Analysis of weekly site reports (Weeks 10–14), progress photographs, subcontractor delivery records and the programme update dated 25 April 2026 against the accepted tender submission (Ref: MER-CQ-T001, dated 14 November 2025) identifies eight scope items where actual works exceed the quoted scope and two items where works are below the quoted allowance.
Of the eight over-scope items, only two have had variations raised (combined value £22.4k). The remaining six represent £67.8k of unclaimed additional work — work that Meridian is delivering and paying for but has not yet submitted a claim against. This is the single largest contributor to the −2.6pp margin gap on this contract.
The two under-scope items (combined value £8.2k) represent work that was quoted but has been descoped or reduced by ISG design changes. These should be tracked as potential client credits and factored into the forecast-at-completion.
| # | Scope item | Quoted qty | Actual qty | Variance | Quoted £ | Variance £ | Status | Source evidence |
|---|---|---|---|---|---|---|---|---|
| Package A — Containment & Cabling | ||||||||
| A1 | Cable tray — 150mm galv, Levels 3–5Quoted: 420 lin.m · Actual: 486 lin.m | 420 m | 486 m | +16% | 33,600 | +5,280 | Unclaimed | Wk 12 report · Progress photos F3-042 to F3-068 |
| A2 | Cable tray — 300mm galv, risersQuoted: 85 lin.m · Actual: 124 lin.m | 85 m | 124 m | +46% | 11,050 | +5,070 | Unclaimed | Wk 11 report · Riser drawing rev C vs tender rev A |
| A3 | Containment route change — Level 4 corridorQuoted: not included · Actual: 38 lin.m additional | — | 38 m | New | — | +6,840 | Drafted | ISG AI-042 · Design change notice 18 Mar |
| A4 | Cat6A data cabling — Levels 3–5 | 2,400 m | 2,380 m | ≈ Match | 62,400 | — | On scope | Wk 14 progress report |
| Package B — Electrical Distribution | ||||||||
| B1 | DB installation — additional boardsQuoted: 12 boards · Actual: 15 boards | 12 nr | 15 nr | +25% | 43,200 | +10,800 | Unclaimed | ISG RFI-028 · Revised electrical layout rev D |
| B2 | Submain cabling — additional runsQuoted: 8 runs · Actual: 11 runs (3 additional for new DBs) | 8 nr | 11 nr | +38% | 28,800 | +10,800 | Unclaimed | Linked to B1 · Same design change |
| B3 | Final circuit wiring — Levels 3–5 | 680 pts | 672 pts | ≈ Match | 108,800 | — | On scope | Wk 14 measured progress |
| Package C — Mechanical / HVAC | ||||||||
| C1 | Ductwork — additional Level 4 branchQuoted: not included · Actual: 22 lin.m rectangular + 6 fittings | — | 22 m | New | — | +8,140 | Unclaimed | ISG AI-038 · Architect revision Level 4 plan |
| C2 | FCU installation — 2 additional unitsQuoted: 18 units · Actual: 20 units | 18 nr | 20 nr | +11% | 54,000 | +6,000 | Submitted | VAR-CQ-003 submitted 12 Apr |
| C3 | Pipework — LTHW flow/return | 340 m | 338 m | ≈ Match | 74,800 | — | On scope | Wk 13 measured |
| C4 | AHU plantroom works — reduced scopeQuoted: full AHU connection · Actual: partial (client using existing) | 1 nr | partial | −40% | 18,400 | −5,200 | Descoped | ISG email 22 Feb · Existing AHU retained |
| Package D — Fire & Life Safety | ||||||||
| D1 | Fire alarm — additional devicesQuoted: 86 devices · Actual: 104 devices (partition changes) | 86 nr | 104 nr | +21% | 17,200 | +3,600 | Unclaimed | Partition layout rev E vs tender rev B |
| D2 | Emergency lighting — Levels 3–5 | 142 nr | 140 nr | ≈ Match | 24,850 | — | On scope | Wk 14 install count |
| Package E — BMS & Controls | ||||||||
| E1 | BMS points — as tendered | 84 pts | 84 pts | Match | 42,000 | — | On scope | BMS schedule unchanged |
| Package F — Prelims & Attendance | ||||||||
| F1 | Programme extension — 2 weeksQuoted: 24 weeks · Actual: 26 weeks (design delay) | 24 wk | 26 wk | +8% | 86,400 | +11,280 | Submitted | VAR-CQ-005 · Time claim submitted 20 Apr |
| F2 | Welfare provision — reduced requirementQuoted: standalone cabin · Actual: shared with main contractor | 1 nr | shared | Reduced | 8,400 | −3,000 | Over-recovery | ISG provided shared welfare from Wk 1 |
| Contract Total | 2,100,000 | +59,610 | ||||||