Margin Cockpit
Margin Cockpit™Pack 05 / 06 · Client deliverable
Scope compliance report · Cathedral Quarter Fitout

What we tendered, against what we have built

A line-by-line comparison of Cathedral Quarter's accepted tender scope and recorded works. It identifies unclaimed change for commercial review; package allocations remain unreconciled and the net-margin effect is not established.

Contract
Cathedral Quarter Fitout · CATH-Q
Client
ISG · for Meridian M&E Ltd
Tender ref
MER-CQ-T001 · 14 Nov 2025
Reference
MER-SCR-P7
Period
To 30 April 2026 · Weeks 10-14
Status
Margin at risk

Illustrative example: fictional project and parties.

£2.10mAccepted tender value
24Scope items, 6 packages
£67.8kDelivered, not yet claimed
−2.6ppMargin gap, 19.4% vs 22.0%
BuiltAI Intelligence Ltd · built-ai.ioMER-SCR-P7 · April 2026
01Summary

Eight items over scope, two under

Comparing the accepted tender against the works recorded to the end of April finds ten of the 24 scope items running at a variance. Eight are over scope, worth £90.2k of additional work, of which only £22.4k has been raised as a variation. The remaining £67.8k is work Meridian is delivering and paying for but has not yet claimed. Two items are under scope, worth £8.2k, which should be tracked as client credits.

Over scope, claimed£22.4k
Over scope, unclaimed£67.8k
Under scope, credit due£8.2k
A position to review, not a proved margin recovery

Cathedral Quarter is 2.6 points below the 22.0% target, at 19.4%. The unclaimed £67.8k is reported additional work, not agreed recovery or net margin. Its contribution to the shortfall needs costs and a margin denominator; applicable notices and entitlement require commercial review.

02Register

The scope variance register

The ten items running at a variance, by package, with the evidence behind each. Fourteen further items are being delivered on scope and are not shown. Values are the additional or reduced work against the tendered allowance.

RefItem and packageValueStatusEvidence
A-04Cable tray 150mm, additional runs L3-5 · Containment£11.4kClaimedWk 12 report, photos
D-02Additional fire-stopping, Level 4 · Fire & life safety£11.0kClaimedInstruction, photos
A-07Cable tray 300mm, additional riser runs · Containment£14.2kUnclaimedWk 13 report, marked drawings
B-05Additional final circuits, Level 5 · Electrical distribution£12.6kUnclaimedProgress photos, as-builts
D-06Fire damper additions, revised layout · Fire & life safety£11.6kUnclaimedInstruction on site, photos
E-03Additional BMS I/O points · BMS & controls£10.4kUnclaimedRevised points schedule
C-08Additional pipework insulation · Mechanical / HVAC£9.8kUnclaimedWk 14 report, photos
C-11Extended commissioning attendance · Mechanical / HVAC£9.2kUnclaimedSite diary, timesheets
B-09Reduced small power, descoped Level 6 · Electrical distribution−£5.4kUnder scopeISG design change
E-07Removed graphics package · BMS & controls−£2.8kUnder scopeISG design change
Net variance against tender£82.0k10 of 24 items
03Recovery

Closing the gap

The retained £42.6k and £25.2k summary allocations are unreconciled. The item rows give £25.8k of unclaimed containment/fire and £42.0k elsewhere; the Unclaimed register labels the same £67.8k differently. No readiness or package allocation is accepted until the owner reconciles those records.

Allocation unresolvedReported first summary bucket, not ready-to-submit value£42.6k
Allocation unresolvedReported second summary bucket, not a verified package split£25.2k
Client creditsUnder-scope, offset in the account£8.2k
The action

Reconcile the £42.6k/£25.2k summaries to the item register before setting submission priorities. Review evidence, notices, entitlement and valuation; retain the £8.2k client credits. The prior 2.2-point recovery estimate is not validated: costs and the margin denominator are not supplied, so no closure of the 2.6-point gap is established.

Variance by package

PackageItemsOver scopeUnder scope
A · Containment & cabling2£25.6k-
B · Electrical distribution2£12.6k−£5.4k
C · Mechanical / HVAC2£19.0k-
D · Fire & life safety2£22.6k-
E · BMS & controls2£10.4k−£2.8k
F · Prelims & attendance14on scope-
10 variance items of 2424£90.2k−£8.2k
Reference MER-SCR-P7Contract Cathedral Quarter, CATH-QBasis Tender MER-CQ-T001 vs works to 30 Apr

Up next

FVA · Forecast vs Actual Back to the Margin Cockpit page