Commercial Control Kit™Pack 04 / 06 · Client deliverable
Monthly commercial submission · Period 7

Application for payment and commercial status

The Period 7 submission for Crestfield DC: the application for payment, the variation status, the programme position and the amount due this period.

Project
Crestfield Distribution Centre, Warrington
Contract
NEC4 ECC Option A · £3,814,200
Reference
CREST-MCS-P7
Period
Period 7 · May 2026
Prepared by
BuiltAI Intelligence Ltd
Status
Application submitted

Illustrative example: fictional project and parties.

£475,037Amount due this period
£300kVariation pipeline, 14 CEs
+1.5 wkCE-009 completion impact
BuiltAI Intelligence Ltd · built-ai.ioCREST-MCS-P7
01Application

Application for payment

ItemDescriptionThis periodCumulative
Main worksActivity Schedule - completed activities£412,800£2,648,200
Variations agreedCE-001 to CE-006 - agreed in Periods 1–6 - £142,000
Recorded CE agreementsCE-007 and CE-008 - period allocation pending£44,200£44,200
Variations submittedCE-009 - quotation submitted 8 Apr, awaiting PM assessment (applied, not yet certified)£43,039£43,039
Subtotal£500,039£2,877,439
Retention · 5% per Contract Data−£25,002−£143,872
Previous certified · Periods 1–6−£2,258,530
Amount due this period£475,037

Period allocation pending: CE-008 is recorded as agreed on 10 April, before the 24 April review window in the Change Event Log. The application retains £44,200 as recorded; its period allocation needs reconciliation.

02CE-009

Note on CE-009

Applied, not certified

CE-009 (the HV switchgear design change, 11kV to 33kV) is applied at the Contractor's submitted quotation value of £43,039 - Defined Cost £38,600 plus the Fee at 11.5% (£4,439). It is not agreed and not deemed accepted. The PM's two-week period for reply (clause 62.6) expired on 22 April 2026 without an assessment; the Contractor's clause 62.6 position is reserved and documented but is not operative and is not relied upon. The assessment is expected in the week of 19 May 2026, and the certified sum may differ from the applied sum.

Agreed variations to date total £186,200 (CE-001 to CE-008); the full change pipeline is £300,439 across 14 CEs. See the Change Event Log (CRE-CEL-001).

Reference CREST-MCS-P7Contract NEC4 ECC Option ARetention 5% per Contract Data