NEC4 ECC is a notice-heavy contract. Missing a notice window doesn't just weaken the position — it kills the entitlement entirely. The Clock tracks four critical windows simultaneously for every compensation event:
The full notice status for all 14 compensation events. Every date, every response, every acknowledgement. One near-miss (CE-007, highlighted in red) — caught with 3 days to spare.
| CE | Aware | EW Issued | CE Notified | PM Response | Quote Req'd | Quote Sub'd | PM Decision | Status |
|---|---|---|---|---|---|---|---|---|
| CE-001 | 18 Nov | 18 Nov | 19 Nov | 24 Nov ✓ | 24 Nov | 10 Dec | 18 Dec ✓ | Agreed |
| CE-002 | 3 Dec | 3 Dec | 4 Dec | 9 Dec ✓ | 9 Dec | 23 Dec | 8 Jan ✓ | Agreed |
| CE-003 | 12 Dec | 12 Dec | 13 Dec | 18 Dec ✓ | 18 Dec | 9 Jan | 22 Jan ✓ | Agreed |
| CE-004 | 8 Jan | 8 Jan | 9 Jan | 15 Jan ✓ | 15 Jan | 3 Feb | 14 Feb ✓ | Agreed |
| CE-005 | 14 Jan | 14 Jan | 15 Jan | 21 Jan ✓ | 21 Jan | 6 Feb | 19 Feb ✓ | Agreed |
| CE-006 | 2 Feb | 2 Feb | 3 Feb | 10 Feb ✓ | 10 Feb | 27 Feb | 12 Mar ✓ | Agreed |
| CE-007 | 18 Feb | — | 11 Apr | 16 Apr ✓ | 16 Apr | 6 May | 19 May ✓ | Agreed |
| CE-008 | 6 Mar | 6 Mar | 7 Mar | 13 Mar ✓ | 13 Mar | 28 Mar | 10 Apr ✓ | Agreed |
| CE-009 | 24 Mar | 25 Mar | 26 Mar | 28 Mar ✓ | 28 Mar | 8 Apr | pending | Submitted |
| CE-010 | 8 Apr | 8 Apr | 9 Apr | 15 Apr ✓ | 15 Apr | 1 May | pending | Submitted |
| CE-011 | 14 Apr | 14 Apr | 15 Apr | 22 Apr ✓ | 22 Apr | 8 May | pending | Submitted |
| CE-012 | 22 Apr | 22 Apr | 23 Apr | 29 Apr ✓ | 29 Apr | 14 May | pending | Submitted |
| CE-013 | 6 May | 6 May | 7 May | 13 May ✓ | 13 May | — | — | Quoting |
| CE-014 | 12 May | 12 May | 13 May | pending | — | — | — | Notified |
Continuing the CE-009 deep dive from The Radar. Here's every notice milestone, every response, every clock window — all tracked and documented.
Not every CE moves smoothly. CE-007 — late issue of revised ventilation design — was detected on 18 February but the formal CE notification wasn't issued until 11 April. Here's what happened and why The Clock exists.
The ventilation design revision was received 18 February. The site team recognised the delay but initially treated it as a programme issue, not a compensation event. The commercial team was not notified until a routine weekly review on 8 April — 7 weeks and 1 day after awareness.
The 8-week time-bar (clause 61.3) would have expired on 15 April 2026. The CE notification was issued on 11 April — with 3 working days to spare. If the weekly review had been one week later, £18,400 of entitlement would have been permanently lost.
Before a CE moves to The Case (Stage 03), The Clock confirms: every required notice has been issued, every response window is tracked, and every deemed-acceptance trigger is documented. No entitlement is lost to a missed deadline.
Handover note to Stage 03 — The Case™: CE-009 quotation submitted, PM additional info provided, assessment expected week of 19 May. Deemed-acceptance position reserved. Build the entitlement narrative on the assumption the PM may assess at a lower value — the cause → effect → entitlement chain needs to withstand scrutiny.