Commercial Control · The Clock™ - Stage 02 (notice tracking) · Worked example Crestfield Distribution Centre - Phase 2 M&E · NEC4 ECC Option A · CE-009 threaded · Period 7 · £3.81m
← CCK Pack
COMMERCIAL CONTROL KIT™STAGE 02 · THE CLOCK

The Clock

Notice & Acknowledgement Tracking
Every notice has a deadline. Miss it and the entitlement is gone — regardless of the merits. The Clock tracks every window, every response, every deemed-acceptance trigger across the contract.
Project
Crestfield Distribution Centre — Phase 2 M&E
Contract
NEC4 ECC Option A · £3,814,200
Period
Month 7 of 12 · May 2026
built-ai.io · hello@built-ai.io Pack 04 / 09 · Commercial Control Kit™ · © 2026 Built AI Ltd BUILT AI
CCK WORKFLOW 1The Radar
2The Clock
3The Case 4The File 5The Count 6The Drop
NEC4 NOTICE MECHANICS

The Windows That Matter

NEC4 ECC is a notice-heavy contract. Missing a notice window doesn't just weaken the position — it kills the entitlement entirely. The Clock tracks four critical windows simultaneously for every compensation event:

CLAUSE 61.3
CE Notification Window
8 weeks from Contractor becoming aware. Miss it → time-barred. The most dangerous deadline in NEC4.
CLAUSE 61.4
PM Response Window
1 week for PM to respond to CE notification. If PM doesn't respond → Contractor can escalate.
CLAUSE 62.3
Quotation Submission Window
3 weeks from PM instruction to quote (or as agreed). The Contractor's clock — quotation must be submitted on time.
CLAUSE 62.6
Deemed Acceptance Trigger
2 weeks for PM to respond to quotation. If PM doesn't respond → quotation is deemed accepted. Powerful lever.
NOTICE TRACKER

14 CEs — Every Notice Tracked

The full notice status for all 14 compensation events. Every date, every response, every acknowledgement. One near-miss (CE-007, highlighted in red) — caught with 3 days to spare.

CEAwareEW IssuedCE NotifiedPM ResponseQuote Req'dQuote Sub'dPM DecisionStatus
CE-00118 Nov18 Nov19 Nov24 Nov ✓24 Nov10 Dec18 Dec ✓Agreed
CE-0023 Dec3 Dec4 Dec9 Dec ✓9 Dec23 Dec8 Jan ✓Agreed
CE-00312 Dec12 Dec13 Dec18 Dec ✓18 Dec9 Jan22 Jan ✓Agreed
CE-0048 Jan8 Jan9 Jan15 Jan ✓15 Jan3 Feb14 Feb ✓Agreed
CE-00514 Jan14 Jan15 Jan21 Jan ✓21 Jan6 Feb19 Feb ✓Agreed
CE-0062 Feb2 Feb3 Feb10 Feb ✓10 Feb27 Feb12 Mar ✓Agreed
CE-00718 Feb11 Apr16 Apr ✓16 Apr6 May19 May ✓Agreed
CE-0086 Mar6 Mar7 Mar13 Mar ✓13 Mar28 Mar10 Apr ✓Agreed
CE-00924 Mar25 Mar26 Mar28 Mar ✓28 Mar8 AprpendingSubmitted
CE-0108 Apr8 Apr9 Apr15 Apr ✓15 Apr1 MaypendingSubmitted
CE-01114 Apr14 Apr15 Apr22 Apr ✓22 Apr8 MaypendingSubmitted
CE-01222 Apr22 Apr23 Apr29 Apr ✓29 Apr14 MaypendingSubmitted
CE-0136 May6 May7 May13 May ✓13 MayQuoting
CE-01412 May12 May13 MaypendingNotified
CE-009 — NOTICE TIMELINE

HV Switchgear — Every Date Tracked

Continuing the CE-009 deep dive from The Radar. Here's every notice milestone, every response, every clock window — all tracked and documented.

24 Mar 2026 · 14:22
Change detected — PMI-047 received
PM instruction changes HV switchgear from 11kV to 33kV. Logged in The Radar within 2 hours. 8-week notice clock starts.
→ 61.3 window opens · Expires 19 May 2026
25 Mar 2026
Early warning issued
Early warning notification issued to PM — risk to cost and programme from switchgear change. Acknowledged by PM same day.
→ Clause 15.1 · Risk to Defined Cost + planned Completion
26 Mar 2026
CE notification issued
Formal compensation event notification to PM. 2 days from awareness — well within the 8-week window. PM has 1 week to respond.
→ Clause 61.3 · PM response due 2 Apr
28 Mar 2026
PM responds — not disputed
PM accepts CE-009 as a compensation event. Quotation requested. 3-week quotation window starts.
→ Clause 62.3 · Quotation due 18 Apr
8 Apr 2026
Quotation submitted
Full quotation submitted: Defined Cost £38,600 plus Fee at 11.5% (£4,439) = £43,039, programme impact 1.5 weeks. 10 days early — submitted within 11 days, not 21. PM has 2 weeks to respond.
→ Clause 62.6 · PM response due 22 Apr · Deemed acceptance if silent
12 May 2026
PM requests additional information
PM queries DNO witness testing lead time. Strictly, the 2-week response window (clause 62.6) has already lapsed — deemed acceptance may apply. J. Navarro (Built AI) notes this position but responds cooperatively with the requested data (14 May) to maintain the commercial relationship. The deemed-acceptance fallback is documented.
→ Clause 62.6 potentially triggered · Position reserved
19 May 2026 (expected)
PM assessment expected
Alder Cost Consultants confirmed assessment will be issued week of 19 May. If the assessment differs materially from Built AI's quotation, the dispute resolution procedure (clause W1/W2) is the next step.
→ Assessment expected · If not → deemed acceptance confirmed
NEAR-MISS — CE-007

3 Days From Time-Bar

Not every CE moves smoothly. CE-007 — late issue of revised ventilation design — was detected on 18 February but the formal CE notification wasn't issued until 11 April. Here's what happened and why The Clock exists.

CE-007 — Near-Miss Analysis

The ventilation design revision was received 18 February. The site team recognised the delay but initially treated it as a programme issue, not a compensation event. The commercial team was not notified until a routine weekly review on 8 April — 7 weeks and 1 day after awareness.

The 8-week time-bar (clause 61.3) would have expired on 15 April 2026. The CE notification was issued on 11 April — with 3 working days to spare. If the weekly review had been one week later, £18,400 of entitlement would have been permanently lost.

Outcome: CE-007 was notified in time. The PM did not dispute the notification. Quotation submitted 6 May, agreed 19 May at £18,400. But the process was tightened — site team now briefed to flag any employer-caused delay to the commercial team within 48 hours, not at the next weekly review.
STAGE 02 GATE — THE CLOCK

Every Window Tracked. Zero Lapsed.

Before a CE moves to The Case (Stage 03), The Clock confirms: every required notice has been issued, every response window is tracked, and every deemed-acceptance trigger is documented. No entitlement is lost to a missed deadline.

Early warning issued where applicable (clause 15.1)
CE notification issued within 8-week window (clause 61.3)
PM response received or non-response documented (clause 61.4)
Quotation submitted within agreed period (clause 62.3)
PM assessment received or deemed-acceptance position documented (clause 62.6)
All dates, communications and acknowledgements logged with audit trail

Handover note to Stage 03 — The Case™: CE-009 quotation submitted, PM additional info provided, assessment expected week of 19 May. Deemed-acceptance position reserved. Build the entitlement narrative on the assumption the PM may assess at a lower value — the cause → effect → entitlement chain needs to withstand scrutiny.

THE CLOCK — SNAPSHOT

14 notices issued. Zero time-barred.

Every compensation event on this project has been notified within the contractual window. One near-miss (CE-007) was caught with 3 days to spare — and the process was tightened as a result. The deemed-acceptance lever (clause 62.6) has been documented on CE-009 as a fallback position. No entitlement has been lost to a missed clock.
NOTICES ISSUED
14
TIME-BARRED
0
NEAR-MISSES
1
DEEMED ACCEPTANCE
1
built-ai.io · Commercial Control Kit™ · The Clock™ · Stage 02 Pack 04 / 09 · Commercial Control Kit™ · © 2026 Built AI Ltd