BuiltAI
Commercial Control Kit™Pack 04 / 06 · Client deliverable
Notice tracker · Period 7
Every notice window tracked, every clock watched
Each compensation event triggers up to four contractual notice windows. This tracker monitors all four across all 14 active CEs, so no entitlement is lost to a missed clock.
- Project
- Crestfield Distribution Centre, Warrington
- Contract
- NEC4 ECC Option A · £3,814,200
- Reference
- CRE-NT-001 · Period 7
- Reporting date
- Friday 22 May 2026
- Prepared by
- BuiltAI Intelligence Ltd · J. Navarro
- Status
- Zero lapsed
Illustrative example: fictional project and parties.
56Notice windows monitored (14 CEs × 4)
1.4 daysAverage time to notify (target < 3)
1Near-miss caught (CE-007)
0Time-barred: zero entitlement lost
BuiltAI Intelligence Ltd · built-ai.ioCRE-NT-001 · Period 7
01Windows
Four deadlines per compensation event
Each compensation event triggers up to four contractual notice windows. Missing any one can weaken or destroy the entitlement, so the tracker monitors all four at once.
Clause 61.3 · CE notification8 weeks from awareness. Miss it and the event is time-barred.
Clause 61.4 · PM response1 week. The PM must respond to the notification.
Clause 62.3 · Quotation3 weeks. The Contractor submits the quotation.
Clause 62.6 · Deemed acceptance2 weeks. The PM must respond, or the quotation is treated as accepted.
02Record
The complete notice record - 14 CEs
| CE | Notified (61.3) | 61.3 expiry | PM resp (61.4) | Quote (62.3) | PM due (62.6) | Notice |
|---|---|---|---|---|---|---|
| CE-001 | 19 Nov | 14 Jan | 24 Nov ✓ | 10 Dec | 24 Dec | OK |
| CE-002 | 4 Dec | 28 Jan | 9 Dec ✓ | 23 Dec | 6 Jan | OK |
| CE-003 | 13 Dec | 6 Feb | 18 Dec ✓ | 9 Jan | 23 Jan | OK |
| CE-004 | 9 Jan | 5 Mar | 15 Jan ✓ | 3 Feb | 17 Feb | OK |
| CE-005 | 15 Jan | 11 Mar | 21 Jan ✓ | 6 Feb | 20 Feb | OK |
| CE-006 | 3 Feb | 30 Mar | 10 Feb ✓ | 27 Feb | 13 Mar | OK |
| CE-007 | 11 Apr | 15 Apr | 16 Apr ✓ | 6 May | 20 May | Near-miss |
| CE-008 | 13 Mar | 1 May | 13 Mar ✓ | 28 Mar | 11 Apr | OK |
| CE-009 | 26 Mar | 19 May | 28 Mar ✓ | 8 Apr | 22 Apr | 62.6 reserved |
| CE-010 | 9 Apr | 4 Jun | 15 Apr ✓ | 1 May | 15 May | Due |
| CE-011 | 15 Apr | 10 Jun | 22 Apr ✓ | 8 May | 22 May | Due |
| CE-012 | 23 Apr | 18 Jun | 29 Apr ✓ | 14 May | 28 May | Due |
| CE-013 | 7 May | 1 Jul | 13 May ✓ | - | - | OK |
| CE-014 | 13 May | 7 Jul | 20 May due; response status not recorded as at 22 May 2026 | - | - | OK |
03Watch
Active watch items
- CE-009 - clause 62.6 deemed acceptance potentially triggered (PM response overdue since 22 Apr). The position is reserved, and a cooperative response was provided on 14 May.
- CE-010, CE-011, CE-012 - PM responses due 15 May, 22 May and 28 May respectively.
- CE-014 - PM response to the notification due 20 May; response status not recorded as at 22 May 2026.
Notification discipline - Month 7
Average 1.4 days to notify (target under 3). Early warnings issued on 13 of 14 events; CE-007 was missed and corrected. Zero events time-barred; one deemed-acceptance position (CE-009) reserved and documented.
Reference CRE-NT-001 · Period 7Contract NEC4 ECC Option APrepared by J. Navarro, Commercial Lead