This schedule was generated from the Output 02 Task Sequence and Output 03 Hazard-Risk-Control Matrix using Built AI's PPE and plant knowledge base. Inspection and calibration dates have been verified by a competent person against current certification records. Plant marked DUE or OVERDUE must be re-certified before mobilisation.
PPE matrix — task by PPE type
REQ — required PPE for the task · ADD — additional PPE if conditions trigger it · OPT — not required for this specific task
EN 397 Class E
EN 20345 S3 SRC
EN 166
SNR ≥ 25 dB
EN 20471 Class 2
EN IEC 61482-2 Cat 2
EN 60903 Class 2
EN 50321
FFP3 / cartridge
Calibrated, in-date
Plant schedule — major plant with inspection currency
HV PlantMobile elevated work platform (MEWP)Scissor lift · 8m platform height
HV-PT-01HV PlantEarth application / removal trolleyPortable earth application rated 25 kA / 1 s · 11 kV system
HV-PT-02HV PlantHot-stick / live-line tools1.2 m insulated rod for switch and earth operation
HV-PT-03HV PlantInsulating mat / mattingSwitch room access matting — 11 kV class
HV-PT-04HV PlantOil sampling kitSealed glass vials, sampling syringes, dispatch packaging
HV-PT-05HV PlantThermal imaging cameraFLIR T540 — for termination scan and post-energisation check
HV-PT-06Equipment list — smaller items, instruments and consumables
Operator competency — who is qualified to do what
For HV substation works the competency stack is non-negotiable. No operative steps onto the work area without their authorisation in date and logged against this schedule.
HV-PT-03 (Hot-stick / live-line tools) is due for its 6-monthly dielectric test within the next 30 days. The test must be completed and certificate filed before the planned outage on Sun 17 May, or a substitute set must be sourced. This is a hard mobilisation gate — no mobilisation without test certificate.
Author confirmation
I confirm this schedule has been prepared from the approved task sequence, hazard-control matrix and current plant / equipment certification records. Inspection and calibration dates verified at preparation. The schedule supports the wider RAMS pack for issue.
Author + role Signature + dateApproval for issue
As Senior Authorised Person for HV operations on this site, I confirm the PPE matrix, plant schedule, equipment list and competency matrix are appropriate for the planned scope of works. Approved for issue subject to closure of the pre-mobilisation action above.
SAP-HV name + authorisation no. Signature + date of approval