Margin Cockpit
Margin Cockpit™Pack 05 / 06 · Client deliverable
Unclaimed variation register · April 2026

The change we have done, and not yet asked to be paid for

Potential gross change value identified from site records, not yet in the variation pipeline. Evidence ratings guide review; entitlement, notices, valuation, costs and collection remain unconfirmed. These estimates are not established net margin.

Client
Meridian M&E Ltd
Portfolio
8 contracts · £14.2m
Reference
MER-UVR-P7
Period
April 2026 · Month 7
Prepared by
BuiltAI Intelligence Ltd
Status
Opportunity

Illustrative example: fictional project and parties.

£224kEstimated unclaimed opportunity
8Opportunities identified
£112kStrong site evidence, commercial review required
£67.8kCathedral Quarter, the largest opportunity
BuiltAI Intelligence Ltd · built-ai.ioMER-UVR-P7 · April 2026
01What it is

Opportunity, not yet pipeline

This register is separate from the £482k variation pipeline. It records £224k of potential gross additional value surfaced from site records, not an agreed claim, net margin or collected cash. Every line needs a commercial reviewer to check notices, entitlement, valuation and costs before submission; agreement, billing and payment are later steps.

How it is found

The Cockpit reads site records, verbal instructions logged on site, and email correspondence against the contract scope, and flags work that appears to sit outside the agreed price. A commercial reviewer confirms each before it moves to the pipeline.

02Register

The unclaimed opportunity register

Estimated opportunities and site-evidence ratings, not confidence of contractual recovery. Cathedral's £42.6k and £25.2k package allocations are unreconciled with the Scope Compliance Report's item rows; the same £67.8k is not additional exposure. Preserve the provisional labels pending owner reconciliation.

RefOpportunityEst. valueEvidenceEvidence rating
CATH-QOut-of-scope containment and cable tray£42.6kSite diary, marked drawingsStrong
CATH-QAdditional fire-stopping, revised layout£25.2kInstruction on site, photosStrong
MERS-GStanding time, delayed access£38.6kSite diary, daywork sheetsTo verify
RIVR-FMReactive attendances beyond the PPM scope£34.4kHelpdesk log, timesheetsMedium
BLUE-TClient-requested finishes, Level 8£26.2kInstruction on site, photosStrong
DOCK-2Extended commissioning support£22.6kEmail correspondenceMedium
WHIT-TMinor client-requested extras£18kInstruction on siteStrong
RIVR-FMOut-of-hours attendances£16.4kHelpdesk logTo verify
Estimated opportunity£224k8 opportunities
03Convert

Converting opportunity into pipeline

Strong, Medium and To verify describe the reported site evidence. All lines need the review above; Strong does not establish entitlement, submission readiness or agreement. Cathedral's package allocation must also be reconciled.

Review before submissionStrong site evidence, entitlement unconfirmed£112k
Confirm firstMedium evidence, reviewer check£57k
To verifyStanding time and attendances£55k
The action

Prioritise commercial review of the £112k Strong and £57k Medium estimates, and verify the £55k balance. Submit only approved lines within applicable contract requirements. These gross estimates do not establish recoverable net margin or guaranteed collection.

The conversion plan

Owners and target dates are review objectives, not assurance that a variation will be accepted. Check each line's contractual requirements and supporting value before adding it to the pipeline.

OpportunityNext stepOwnerTarget
Cathedral containment and cable trayReview, then raise if approvedK. Hughes09 May
Cathedral fire-stoppingReview, then raise if approvedK. Hughes09 May
Bluewater client finishesReview, then raise if approvedK. Hughes12 May
Whitmore client extrasReview, then raise if approvedJ. Palmer12 May
Riverside reactive attendancesConfirm entitlementJ. Palmer16 May
Docklands commissioning supportConfirm entitlementJ. Palmer16 May
Kingsferry standing timeVerify site recordsR. Barker23 May
Riverside out-of-hours attendancesVerify helpdesk logR. Barker23 May
8 opportunities£224kby 23 May
Timing and entitlement both require review

The £224k total is provisional. The applicable notice dates and consequences must be checked against each contract; no universal expiry rule or established entitlement is supplied. Site evidence alone does not prove recovery, net benefit or payment.

Target review of the strongest £112k inside a fortnight; submission remains conditional on approval and the Cathedral allocation reconciliation.

Reference MER-UVR-P7Period April 2026, Month 7Basis Identified, not yet in the pipeline

Up next

QBR · QBR / Board Reporting Narrative Back to the Margin Cockpit page