Operational Margin Cockpit™ · Scope Compliance Report

Scope vs Actual

Line-by-line comparison of the accepted tender scope against actual works delivered — using data from weekly site reports, progress updates and programme records. Cathedral Quarter Fitout — ISG — Period ending 30 April 2026.

Quoted value
£2.10m
accepted tender
Scope items
24
across 6 packages
Over-scope items
8
doing more than quoted
Under-scope items
2
doing less than quoted
Unclaimed value
£67.8k
variation not raised
Already claimed
£22.4k
variation submitted
01
Compliance Summary

Analysis of weekly site reports (Weeks 10–14), progress photographs, subcontractor delivery records and the programme update dated 25 April 2026 against the accepted tender submission (Ref: MER-CQ-T001, dated 14 November 2025) identifies eight scope items where actual works exceed the quoted scope and two items where works are below the quoted allowance.

Of the eight over-scope items, only two have had variations raised (combined value £22.4k). The remaining six represent £67.8k of unclaimed additional work — work that Meridian is delivering and paying for but has not yet submitted a claim against. This is the single largest contributor to the −2.6pp margin gap on this contract.

The two under-scope items (combined value £8.2k) represent work that was quoted but has been descoped or reduced by ISG design changes. These should be tracked as potential client credits and factored into the forecast-at-completion.

02
Scope Compliance Register 24 items · 6 packages
# Scope item Quoted qty Actual qty Variance Quoted £ Variance £ Status Source evidence
Package A — Containment & Cabling
A1 Cable tray — 150mm galv, Levels 3–5Quoted: 420 lin.m · Actual: 486 lin.m 420 m 486 m +16% 33,600 +5,280 Unclaimed Wk 12 report · Progress photos F3-042 to F3-068
A2 Cable tray — 300mm galv, risersQuoted: 85 lin.m · Actual: 124 lin.m 85 m 124 m +46% 11,050 +5,070 Unclaimed Wk 11 report · Riser drawing rev C vs tender rev A
A3 Containment route change — Level 4 corridorQuoted: not included · Actual: 38 lin.m additional 38 m New +6,840 Drafted ISG AI-042 · Design change notice 18 Mar
A4 Cat6A data cabling — Levels 3–5 2,400 m 2,380 m ≈ Match 62,400 On scope Wk 14 progress report
Package B — Electrical Distribution
B1 DB installation — additional boardsQuoted: 12 boards · Actual: 15 boards 12 nr 15 nr +25% 43,200 +10,800 Unclaimed ISG RFI-028 · Revised electrical layout rev D
B2 Submain cabling — additional runsQuoted: 8 runs · Actual: 11 runs (3 additional for new DBs) 8 nr 11 nr +38% 28,800 +10,800 Unclaimed Linked to B1 · Same design change
B3 Final circuit wiring — Levels 3–5 680 pts 672 pts ≈ Match 108,800 On scope Wk 14 measured progress
Package C — Mechanical / HVAC
C1 Ductwork — additional Level 4 branchQuoted: not included · Actual: 22 lin.m rectangular + 6 fittings 22 m New +8,140 Unclaimed ISG AI-038 · Architect revision Level 4 plan
C2 FCU installation — 2 additional unitsQuoted: 18 units · Actual: 20 units 18 nr 20 nr +11% 54,000 +6,000 Submitted VAR-CQ-003 submitted 12 Apr
C3 Pipework — LTHW flow/return 340 m 338 m ≈ Match 74,800 On scope Wk 13 measured
C4 AHU plantroom works — reduced scopeQuoted: full AHU connection · Actual: partial (client using existing) 1 nr partial −40% 18,400 −5,200 Descoped ISG email 22 Feb · Existing AHU retained
Package D — Fire & Life Safety
D1 Fire alarm — additional devicesQuoted: 86 devices · Actual: 104 devices (partition changes) 86 nr 104 nr +21% 17,200 +3,600 Unclaimed Partition layout rev E vs tender rev B
D2 Emergency lighting — Levels 3–5 142 nr 140 nr ≈ Match 24,850 On scope Wk 14 install count
Package E — BMS & Controls
E1 BMS points — as tendered 84 pts 84 pts Match 42,000 On scope BMS schedule unchanged
Package F — Prelims & Attendance
F1 Programme extension — 2 weeksQuoted: 24 weeks · Actual: 26 weeks (design delay) 24 wk 26 wk +8% 86,400 +11,280 Submitted VAR-CQ-005 · Time claim submitted 20 Apr
F2 Welfare provision — reduced requirementQuoted: standalone cabin · Actual: shared with main contractor 1 nr shared Reduced 8,400 −3,000 Over-recovery ISG provided shared welfare from Wk 1
Contract Total 2,100,000 +59,610
Showing 15 of 24 scope items. Remaining 9 items are on-scope with no material variance.
03
Unclaimed Value Summary
Over-scope · No variation raised — £67.8k
B1/B2 — 3 additional DBs + submain runs
£21,600
C1 — Level 4 ductwork branch (new)
£8,140
A1/A2 — Additional cable tray (measured)
£10,350
A3 — Containment route change (drafted)
£6,840
C2 — 2 additional FCUs (submitted)
£6,000
D1 — 18 additional fire alarm devices
£3,600
F1 — 2-week programme extension (submitted)
£11,280
£67.8k total over-scope — of which £22.4k has variations raised (£6k submitted, £11.3k submitted, £6.8k drafted). Remaining £43.8k has no variation action at all.
Margin impact analysis
Current state
Contract margin at 19.4% — 2.6pp below target. The £43.8k of unclaimed over-scope work is being absorbed into costs without corresponding revenue recovery. This accounts for approximately 2.1pp of the margin gap.
If all variations raised
Submitting variations for the remaining £43.8k (net of the £8.2k under-scope credit) would add approximately +1.7pp to contract margin, bringing it to 21.1% — within 0.9pp of target.
Root cause: The over-scope items fall into two categories — design-driven changes (architect revisions to partitions, containment routes and mechanical layouts) and measured quantity exceedances (more cable tray, more fire alarm devices than the tender drawings showed). Both are legitimate variation triggers but were not captured at the point of change because the site team treated them as part of the normal workflow.
04
Recommended Actions
Immediate · £21.6k
Raise variation for DB & submain additions
Items B1/B2 — 3 additional distribution boards and submain runs instructed via revised electrical layout. Evidence: ISG RFI-028, drawing rev D, weekly report Wk 11.
Owner: J. Palmer · By: 09 May
This week · £18.5k
Raise variations for ductwork & cable tray
Items A1/A2/C1 — measured quantity exceedances and new ductwork branch. Combine into a single measured works variation with photo and drawing evidence.
Owner: J. Palmer · By: 16 May
Process · Ongoing
Implement weekly scope compliance check
Run this scope comparison weekly as part of the site reporting cycle. Flag any item where actual quantity exceeds quoted by >5% or where new work is instructed. Auto-trigger variation notice.
Owner: K. Hughes · By: Ongoing