| Status | Value | Contracts | Action |
|---|---|---|---|
| Agreed & invoiced | £412,000 | 5 | Revenue recognised. In Sage. |
| Agreed — not yet invoiced | £202,000 | 4 | Invoice immediately. CNI item. |
| Submitted — awaiting assessment | £92,000 | 3 | Chase PM responses. Track deadlines. |
| In preparation | £68,000 | 3 | Complete narratives. Submit by month-end. |
| Anticipated — not yet notified | £118,000 | 2 | Notify immediately. Time-bar risk on £31k. |
| TOTAL PIPELINE | £892,000 | 8 |
At risk: £186k (submitted + anticipated) is revenue not yet secured. The £31k re-measure on Mersey Gateway has a client deadline of 15 May — if not submitted by then, entitlement weakens significantly. This is the highest-priority action in The Pulse.
3 deductions raised across the portfolio in April. 2 accepted (£12,200). 1 being defended (£6,200 on Riverside Academy — disputed liquidated damages calculation). Defence pack produced by CCK, submitted to the PM 22 April.
Handover to Stage 05 — The Pulse™: Mersey Gateway £31k re-measure is the priority action. Riverside Academy defence pack submitted — track response. £202k agreed-not-invoiced needs clearing this month.