The Drop™ · submission pack assembly

The pack that lands on the assessor's desk

Narrative, evidence, valuation and programme - compiled, formatted, checked and sent. Every submission follows the same structure, so every assessor gets the same quality.

Project
Crestfield Distribution Centre, Warrington
Contract
NEC4 ECC Option A · £3,814,200
Period
Month 7 of 12 · May 2026
Reference
CREST-MCS-P7
Prepared by
BuiltAI Intelligence Ltd · J. Navarro
Submitted to
R. Whitworth · Alder Cost Consultants (PM)

Illustrative example: fictional project and parties.

18Submissions tracked
14CEs managed
£300,439Pipeline across all CEs
0Time-barred; 0 incomplete
BuiltAI Intelligence Ltd · built-ai.ioThe Drop™ · Stage 06
01Purpose

Compile, format, check, send

The Drop takes everything the previous five stages produced - the classification from The Radar, the notice trail from The Clock, the narrative from The Case, the evidence from The File and the valuation from The Count - and compiles it into a single submission pack formatted to the PM's template. A pre-submission check confirms every element is present, consistent and reconciled before it goes out. The Drop also runs the monthly commercial submission cycle: not just individual quotations, but the compiled monthly pack Alder expects on the last Friday of each month.

02The pack

CE-009 - what the PM received

The complete submission for CE-009, sent to R. Whitworth (Alder) on 8 April 2026 - seven documents in one structured pack, each produced by an upstream stage.

#DocumentFrom
1Cover letter and summary - formal quotation per clause 62.3: reference, value summary (£43,039), programme impact (1.5 weeks), response deadline, signed by J. NavarroThe Drop
2Entitlement narrative - cause (PMI-047), effect, entitlement (clause 60.1(1)), programme impactThe Case
3Defined Cost build-up - five categories per the Schedule of Cost Components, plus the Fee at 11.5%, total £43,039The Count
4Assessed programme - Rev 7 extract, 1.5-week delay, critical-path analysis, no float consumedThe Count
5Evidence bundle index - 10 items (EV-009-01 to -10), cross-referenced, completeness 10/10The File
6Supporting evidence (attached) - PMI-047, DNO agreement, Schneider quotation, civil estimate, programme extracts, photographs, noticesThe File
7Notice audit trail - awareness → early warning → notification → PM response → quotation request → submissionThe Clock
Submitted
8 April 2026, 14:18 BST, to R. Whitworth (Alder Cost Consultants) by email and hard copy to the site office.
PM response due
22 April 2026 (clause 62.6). Further information requested 12 May (DNO witness-testing lead), responded 14 May.
Current status
PM assessment expected the week of 19 May. The clause 62.6 deemed-acceptance position is reserved.
03Rhythm

The monthly commercial submission cycle

Beyond individual quotations, The Drop compiles the monthly pack that goes to Alder on the last Friday of each month - all CEs, the variation pipeline, the programme position and the commercial summary.

  1. Week 1 - data ingestion.

    Pull updated CE data from The Radar, Clock, Case, File and Count. Reconcile against the prior month; identify new CEs and status changes.

  2. Week 2 - narrative and valuation.

    Complete outstanding narratives and valuations for CEs that have progressed; update pipeline values where assessments have been received.

  3. Week 3 - compile and review.

    Assemble the monthly pack. J. Navarro reviews for consistency, reconciliation and completeness against the pre-submission checklist.

  4. Week 4, Friday - submit.

    The monthly submission to Alder: variation pipeline, programme update, CE status tracker and commercial summary. The audit log is updated.

04Audit log

Every submission tracked

A complete audit trail of every submission - individual CE quotations and monthly packs. Each has a date, a recipient, a response deadline and a status, so nothing is lost between send and response.

RefTypeSubmittedResponse dueStatus
SUB-001CE-001 quotation10 Dec 2524 Dec 25Agreed 18 Dec
SUB-002Monthly - Nov 2528 Nov 25 - Received
SUB-003CE-002 quotation23 Dec 256 Jan 26Agreed 8 Jan
SUB-004CE-003 quotation9 Jan 2623 Jan 26Agreed 22 Jan
SUB-005Monthly - Dec 2527 Dec 25 - Received
… SUB-006 to SUB-016 - the remaining CE quotations and monthly packs …
SUB-017CE-012 quotation14 May 2628 May 26Awaiting
SUB-018Monthly - Apr 2624 Apr 26 - Received
18 submissions total - 12 CE quotations (CE-001 to CE-012) and 6 monthly packs (Nov 2025 to Apr 2026)
05Final check

Stage 06 gate - the pre-submission checklist

Every submission - a CE quotation or a monthly pack - passes this checklist before it leaves. The Drop sends nothing that fails a check.

  • The entitlement narrative references the correct NEC4 clauses.
  • The Defined Cost build-up reconciles to the quotation total.
  • The evidence index cross-references every narrative claim, and every item is attached.
  • The programme extract shows the critical path and float position.
  • The Fee percentage is correct (11.5% per Contract Data).
  • The notice trail is complete - no time-bar exposure - and the cover letter is signed, with the response deadline stated.
Commercial Control Kit - complete

Six stages, one CE tracked from detection to submission. 14 compensation events managed across 7 months: £300,439 in the pipeline, £186,200 agreed, zero time-barred, zero incomplete submissions. Every pound sourced, every claim evidenced, every deadline tracked.

Reference CREST-MCS-P7Contract NEC4 ECC Option ALast stage of the Commercial Control Kit