BuiltAI
Commercial Control Kit™Pack 04 / 06 · Client deliverable
Valuation build-up · CE-009

Defined Cost build-up: the HV switchgear change

The Defined Cost assessment: plant and materials, subcontracted civils, people, equipment, charges and the Fee, each line traced to a source quotation, subcontract price, timesheet or Contract Data rate.

Project
Crestfield Distribution Centre, Warrington
Contract
NEC4 ECC Option A · £3,814,200
Reference
CREST-VBU-CE009 · Rev 1
Period
Period 7 · May 2026
Prepared by
BuiltAI Intelligence Ltd
Basis
Schedule of Cost Components

Illustrative example: fictional project and parties.

£38,600Defined Cost (Schedule of Cost Components)
£4,439Fee at 11.5% (Contract Data Part 2)
£43,039Total change to the Prices
BuiltAI Intelligence Ltd · built-ai.ioCREST-VBU-CE009 · Rev 1
01Basis

How the change is assessed

Assessed as the change in Defined Cost using the Schedule of Cost Components per NEC4 ECC Option A, with the Fee applied at 11.5% (Contract Data Part 2). Each line is traced to a supplier quotation, subcontract price, timesheet or Contract Data rate. Deductions are taken for the 11kV work already priced in the Activity Schedule: this is the net additional cost caused by the compensation event, not the gross cost.

02Build-up

Component breakdown

Cost componentDescriptionSourceAmount
1 · Plant and materials33kV MCSET switchgear panel, supply only, delivered (£48,200), less the 11kV RM6 ring-main unit already priced in the Activity Schedule (−£29,800)EV-009-04£18,400
2 · Subcontracted civilsExtended reinforced base 2.4m × 1.8m × 300mm (£5,400) and cable-trench diversion around the larger base - 3.6m of trench, duct, backfill and reinstatement (£2,800)EV-009-05£8,200
3 · PeopleHV jointer for 33kV dry-type stress-cone terminations (3 days), electrician attendance (2 days) and site engineer supervision (3 days), less the 11kV termination labour that would have been incurred anyway (−£1,640)Timesheets + SCC rates£2,800
4 · Equipment33kV primary injection test set hire, 2 days including calibration (£1,800), and the DNO witness-test fee differential - £3,200 at 33kV against £600 at 11kV (£2,600)Hire quote + DNO schedule£4,400
5 · ChargesSite preliminaries extension of 1.5 weeks at £3,200/wk, driven by the 33kV DNO witness-testing lead time (4 weeks against 2)EV-009-07£4,800
Subtotal - Defined Cost£38,600
Fee at 11.5% (Contract Data Part 2)£4,439
Total change to the Prices£43,039
03Assurance

Sourcing and audit

Audit note

The quotation was submitted at £43,039 - Defined Cost £38,600 plus the Fee at 11.5% (£4,439) - and the build-up above supports the submitted figure. The indexed Schneider quotation SC-2026-1147 evidences the £18,400 plant differential.

Reference CREST-VBU-CE009 · Rev 1Contract NEC4 ECC Option AFee 11.5% per Contract Data Part 2