Commercial Control Kit™Pack 04 / 06 · Client deliverable
Evidence bundle index · CE-009
The evidence chain behind CE-009
Every document supporting the CE-009 entitlement, variation narrative and valuation: indexed by type, dated, and cross-referenced to the clause it supports.
- Project
- Crestfield Distribution Centre, Warrington
- Contract
- NEC4 ECC Option A · £3,814,200
- Reference
- CREST-EBI-CE009 · Rev 1
- Period
- Period 7 · May 2026
- Prepared by
- BuiltAI Intelligence Ltd
- Completeness
- Verified 10 / 10
Illustrative example: fictional project and parties.
10Evidence items, EV-009-01 to EV-009-10
4Third-party sourced, hash-verified
0Gaps: every claim has a document
BuiltAI Intelligence Ltd · built-ai.ioCREST-EBI-CE009 · Rev 1
01Index
Ten documents, complete evidence chain
| # | Document | Date | Source | Clause |
|---|---|---|---|---|
| EV-009-01 | PMI-047 - PM instruction changing the HV specification from 11kV to 33kV, signed to BuiltAI | 24 Mar 26 | R. Whitworth · Alder Cost Consultants (PM) | 60.1(1) |
| EV-009-02 | DNO connection agreement DNO-CRE-2026-044 - revised agreement specifying 33kV incoming supply (was 11kV) | 18 Mar 26 | DNO (third party) | 60.1(1) |
| EV-009-03 | Works Information Part 2, Section 4.3.1 (extract) - original Scope specifying the 11kV ring-main unit (Schneider RM6) | Oct 25 | Contract documents | 60.1(1) |
| EV-009-04 | Schneider quotation SC-2026-1147 - 33kV MCSET panel against the 11kV RM6 baseline; evidences the £18,400 plant differential | 28 Mar 26 | Schneider Electric | SCC |
| EV-009-05 | Civil works estimate CE009-CIV-01 - additional base 2.4m × 1.8m × 300mm and trench diversion; labour, materials and plant, £8,200 | 2 Apr 26 | BuiltAI | SCC |
| EV-009-06 | Programme Rev 6 - accepted programme (extract): HV commissioning at Week 38, 2-week DNO lead for 11kV | 14 Mar 26 | BuiltAI | 63.5 |
| EV-009-07 | Programme Rev 7 - revised programme (extract): HV commissioning at Week 39.5, 4-week DNO lead for 33kV; 1.5-week delay | 8 Apr 26 | BuiltAI | 63.5 |
| EV-009-08 | Early warning notification - issued to the PM and acknowledged the same day | 25 Mar 26 | BuiltAI | 15.1 |
| EV-009-09 | CE notification and PM response - notified 26 Mar; PM responded 28 Mar, not disputed, quotation requested | 26–28 Mar 26 | BuiltAI / PM | 61.3 |
| EV-009-10 | Site photographs - the existing 11kV installation (4 photos: RM6 unit, cable entries, civil base); establishes the as-built baseline | 26 Mar 26 | BuiltAI | 60.1(1) |
02Integrity
Evidence integrity
All documents are stored in the CCK evidence vault with SHA-256 hash verification. EV-009-01 to EV-009-04 are issued by the Project Manager, the DNO, the contract documents and the supplier respectively, and are hash-verified against the originals. EV-009-05 to EV-009-10 are contractor-produced, timestamped and version-controlled.
Completeness verified at Stage 04 (The File™)
10 of 10, no gaps: every claim in the entitlement narrative has a supporting document. The complete bundle is exportable as a single PDF for PM submission or dispute proceedings.
Reference CREST-EBI-CE009 · Rev 1Contract NEC4 ECC Option AVerification SHA-256, CCK evidence vault