Commercial Control Kit™Stage 01 of 6 · Internal workflow
The Radar™ · change capture and classification

Catch the change before the clock starts

Detecting change as it happens, and classifying it against the contract before the notice clock starts ticking - so every compensation event is logged, classified and handed on with its notice window intact.

Project
Crestfield Distribution Centre, Warrington
Contract
NEC4 ECC Option A · £3,814,200
Period
Month 7 of 12 · May 2026
Employer
Crestfield Logistics Ltd
Contractor
Kelbrook Construction Ltd
M&E sub
BuiltAI (NEC4 ECS)

Illustrative example: fictional project and parties.

14Compensation events detected
£300,439Pipeline across all CEs
£186,200Agreed to date
0Missed: every change caught in 24h
BuiltAI Intelligence Ltd · built-ai.ioThe Radar™ · Stage 01
01Purpose

Catch the change before the clock starts

Under NEC4 ECC, a compensation event must be notified within 8 weeks of the Contractor becoming aware of it (clause 61.3). Miss the window and the entitlement is lost - time-barred, regardless of the merits. The Radar detects change events in real time, classifies each against the correct NEC4 clause, and hands it to The Clock (Stage 02) before the notice window closes.

This project - Crestfield Distribution Centre Phase 2 - is 7 months into a 12-month NEC4 ECC Option A contract. BuiltAI is the M&E subcontractor running power distribution, BMS, fire detection, lighting, ventilation and EV charging across a 180,000 sq ft logistics facility. 14 compensation events have been logged to date.

02Classify

Classifying against the contract

Every change is classified against the NEC4 ECC compensation-event clauses (60.1). The classification sets the notice route, the time-bar risk and the entitlement basis. Three categories are most active on this project.

60.1(1) · PM changes Scope7 CEs on this project

The most common trigger: an instruction that changes the Works Information - additional scope, design change, revised specification.

60.1(5) · Late employer provision4 CEs on this project

Late information, access or decisions. HV substation access was 3 weeks late.

60.1(12) · Physical conditions2 CEs on this project

Conditions an experienced contractor would not have foreseen - an unmapped gas main found during trench excavation.

60.1(3) · Stop instruction1 CE on this project

CE-005: work in Zone C stopped for six working days pending archaeological assessment.

03Log

The live change event log - Month 7

Every event detected by The Radar, classified and time-stamped. The log feeds The Clock (notices), The Case (narrative) and The Count (valuation). Status: 8 agreed, 4 submitted, 2 in preparation.

CEDescriptionClauseDetectedEst. valueStatus
CE-001Additional fire-rated cable penetration seals60.1(1)18 Nov 25£8,200Agreed
CE-002Revised BMS point schedule - 34 additional points60.1(1)3 Dec 25£14,600Agreed
CE-003Late access to HV substation - 3-week delay60.1(5)12 Dec 25£41,800Agreed
CE-004Unmapped gas main in cable-trench zone60.1(12)8 Jan 26£22,400Agreed
CE-005PM stop instruction - archaeological find60.1(3)14 Jan 26£16,800Agreed
CE-006EV charging upgrade - 22kW to 50kW DC60.1(1)2 Feb 26£38,200Agreed
CE-007Late issue of revised ventilation design - 2-week delay60.1(5)18 Feb 26£18,400Agreed
CE-008Additional external lighting columns - car park extension60.1(1)6 Mar 26£25,800Agreed
CE-009HV switchgear design change - civil works and programme impact60.1(1)24 Mar 26£43,039Submitted
CE-010Concealed asbestos in riser duct - diversion required60.1(12)8 Apr 26£12,400Submitted
CE-011Late power-on date from DNO - 4-week delay60.1(5)14 Apr 26£18,200Submitted
CE-012Additional emergency lighting to mezzanine60.1(1)22 Apr 26£7,800Submitted
CE-013Fire alarm panel relocation - structural clash60.1(1)6 May 26£12,200In prep
CE-014Late landlord BMS integration spec - commissioning60.1(5)12 May 26£20,600In prep
Total pipeline - 14 CEs£300,439Agreed: £186,200
04Deep dive

CE-009 - the event moving through the kit

CE-009 is the compensation event currently moving through the Commercial Control Kit workflow, from detection here to submission at The Drop. Each subsequent stage picks it up and shows how it progresses.

What changed
PM instruction PMI-047 (24 March 2026) changed the HV switchgear from an 11kV ring-main unit (Schneider RM6) to a 33kV panel (Schneider MCSET), following a revised DNO connection agreement. Not a like-for-like substitution: it needs a larger enclosure (an additional 2.4m × 1.8m civil base), dry-type terminations, and a re-sequenced commissioning programme.
When detected
24 March 2026, logged at 14:22, within 2 hours of receiving PMI-047.
Classification
Clause 60.1(1) - a PM instruction changing the Scope. Clear-cut, no mixed classification.
Cost impact
Estimated Defined Cost £38,600 (switchgear differential £18,400, civil base £8,200, terminations £2,800, commissioning re-sequence £4,400, prelims £4,800); with the Fee at 11.5% (£4,439) the submitted quotation is £43,039.
Programme
1.5 weeks added to planned Completion - the 33kV DNO witness test needs a 4-week booking against 2 for 11kV, net of re-sequencing.
Notice status
Early warning 25 March (clause 15.1); CE notified 26 March (clause 61.3); PM responded 28 March, not disputed; quotation submitted 8 April (clause 62.3).
05Stage gate

Stage 01 gate - change detected, clock set

Confirmed before hand-off to The Clock

A misclassified CE costs time downstream; a missed CE costs money forever. The gate confirms each of these before the event moves on.

  • Change event detected and logged within 24 hours.
  • NEC4 clause classification confirmed (the 60.1 sub-clause identified).
  • Source instruction or event documented (PMI, RFI, site record, photo).
  • Initial cost and programme impact estimated (order of magnitude).
  • Early-warning assessment made (clause 15.1).
  • CE handed to The Clock for notice tracking and deadline management.

Hand-off to The Clock™: CE-009 is the priority item - quotation submitted 8 Apr, PM response due 22 Apr, further information requested 12 May. Track the deemed-acceptance trigger (clause 62.6). CE-013 and CE-014 need notification within the 8-week window - by 1 Jul and 7 Jul respectively.

Reference CRE-CEL-001 · Period 7Contract NEC4 ECC Option ANext Stage 02 · The Clock