Final account position · Period 7 snapshot

Forecast final account position

The current forecast outturn for Crestfield DC: the original contract sum, agreed and submitted variations, anticipated variations and the risk provision, reconciled to the Change Event Log.

Project
Crestfield Distribution Centre, Warrington
Contract
NEC4 ECC Option A · £3,814,200
Reference
CREST-FAP-P7
Period
Period 7 · May 2026
Prepared by
BuiltAI Intelligence Ltd
Status
Forecast snapshot

Illustrative example: fictional project and parties.

£4,139,639Forecast outturn
+8.5%Against the original contract sum
£300,439Change pipeline, 14 CEs
BuiltAI Intelligence Ltd · built-ai.ioCREST-FAP-P7
01Forecast

Forecast outturn

The current forecast final account position, based on agreed variations, submitted variations, variations in valuation and a risk provision. The five variation lines below total the £300,439 Period 7 change pipeline across 14 CEs, reconciled to the Change Event Log (CRE-CEL-001). Updated monthly as part of the CCK workflow.

ComponentValueStatus
Original contract sum£3,814,200Agreed
Agreed variations (CE-001 to CE-006)+£142,000Agreed
Agreed variations (CE-007, CE-008)+£44,200Agreed
Submitted - awaiting PM assessment (CE-009)+£43,039Submitted
Submitted - PM assessing (CE-010 to CE-012)+£38,400Submitted
Anticipated - in valuation (CE-013, CE-014)+£32,800Anticipated
Risk provision+£25,000Provisional
Forecast outturn£4,139,639+8.5%
02Risk

Key risks in the forecast

CE-009 - submitted, not agreed

CE-009 (£43,039) is submitted and awaiting the PM's assessment: it is not agreed and not deemed accepted, and the assessed sum may differ from the quotation.

CE-013 and CE-014 - notified, not yet quoted

CE-013 and CE-014 (£32,800) are notified but not yet quoted. CE-013 (fire alarm panel relocation) was notified on 7 May with the clause 61.3 window running to 1 July and its quotation in preparation. CE-014 (late landlord BMS integration spec) was notified on 13 May, awaits the PM's clause 61.4 response, and its programme effect remains TBC pending the landlord's final integration specification.

Reference CREST-FAP-P7Contract NEC4 ECC Option AReconciled to CRE-CEL-001