Scope compliance analysis across the portfolio has identified £112k of additional work being delivered beyond the accepted tender scope where no variation has been raised. This covers 14 individual items across four contracts. The work has been carried out, the cost has been incurred, but no claim has been submitted.
Of the £112k, £52k qualifies as a "quick win" — the evidence already exists (drawings, RFIs, site reports, photos) and a variation could be prepared and submitted within two weeks. A further £42k requires some evidence gathering or measurement confirmation. The remaining £18k has an approaching notice period and must be actioned within the next 30 days to preserve entitlement.
If recovered at the portfolio average variation recovery rate of 82%, these opportunities would contribute an estimated +£92k to revenue and lift blended margin by approximately +0.8 percentage points — the difference between 21.4% and 22.2%, which would bring the portfolio above target for the first time since October 2025.
| # | Contract | Scope exceedance | Est. value | Type | Readiness | Evidence held | Owner | Urgency |
|---|---|---|---|---|---|---|---|---|
| 01 | Cathedral Quarter | 3 additional DBs + submain runs — ISG revised electrical layout | 21,600 | Design change | Ready | RFI-028, drawing rev D, Wk 11 report | JPJ. Palmer | Expiring |
| 02 | Cathedral Quarter | Cable tray quantity exceedance — 66m additional across Levels 3–5 | 10,350 | Measured qty | Ready | Wk 12 report, progress photos F3-042–068 | JPJ. Palmer | High |
| 03 | Cathedral Quarter | Level 4 ductwork branch — new work from architect revision | 8,140 | Design change | Needs meas. | AI-038, Level 4 plan rev, site photos | JPJ. Palmer | High |
| 04 | Cathedral Quarter | 18 additional fire alarm devices — partition layout changes | 3,600 | Design change | Ready | Partition layout rev E vs tender rev B | JPJ. Palmer | Medium |
| 05 | Pennine Pkg C | Additional cable containment — verbally instructed, 48m beyond scope | 14,400 | Instruction | Needs evidence | Verbal instruction, daywork sheets (missing) | RBR. Barker | High |
| 06 | Pennine Pkg C | Earthing system — additional earth rods and bonding beyond spec | 8,200 | Spec change | Ready | Updated earthing spec, site install records | RBR. Barker | Medium |
| 07 | Docklands Phase 2 | Riser pipework — 12m additional run due to revised plant room layout | 9,600 | Design change | Ready | Plant room layout rev C, measured on site | MTM. Taylor | Medium |
| 08 | Docklands Phase 2 | Additional fire stopping — 24 penetrations not on tender drawings | 7,200 | Measured qty | Needs photos | Site count confirmed, photos needed before cover | MTM. Taylor | Urgent |
| 09 | Trafford Retail | Temporary power supply — not included in tender, instructed by Mace | 12,800 | Instruction | Needs evidence | Email instruction from Mace PM, hire invoices | RBR. Barker | Expiring |
| 10 | Trafford Retail | Night shift premium — 3 weekends not in original programme | 5,800 | Programme | Ready | Programme comparison, labour records, Mace emails | RBR. Barker | High |
| 11–14 | 4 additional minor items across Cathedral Quarter and Pennine (measured qty exceedances <£3k each) | 10,310 | Various | Mixed | Various site reports and measurements | Various | Medium | |
| Portfolio Total — Unclaimed | 112,000 | |||||||