT-001 Period 7
Up next
VN · Variation Narrative
← Or back to the Commercial Control Kit page