The Count™ · valuation build-up

Every pound counted, every rate sourced

Defined Cost built from evidence, not estimates - the valuation that stands up because every number traces to a document in The File.

Project
Crestfield Distribution Centre, Warrington
Contract
NEC4 ECC Option A · £3,814,200
Period
Month 7 of 12 · May 2026
Reference
CREST-VBU-CE009
Prepared by
BuiltAI Intelligence Ltd
Fee
11.5% per Contract Data Part 2

Illustrative example: fictional project and parties.

£300,439Pipeline valued, 14 CEs
£186,200Agreed to date
£43,039CE-009 quotation
11.5%Fee rate
BuiltAI Intelligence Ltd · built-ai.ioThe Count™ · Stage 05
01Mechanism

Defined Cost plus Fee - not daywork, not guesswork

Under NEC4 ECC Option A, compensation events are assessed as the change in Defined Cost plus the resulting Fee (clause 63.1). Defined Cost is the actual cost of the changed work, broken into the Schedule of Cost Components - people, equipment, plant and materials, subcontractors and charges. The Fee (11.5% here, per Contract Data Part 2) is then applied. Every valuation follows the same structure: Defined Cost by component, each sourced from evidence in The File, the Fee applied at the end.

02Build-up

CE-009 - the Defined Cost build-up in detail

Structured per the Schedule of Cost Components; every line traces to an evidence item in The File. Deductions are taken for the 11kV work already in the Activity Schedule - the net additional cost, not the gross.

CatDescriptionEvidenceDefined Cost
1.133kV MCSET switchgear panel, supply only, deliveredEV-009-04£48,200
1.2Less: 11kV RM6 ring-main unit, in the original Activity ScheduleAct. Sched.−£29,800
Plant & materials sub-total£18,400
2.1Extended civil base - 2.4m × 1.8m × 300mm reinforced concreteEV-009-05£5,400
2.2Cable-trench diversion around the larger base - 3.6mEV-009-05£2,800
Subcontractor sub-total£8,200
3.1HV jointer, 33kV dry-type stress-cone terminations - 3 daysTimesheet£2,040
3.2Electrician attendance - 2 daysTimesheet£840
3.3Site engineer supervision - 3 days (pro-rata)Timesheet£1,560
3.4Less: 11kV termination labour that would have been incurredAct. Sched.−£1,640
People sub-total (net additional)£2,800
4.133kV primary injection test set - 2-day hire, with calibrationHire quote£1,800
4.2DNO witness-test fee differential - £3,200 at 33kV against £600DNO schedule£2,600
Equipment sub-total£4,400
5.1Site preliminaries - 1.5-week extension at £3,200/wkEV-009-07£4,800
Charges sub-total£4,800
Total Defined Cost£38,600
Fee at 11.5% (Contract Data Part 2)£4,439
Total CE-009 quotation£43,039

The quotation was submitted at £43,039 - the Defined Cost of £38,600 plus the Fee (£4,439) - and the build-up above supports it. The deductions for the original 11kV costs show the "change in Defined Cost" approach: net additional cost, not gross.

03Pipeline

£300,439 Valued - the full pipeline

The live variation pipeline, every CE with its valued position. This feeds the Margin Cockpit (Pack 05) for monthly margin tracking.

CEDescriptionValuedStatus
CE-001Additional fire-rated cable penetration seals£8,200Agreed
CE-002Revised BMS point schedule£14,600Agreed
CE-003Late access to HV substation£41,800Agreed
CE-004Unmapped gas main in cable-trench zone£22,400Agreed
CE-005PM stop instruction - archaeological find£16,800Agreed
CE-006EV charging upgrade - 22kW to 50kW DC£38,200Agreed
CE-007Late issue of revised ventilation design£18,400Agreed
CE-008Additional external lighting columns£25,800Agreed
CE-009HV switchgear design change£43,039Submitted
CE-010Concealed asbestos in riser duct£12,400Submitted
CE-011Late power-on date from DNO£18,200Submitted
CE-012Additional emergency lighting to mezzanine£7,800Submitted
CE-013Fire alarm panel relocation£12,200Valuing
CE-014Late landlord BMS integration spec£20,600Valuing
Total pipeline£300,439Agreed: £186,200
£186,200Agreed (CE-001 to CE-008)
£81,439Submitted (CE-009 to CE-012)
£32,800In valuation (CE-013, CE-014)
04Stage gate

Stage 05 gate - every pound sourced, every rate evidenced

  • Defined Cost built per the Schedule of Cost Components.
  • Every cost line traces to evidence in The File.
  • Deductions included for costs already in the Activity Schedule.
  • Fee percentage correctly applied (11.5%).
  • Programme impact valued separately (the prelims extension).
  • Total reconciles to the submitted quotation figure.

Hand-off to The Drop™: the CE-009 valuation is complete - Defined Cost £38,600 plus the Fee £4,439. Narrative, evidence and valuation are aligned. Compile the submission pack - cover letter, entitlement narrative, evidence index, Defined Cost build-up and assessed programme - to Alder's template.