Completed-not-invoiced · April 2026

Work that is done, valued, and still not billed

The £214k of completed work waiting to be invoiced, by contract and by the blocker holding each line. Expected billing dates depend on the recorded conditions; clearing a blocker does not establish invoice issue or collection.

Client
Meridian M&E Ltd
Portfolio
8 contracts · £14.2m
Reference
MER-CNI-P7
Period
April 2026 · Month 7
Prepared by
BuiltAI Intelligence Ltd
Status
Clearing

Illustrative example: fictional project and parties.

£214kCompleted, not invoiced
5Contracts holding CNI
£170kReported 30-day view - reconciliation pending
£44kReported client-action view - reconciliation pending
BuiltAI Intelligence Ltd · built-ai.ioMER-CNI-P7 · April 2026
01Register

The completed-not-invoiced register

Reported completed work not yet billed, by contract, with the reason it is held and the expected billing date. Sorted by value; the dates remain conditional on the recorded requirements.

RefContractCNIWhy it is heldExpected
RIVR-FMRiverside FM£87.4kAwaiting the client's monthly POMay, wk 2
DOCK-2Docklands Phase 2£54.1kValuation certified, on the next billing runMay, wk 1
CATH-QCathedral Quarter£28.5kHeld pending a scope sign-offMay, wk 3
MERS-GKingsferry Crossing£22.8kCertified, awaiting retention termsMay, wk 2
WHIT-TWhitmore Tower£21.2kOn the next billing runMay, wk 1
Total completed not invoiced£214k5 contracts
02By reason

Why billing is pending

Docklands and Whitmore's £75.3k is on normal billing runs. Riverside's £87.4k awaits the client's PO; Cathedral's £28.5k awaits scope sign-off; Kingsferry's £22.8k awaits retention terms. These conditions affect expected invoice dates, not evidence of collection.

Reported 30-day viewReconciliation pending£170k
Reported client-action viewReconciliation pending£44k

The retained £170k and £44k summary values are not reconciled to the row classifications: £75.3k is on normal billing runs and £138.7k is subject to PO, scope sign-off or retention terms. The business must confirm the summary allocation.

May, week 1
Docklands and Whitmore billing run · £75.3k
May, week 2
Riverside PO and Kingsferry retention terms · £110.2k
May, week 3
Cathedral Quarter scope sign-off · £28.5k
May billing follow-up

All £214k is scheduled for May, subject to normal billing runs, the Riverside FM purchase order, Cathedral Quarter scope sign-off and Kingsferry retention terms. These are expected dates, not guaranteed invoice issue or payment; each condition needs an owner and follow-up.

Reference MER-CNI-P7Period April 2026, Month 7Basis Certified work not yet invoiced