Current forecast final account position for the Crestfield DC project. Original contract sum, agreed variations, anticipated variations, risk allowance, and forecast outturn.
Current forecast final account position based on agreed variations, submitted variations, variations in valuation, and risk provision. Reconciled to the Change Event Log (CRE-CEL-001) — the five variation lines below total the £300,439 Period 7 change pipeline across 14 CEs. Updated monthly as part of the CCK workflow.
| Component | Value | Status |
|---|---|---|
| Original contract sum | £3,814,200 | Agreed |
| Agreed variations (CE-001 to CE-006) | +£142,000 | Agreed |
| Agreed variations (CE-007, CE-008) | +£44,200 | Agreed |
| Submitted — awaiting PM assessment (CE-009) | +£43,039 | Submitted |
| Submitted — PM assessing (CE-010 to CE-012) | +£38,400 | Submitted |
| Anticipated — in valuation (CE-013, CE-014) | +£32,800 | Anticipated |
| Risk provision | +£25,000 | Provisional |
| FORECAST OUTTURN | £4,139,639 | +8.5% vs original |