The Clock™ · notice and acknowledgement tracking

Every window tracked, every clock watched

Every notice has a deadline, and missing it ends the entitlement regardless of the merits. The Clock tracks every window, every response and every deemed-acceptance trigger across the contract.

Project
Crestfield Distribution Centre, Warrington
Contract
NEC4 ECC Option A · £3,814,200
Period
Month 7 of 12 · May 2026
Reference
CRE-NT-001 · Period 7
Prepared by
BuiltAI Intelligence Ltd · J. Navarro
Status
Zero lapsed

Illustrative example: fictional project and parties.

14Notices issued
0Time-barred
1Near-miss caught (CE-007)
1Deemed-acceptance position (CE-009)
BuiltAI Intelligence Ltd · built-ai.ioThe Clock™ · Stage 02
01Windows

The windows that matter

NEC4 ECC is a notice-heavy contract: missing a window does not just weaken the position, it ends the entitlement. The Clock tracks four windows at once for every compensation event.

Clause 61.3 · CE notification8 weeks from awareness

Miss it and the event is time-barred - the most dangerous deadline in NEC4.

Clause 61.4 · PM response1 week

The PM must respond to the notification; if not, the Contractor can escalate.

Clause 62.3 · Quotation3 weeks

The Contractor's clock: the quotation must be submitted on time.

Clause 62.6 · Deemed acceptance2 weeks

The PM must respond to the quotation, or it is treated as accepted - a powerful lever.

02Tracker

The notice tracker - all 14 CEs

The full notice status for every event: notification, PM response, quotation and decision. One near-miss (CE-007) was caught with 3 days to spare.

CENotifiedPM respQuote subPM decisionStatus
CE-00119 Nov24 Nov ✓10 Dec18 Dec ✓Agreed
CE-0024 Dec9 Dec ✓23 Dec8 Jan ✓Agreed
CE-00313 Dec18 Dec ✓9 Jan22 Jan ✓Agreed
CE-0049 Jan15 Jan ✓3 Feb14 Feb ✓Agreed
CE-00515 Jan21 Jan ✓6 Feb19 Feb ✓Agreed
CE-0063 Feb10 Feb ✓27 Feb12 Mar ✓Agreed
CE-00711 Apr16 Apr ✓6 May19 May ✓Agreed (near-miss)
CE-0087 Mar13 Mar ✓28 Mar10 Apr ✓Agreed
CE-00926 Mar28 Mar ✓8 AprpendingSubmitted
CE-0109 Apr15 Apr ✓1 MaypendingSubmitted
CE-01115 Apr22 Apr ✓8 MaypendingSubmitted
CE-01223 Apr29 Apr ✓14 MaypendingSubmitted
CE-0137 May13 May ✓ - - Quoting
CE-01413 Maypending - - Notified
03Timeline

CE-009 - every date tracked

  1. 24 Mar 2026, 14:22 - change detected.

    PMI-047 changes the HV switchgear from 11kV to 33kV. Logged in The Radar within 2 hours; the 8-week clock (clause 61.3) starts, expiring 19 May 2026.

  2. 25 Mar 2026 - early warning issued.

    Early warning to the PM under clause 15.1 - risk to Defined Cost and planned Completion. Acknowledged the same day.

  3. 26 Mar 2026 - CE notification.

    Formal notification to the PM, 2 days from awareness, well within the 8-week window. The PM has 1 week to respond (clause 61.4).

  4. 28 Mar 2026 - PM responds, not disputed.

    The PM accepts CE-009 as a compensation event and requests a quotation. The 3-week window starts (clause 62.3, due 18 Apr).

  5. 8 Apr 2026 - quotation submitted.

    Defined Cost £38,600 plus the Fee at 11.5% (£4,439) = £43,039, programme impact 1.5 weeks. Submitted 10 days early. The PM has 2 weeks to respond (clause 62.6, due 22 Apr).

  6. 12 May 2026 - PM requests information.

    The PM queries the DNO witness-testing lead. The two-week reply window (clause 62.6) has already lapsed, so deemed acceptance may apply; the position is reserved, and BuiltAI responds cooperatively with the data on 14 May to keep the relationship.

  7. 19 May 2026 (expected) - PM assessment.

    Alder Cost Consultants confirmed the assessment for the week of 19 May. If it differs materially from the quotation, the dispute resolution procedure (clause W1 or W2) is next.

04Near-miss

CE-007 - three days from a time-bar

Why The Clock exists

The ventilation design revision arrived on 18 February. The site team recognised the delay but treated it as a programme issue, not a compensation event, and the commercial team was not told until a routine weekly review on 8 April - 7 weeks and 1 day after awareness. The 8-week time-bar (clause 61.3) would have expired on 15 April. The CE was notified on 11 April, with 3 working days to spare. One week later, £18,400 of entitlement would have been lost.

Outcome: CE-007 was notified in time, the PM did not dispute it, and it was agreed on 19 May at £18,400. The process was tightened: the site team now flags any employer-caused delay to the commercial team within 48 hours, not at the next weekly review.

05Stage gate

Stage 02 gate - every window tracked, zero lapsed

  • Early warning issued where applicable (clause 15.1).
  • CE notification issued within the 8-week window (clause 61.3).
  • PM response received, or non-response documented (clause 61.4).
  • Quotation submitted within the agreed period (clause 62.3).
  • PM assessment received, or the deemed-acceptance position documented (clause 62.6).
  • All dates, communications and acknowledgements logged with an audit trail.

Hand-off to The Case™: CE-009's quotation is submitted and the assessment is expected the week of 19 May, with the deemed-acceptance position reserved. Build the entitlement narrative on the assumption the PM may assess lower - the cause → effect → entitlement chain must withstand scrutiny.

Reference CRE-NT-001 · Period 7Contract NEC4 ECC Option ANext Stage 03 · The Case