Commercial Control · The Count™ - Stage 05 (period reconciliation) · Worked example Crestfield Distribution Centre - Phase 2 M&E · NEC4 ECC Option A · CE-009 threaded · Period 7 · £3.81m
← CCK Pack
COMMERCIAL CONTROL KIT™STAGE 05 · THE COUNT

The Count

Valuation Build-Up
Every pound counted. Every rate sourced. Defined Cost built from evidence, not from estimates. The valuation that stands up because every number traces to a document in The File.
Project
Crestfield Distribution Centre — Phase 2 M&E
Contract
NEC4 ECC Option A · £3,814,200
Period
Month 7 of 12 · May 2026
built-ai.io · hello@built-ai.io Pack 04 / 09 · Commercial Control Kit™ · © 2026 Built AI Ltd BUILT AI
CCK WORKFLOW 1The Radar 2The Clock 3The Case 4The File
5The Count
6The Drop
NEC4 VALUATION MECHANISM

Defined Cost + Fee — Not Daywork, Not Guesswork

Under NEC4 ECC Option A, compensation events are assessed as the change in Defined Cost plus the resulting Fee (clause 63.1). Defined Cost is not a lump sum or a daywork rate — it's the actual cost of doing the changed work, broken down into the Schedule of Cost Components: people, equipment, plant and materials, subcontractors, and charges. The Fee percentage (agreed in the Contract Data) is then applied to the Defined Cost to arrive at the total assessed value.

On this contract, the Fee percentage is 11.5% (Contract Data Part 2). Every valuation built by The Count follows the same structure: Defined Cost broken into components, each component sourced from evidence in The File, Fee applied at the end.

CE-009 — DEFINED COST BUILD-UP

HV Switchgear — £43,039 in Detail

The full Defined Cost build-up for CE-009, structured per the Schedule of Cost Components. Every line traces to an evidence item in The File. The Fee (11.5%) is applied to the total Defined Cost.

CatDescriptionEvidenceDefined Cost
1 · PLANT & MATERIALS — Equipment differential
1.133kV switchgear panel (Schneider MCSET)Supply only. Delivered to site. Replaces 11kV RM6.EV-009-04£48,200
1.2Less: 11kV ring-main unit (Schneider RM6) — original priceDeducted — this was included in the original activity schedule.Act. Sched.−£29,800
Plant & Materials sub-total£18,400
2 · SUBCONTRACTOR — Civil works
2.1Extended civil base — 2.4m × 1.8m × 300mm reinforced concreteExcavation, formwork, rebar, concrete, backfill. Labour + materials.EV-009-05£5,400
2.2Cable trench modification — route diversion around larger baseAdditional 3.6m trench, duct, backfill, reinstatement.EV-009-05£2,800
Subcontractor sub-total£8,200
3 · PEOPLE — Skilled labour for cable terminations
3.1HV jointer — 33kV dry-type stress-cone terminationsSpecialist termination. 3 days × £680/day (HV jointer rate per SCC).Timesheet£2,040
3.2Electrician attendance — cable preparation and support2 days × £420/day.Timesheet£840
3.3Supervision — site engineer attendance during termination3 days × £520/day (pro-rata).Timesheet£1,560
3.4Less: 11kV termination labour — deducted (would have been incurred)Act. Sched.−£1,640
People sub-total (net additional)£2,800
4 · EQUIPMENT — Testing & commissioning
4.133kV primary injection test set — hire2 days hire inc. calibration certificates. Not required for 11kV.Hire quote£1,800
4.2DNO witness test fee — 33kV (differential)33kV witness fee £3,200 vs 11kV fee £600. Net additional £2,600.DNO schedule£2,600
Equipment sub-total£4,400
5 · CHARGES — Prelims extension
5.1Site prelims — 1.5-week extension to planned CompletionWeekly prelims rate £3,200/wk × 1.5 weeks. Driven by DNO witness testing lead time extension (4 wks vs 2 wks).Programme£4,800
Charges sub-total£4,800
TOTAL DEFINED COST£38,600
FEEFee percentage applied to Defined Cost11.5% per Contract Data Part 2£4,439
TOTAL CE-009 QUOTATION£43,039

Quotation submitted as £43,039. The detailed build-up above supports the submitted figure. Every line references evidence in The File. The deductions (original 11kV costs that would have been incurred anyway) demonstrate the "change in Defined Cost" approach — not gross cost, but the net additional cost caused by the compensation event.

VARIATION PIPELINE — MONTH 7

£300,439 Valued — Full Pipeline

The Count maintains the live variation pipeline showing every CE with its valued position. This feeds directly into the Margin Cockpit (Pack 05) for monthly margin tracking.

CEDescriptionValuedStatus
CE-001Additional fire-rated cable penetration seals£8,200Agreed
CE-002Revised BMS point schedule — 34 additional points£14,600Agreed
CE-003Late access to HV substation — 3-week delay£41,800Agreed
CE-004Unmapped gas main in cable trench zone£22,400Agreed
CE-005PM stop instruction — archaeological find£16,800Agreed
CE-006EV charging specification upgrade — 22kW to 50kW DC£38,200Agreed
CE-007Late issue of revised ventilation design£18,400Agreed
CE-008Additional external lighting columns£25,800Agreed
CE-009HV switchgear design change£43,039Submitted
CE-010Concealed asbestos in riser duct£12,400Submitted
CE-011Late power-on date from DNO£18,200Submitted
CE-012Additional emergency lighting to mezzanine£7,800Submitted
CE-013Fire alarm panel relocation£12,200Valuing
CE-014Late landlord BMS integration spec£20,600Valuing
Total Pipeline£300,439Agreed: £186,200
£186,200
AGREED
£81,439
SUBMITTED
£32,800
IN VALUATION
STAGE 05 GATE — THE COUNT

Every Pound Sourced. Every Rate Evidenced.

Before a CE moves to The Drop (Stage 06), The Count confirms: the Defined Cost is built from source evidence (not estimated), deductions for work that would have been done anyway are included, the Fee is correctly applied, and the total reconciles to the submitted quotation figure.

Defined Cost built per Schedule of Cost Components
Every cost line traces to evidence in The File
Deductions included for costs already in the activity schedule
Fee percentage correctly applied (11.5%)
Programme impact valued separately (prelims extension)
Total reconciles to submitted quotation figure

Handover note to Stage 06 — The Drop™: CE-009 valuation complete at £43,039 (£38,600 Defined Cost + £4,439 Fee). Narrative, evidence and valuation are all aligned. Compile the submission pack: cover letter, entitlement narrative, evidence index, Defined Cost build-up, assessed programme. Format per Alder's submission template.

THE COUNT — SNAPSHOT

£300k valued. Every pound sourced.

14 compensation events valued using Defined Cost + Fee. Every cost line traces to a supplier quotation, a timesheet, a hire invoice or a programme extract in The File. No estimates. No round numbers. No "we think it's about £X." The assessor sees exactly where every number comes from.
PIPELINE
£300k
AGREED
£186k
FEE RATE
11.5%
CEs VALUED
14
built-ai.io · Commercial Control Kit™ · The Count™ · Stage 05 Pack 04 / 09 · Commercial Control Kit™ · © 2026 Built AI Ltd