Completed-not-invoiced value stands at £214k across five contracts, with seven individual blockers preventing invoicing. This is an increase of £6k from March. The work is physically complete — the value is earned — but cannot be converted into cash until the specific blocker on each item is resolved.
The single largest CNI item is the Riverside FM monthly application (£87.4k) — rejected by Mitie because the application format does not match their updated template. This is the same root cause driving £124.6k of aged WIP. Together, these two issues on a single contract represent a combined £212k cash exposure from one format problem.
If all seven blockers were resolved this month, £214k of revenue would enter the invoicing pipeline immediately. The estimated cashflow benefit, assuming standard 30-day payment terms, would be £214k received by end of June.
| # | Contract | Completed work | Value | Days out | Blocker | Resolution path | Owner | Target | Status |
|---|---|---|---|---|---|---|---|---|---|
| 01 | Riverside FMMitie | March reactive works and planned maintenance — all completed, signed off by site team | 87,400 | 47d | Format | Reformat monthly application to match Mitie's updated template. Combine with WIP item. | KHK. Hughes | 02 May ⚠ | Overdue |
| 02 | Cathedral QuarterISG | M&E first fix — floors 3–5 complete, inspected and accepted. Measured rates queried by ISG QS. | 54,100 | 38d | QS query | Rate comparison sent 24 Apr. Follow up if no response by 9 May. Escalate to ISG PM. | JPJ. Palmer | 12 May | In progress |
| 03 | Docklands Ph 2Lendlease | Second-fix completion — Level 4 handed over. Retention release pending snagging sign-off. | 28,500 | 34d | Sign-off | Joint inspection with Lendlease site manager. Snagging list 90% complete. Final items due 12 May. | MTM. Taylor | 16 May | In progress |
| 04 | Pennine Pkg CKier | Additional cable containment works — instructed verbally, completed. Missing daywork sheets. | 22,800 | 44d | Evidence | Ops team locating 4 daywork sheets. Once recovered, include in Application 3 resubmission. | RBR. Barker | 09 May | In progress |
| 05 | Trafford RetailMace | Distribution board installation — complete, tested, commissioned. Awaiting Mace QS site visit. | 21,200 | 22d | QS avail. | Mace QS site visit booked for 8 May. Measure and agree on-site. Include in Valuation 2. | RBR. Barker | 16 May | On track |
| Total CNI | 214,000 | 38d avg |