RAMS Factory
RAMS Factory™Pack 03 / 06 · Client deliverable
Environmental controls · bridge replacement

Calibrated to the receptors, not generic

Six categories of environmental control covering water, air, noise, waste, ecology and site protection, each calibrated to the receptors at this specific location rather than a generic schedule. A watercourse runs twelve metres from the works, so a pollution incident, ecological breach or noise exceedance is grounds to stop work and notify the ecologist.

Client
River Marsh Bridge
Site
B1071 crossing · IP21 5RH
Work type
Civils, bridge demolition and rebuild
Reference
BAI-ENV-MRH-BRG-001
Sector
Infrastructure
Status
For approval

Illustrative example: fictional project and parties.

6Control categories
33Individual controls in the plan
3High-priority categories
12 mFrom the works to the watercourse
BuiltAI Intelligence Ltd · built-ai.ioBAI-ENV-MRH-BRG-001 · Rev 01
01Receptors

The receptors this plan protects

The plan is engineered around the receptors particular to this location, not lifted from a template. The River Marsh runs twelve metres from the worksite inside an SSSI buffer with recorded water vole and otter populations and a trout fishery downstream. Schedule 1 breeding birds, barn owls and kingfishers, are recorded within 200 metres, so vegetation clearance is restricted to September through February. The nearest residential properties are 80 metres away, listed cast-iron parapets sit adjacent to the works, and the county archaeologist holds a watching brief on any excavation deeper than one metre.

Programme window

The works run 22 weeks from August 2026 to January 2027, timed so the ecology windows and the breeding-bird restriction shape the programme rather than fight it.

02Controls

Six categories, thirty-three controls

Each category carries a priority calibrated to its receptor. Three are high priority: water, noise and ecology.

RefCategory and headline controlPriority
ENV-01Water, silt fence, bunded fuel, zero discharge to the watercourseHigh
ENV-02Air and dust, bowser suppression, wheel wash, boundary monitorsMedium
ENV-03Noise and vibration, BS 5228 hours, 65 dB(A) action thresholdHigh
ENV-04Waste, segregated skips, SWMP targeting 90 percent diversionMedium
ENV-05Ecology, vole exclusion fencing, clearance September to FebruaryHigh
ENV-06Site protection, listed-parapet protection, footpath diversionMedium

Three controls run as continuous monitors, and five spill kits are held across the plant locations, fuel store and bridge deck.

03Stop-work

Triggers that stop the job

Six events trigger an immediate stop pending review, each non-negotiable: turbidity or sheen on the River Marsh, a pollution incident of any volume, a noise exceedance above 65 dB(A) at a boundary monitor, a water vole sighting inside the exclusion zone, accidental clearance during the breeding-bird window, and an archaeological discovery during excavation. Each event triggers its statutory notification, to the Environment Agency, the ecologist or the county archaeologist, within the relevant window.

Understood at induction

Stop-work triggers are briefed to every operative at induction. Controls are calibrated to actual conditions on this site, and the monitoring, ecologist briefings and notification routes are agreed and in place before works begin.

04Monitoring

What is monitored, and who is told

Three receptors carry continuous monitoring; the rest are inspected on a fixed cycle. Every reading has a threshold and a named route for the notification if it is crossed.

ParameterMethod and frequencyThreshold and route
Watercourse turbidityContinuous probe upstream and downstream of the worksVisible sheen or turbidity, stop and notify the Environment Agency
Boundary noiseTwo fixed monitors, logged through working hours65 dB(A) action level, review method before resuming
Dust depositionBoundary gauges read weekly against the baselineRising trend, add suppression and re-read daily
Vole exclusion zoneEcologist walkover before clearance and weekly afterAny sighting inside the fence, stop and call the ecologist
Fuel and washout storesDaily visual by the supervisor, weekly bund integrity checkAny loss of containment, deploy spill kit and log
Archaeology watching briefCounty archaeologist attends excavation below one metreAny find, stop excavation and notify the county archaeologist
Vibration at listed parapetsTransducer during breakout adjacent to the cast-iron parapetsPeak particle velocity limit, pause and reassess the method
River level and flowGauge checked each shift and before any in-channel taskHigh-flow forecast, suspend works near the watercourse
Breeding-bird windowEcologist confirms clearance stays within September to FebruaryAny active nest found, stop clearance and call the ecologist
Waste diverted from landfill90% target
Categories on continuous monitors3 of 6
Spill kits held across the site5 held
Reported monthly

Monitoring data, waste transfer notes and any incident records are compiled into a monthly environmental report for the client and the principal contractor. The record closes out at completion with the SWMP reconciliation and the ecologist sign-off.

Reference BAI-ENV-MRH-BRG-001Programme 22 weeks, Aug 2026 to Jan 2027Revision 01

Up next

EMG · Emergency Arrangements Back to the RAMS Factory page