Cockpit · Aged WIP Tracker (WIP) · Worked example Meridian M&E Ltd · 8 contracts · April 2026 (Month 7) · Margin 21.4% (target 22%) · £14.2m
← Margin Cockpit
● BUILT AI — MARGIN COCKPIT™ — EXAMPLE OUTPUT — All client, site and project details are fictional and for illustration purposes only.
BuiltAI
Confidential
Ref: BAI-WIP-2026-04
Generated: 30 April 2026
Operational Margin Cockpit™ · Aged WIP Tracker

Aged WIP Tracker

Work-in-progress aged by time band with root-cause classification, contract attribution and owner assignment. Meridian M&E Ltd — period ending 30 April 2026.

Total WIP
£387k
+£42k vs March
90+ days
£62k
16% of total · 2 items
Avg age
52 days
+6 days vs March
Root causes
5
top 2 = 68% of value
Contracts affected
8 / 8
2 account for 54%
01
WIP Summary

Total WIP increased by £42k in April to £387k, the highest level in the past six months. Average ageing has risen to 52 days, up from 46 days in March. This is the fifth consecutive month of WIP growth and represents a 78% increase since November 2025.

The concentration risk is significant: two contracts — Riverside FM (£124.6k) and Cathedral Quarter (£86.2k) — account for 54% of total WIP. Both have identifiable, resolvable blockers. Riverside has had two consecutive monthly applications rejected due to format issues. Cathedral Quarter is awaiting QS agreement on measured rates following a valuation query.

If both blockers are resolved before mid-May, WIP could reduce to approximately £176k — below the March position. If unresolved, the 90-day threshold will be breached on both contracts in the next reporting period, requiring board-level escalation.

02
Ageing Band Overview
0 – 30 days
£108k
27.9%
On track
5 items across 5 contracts. All within normal billing cycle. No action required — standard month-end applications in progress.
31 – 60 days
£124k
32.0%
Monitor
4 items across 3 contracts. Largest: Cathedral Quarter £54.1k (QS query) and Pennine Pkg C £32.8k (daywork evidence). Both have resolution actions assigned.
61 – 90 days
£93k
24.0%
At risk
3 items across 2 contracts. Riverside FM accounts for £68.2k — the Feb application that was rejected and not yet resubmitted. Approaching 90-day threshold.
90+ days
£62k
16.0%
Escalate
2 items. Riverside FM Jan application £56.4k (format rejected, 94 days) and Cathedral Quarter legacy item £5.6k (103 days). Both require immediate escalation.
03
WIP Register 14 items
# Contract Description Value Age Root cause Owner Target date Status
90+ days — £62,000 — 2 items
01 Riverside FMMitie · FM Contract Yr 2 January monthly application — rejected by Mitie due to application format not matching their updated template requirements 56,400 94d Format KHK. Hughes 02 May ⚠ Overdue
02 Cathedral QuarterISG · Fitout Legacy valuation adjustment — residual from Val 2, QS has not responded to final query 5,600 103d QS delay JPJ. Palmer 28 Apr ⚠ Overdue
61 – 90 days — £93,000 — 3 items
03 Riverside FMMitie · FM Contract Yr 2 February monthly application — also rejected on same format grounds. Resubmission combined with Jan app. 68,200 63d Format KHK. Hughes 02 May In progress
04 Cathedral QuarterISG · Fitout Valuation 3 measured works — client QS queried 3 rates, response sent 18 Mar, awaiting confirmation 18,400 72d QS delay JPJ. Palmer 09 May In progress
05 Docklands Phase 2Lendlease · Construction Retention release — snagging works 90% complete, final sign-off pending joint inspection 6,400 66d Sign-off MTM. Taylor 16 May In progress
31 – 60 days — £124,000 — 4 items
06 Cathedral Quarter Valuation 4 measured works — QS query on 5 measured rates, response sent 24 Apr 54,100 38d QS delay JPJ. Palmer 12 May In progress
07 Pennine Pkg C Application 3 — 4 missing daywork sheets preventing submission of measured element 32,800 44d Evidence RBR. Barker 09 May In progress
08 Docklands Phase 2 Valuation 8 — Lendlease QS not available for site measure until 12 May 22,100 36d QS avail. MTM. Taylor 19 May Waiting
09 Pennine Pkg C Variation claim — submitted but not yet included in application (£18k, awaiting Kier response) 15,000 32d Variation JPJ. Palmer 23 May Waiting
0 – 30 days — £108,000 — 5 items
10 Whitmore Tower April application in preparation — on standard monthly cycle 18,400 8d Normal KHK. Hughes 07 May On track
11 Mersey Gateway April application in preparation — includes re-measure adjustment if approved 31,800 12d Normal CDC. Dean 09 May On track
12 Alderley Park Valuation 3 submitted — expected agreement w/c 5 May 14,200 18d Normal JPJ. Palmer 12 May On track
13 Trafford Retail Valuation 2 — Mace QS site visit booked 8 May for measure 17,300 22d QS avail. RBR. Barker 16 May On track
14 Docklands Phase 2 April application — final measured section submitted, awaiting inclusion in cert 26,300 6d Normal MTM. Taylor 14 May On track
Portfolio Total 387,000 52d avg
04
Root Cause Analysis

WIP categorised by the underlying root cause preventing invoicing or certification. Addressing the top two categories would resolve £196k (51%) of total WIP.

Root cause
Distribution
Value
%
Items
Application format
£124,600
32.2%
2
QS delay / query
£78,100
20.2%
3
Normal billing cycle
£90,700
23.4%
4
Missing evidence
£47,800
12.4%
2
Client QS availability
£39,400
10.2%
2
Sign-off / Variation
£6,400
1.7%
1
05
Contract × Ageing Heatmap

WIP value (£'000s) by contract and ageing band. Darker shading indicates higher concentration risk.

Contract 0–30d 31–60d 61–90d 90+d Total % of portfolio
Riverside FM
68.2
56.4
124.6 32.2%
Cathedral Quarter
54.1
18.4
5.6
78.1 20.2%
Docklands Phase 2
26.3
22.1
6.4
54.8 14.2%
Pennine Pkg C
47.8
47.8 12.4%
Mersey Gateway
31.8
31.8 8.2%
Whitmore Tower
18.4
18.4 4.8%
Trafford Retail
17.3
17.3 4.5%
Alderley Park
14.2
14.2 3.7%
Total 108.0 124.0 93.0 62.0 387.0 100%
06
Resolution Priorities
Priority 1 · Immediate
Riverside FM — reformat & resubmit
Combine Jan + Feb applications into Mitie's updated format. K. Hughes has the template. Resubmission unlocks £124.6k.
Owner: K. Hughes · Target: 2 May · Value: £124.6k
Priority 2 · This week
Cathedral Quarter — chase QS agreement
Response sent on Val 3 + Val 4. Three rates still queried. Escalate to ISG project manager if no confirmation by 9 May. Value at risk: £78.1k.
Owner: J. Palmer · Target: 9 May · Value: £78.1k
Priority 3 · Process fix
Standardise FM application template
Application format is the single largest root cause at 32.2% of total WIP. Create a standardised template matching all client formats to prevent recurrence.
Owner: K. Hughes · Target: 23 May · Prevention value: £124.6k+
07
Six-Month WIP Trend
£400k £350k £300k £250k £200k Nov Dec Jan Feb Mar Apr 218k 264k 296k 318k 345k 387k
Trend observation: WIP has risen every month for six consecutive periods — from £218k in November to £387k in April (+78%). The primary drivers have been Riverside FM format rejections (persisting since January) and Cathedral Quarter QS delays (persisting since February). Without resolution of these two structural blockers, WIP will continue to climb regardless of billing performance on other contracts. Resolving both would reduce WIP to approximately £184k — below the November baseline.