RAMS Factory · Method Statement (MS) · Worked example Method Statement · Linnet Lane Cat-A Fit-Out · BAI-MSS-LNL-MCR-001 · Commercial fit-out
RAMSFactory
Output 04 of 11 BAI-MSS-LNL-MCR-001 02-05-2026
← RAMS FACTORY
OUTPUT 04 — METHOD STATEMENT ● COMPLETED · FOR REVIEW BAI-MSS-LNL-MCR-001 · 02 MAY 2026 · REV 02

Method Statement Sheet 7 sequenced operations · resources locked · referenced standards · pre-mob sign-off.

Defines the safe sequence of works for the Cat-A fit-out at Linnet Lane, Manchester — Levels 4–6 mechanical first-fix and ceiling-grid installation. Each step is gated on inspection sign-off. Read alongside the corresponding Risk Assessment Sheet (Output 03 — BAI-RAS-RVS-EDI-001 pattern).

Client
Tunbridge Capital LLPProperty & investment · NW
Site
Linnet Lane Cat-A Fit-OutLinnet Tower, M2 5BU · Levels 4–6
Work type
Cat-A commercial fit-outM&E first fix · ceiling grid · partitions
Reference
BAI-MSS-LNL-MCR-001Prepared by Built AI · 02-05-2026

AI-ASSISTED

This Method Statement was produced using AI-assisted structured generation as part of the RAMS Factory™ workflow. The sequence of operations, resource allocations and inspection gates have been reviewed and confirmed by a competent person. This document is Output 04 of 11. It must be read alongside the corresponding Risk Assessment Sheet (Output 03), the Permits & Isolations Checklist (Output 05) and the project Toolbox Talk (Output 11).

01 SCOPE

Cat-A fit-out, Levels 4–6, mechanical first-fix and ceiling grid.

18,400 sq ft over three floors. Mechanical risers terminate at Level 3; this Method Statement covers the works above that point. Programme: 6 weeks total, mobilisation Week 1, M&E first fix Weeks 2–4, ceiling grid Weeks 4–5, snagging Week 6.

02 SEQUENCE OF OPERATIONS

Seven steps. Inspection-gated.

Each step has explicit pre-conditions and acceptance criteria. Step N+1 cannot start until Step N has been inspected and signed off. The site supervisor holds the inspection register; BAI cross-references it weekly via the QA Checklist (Output 09).

01

Site mobilisation and welfare set-up

Week 1 · Days 1–2 · 2 operatives

Establish on-site welfare unit (jubilee, drying room, toilet block) at car-park location agreed with building manager. Confirm 110V supply at distribution board. Mark exclusion zones at lift lobby entries to Levels 4–6 with barriers + signage. Issue site induction to all incoming operatives.

Welfare in place 110V supply tested Exclusion zones marked Induction logged
02

Containment installation — high-level cable tray

Week 2 · Days 1–4 · 4 electricians

Install perforated steel cable tray to design layout (drawing refs LNL-M-201 to LNL-M-203). Tray spans 6m clear; intermediate hangers at 1.5m centres per BS 6651:1999. Earth-bond every tray at section joints. Hold for inspection by M&E lead before cable pull.

Tray runs match drawings Hangers at 1.5m Bonding tested Inspection signed
03

Cable pull and termination

Week 2 Day 5 → Week 3 Day 3 · 6 electricians

Pull cables per schedule LNL-CABLE-04. SWA armoured for distribution; LSF for branch circuits. Mark every cable end at both terminations. Test continuity, insulation resistance and earth-loop impedance to BS 7671 18th Edition before energisation.

Cable schedule met Terminations marked BS 7671 tests pass Megger printout logged
04

Mechanical pipework — chilled and condensate

Week 3 Day 3 → Week 4 Day 1 · 3 fitters

Install copper chilled-water pipework (compression jointed to BS EN 1057) and condensate drainage to FCU and AHU positions. Pressure-test to 1.5× working pressure for 60 minutes; condensate run-fall checked at 1:100 minimum. No hot works on this pipe run — all joints mechanical.

Pressure test pass Run-fall verified No hot-work permits raised
05

Ceiling grid installation

Week 4 Day 2 → Week 5 Day 3 · 4 ceilings ops

Install exposed-grid ceiling system (Armstrong Prelude 24mm or equivalent). Grid level checked with laser at 4 corners + 2 mid-points per zone. Service penetrations cut to within 5mm tolerance; edge trim seated on perimeter angle. Tiles loose-laid for snagging access.

Grid level ±2mm Penetrations within 5mm Tiles loose-laid
06

Commissioning and pre-handover snagging

Week 5 Day 4 → Week 6 Day 3 · M&E commissioning team

Commissioning per BSRIA BG 49/2015. Air-tightness pressure test on FCU connections; chilled-water flush + flow balance per design schedule LNL-MECH-FLOW. Snag list raised by client rep; 48-hour close-out target on Cat-A snags.

BSRIA BG 49 Flush + flow done Snag list closed
07

Handover and demobilisation

Week 6 Days 4–5 · Site supervisor + 1 labourer

Final clean of all worked areas. O&M manuals to client (printed + digital). As-built drawings updated and re-issued. Remove welfare unit, restore car-park barriers. Practical Completion certificate signed by client representative.

O&M issued As-builts re-issued Welfare cleared PC signed
03 RESOURCES

Personnel · plant · materials.

Resource ceiling for this Method Statement. Daily allocation tracked by site supervisor against the weekly programme. Substitutions require RAMS revision (raise via Job Intake form, Output 01).

PERSONNEL
  • 1 × Site supervisor (NEBOSH)
  • 6 × Electricians (JIB Gold)
  • 3 × M&E fitters
  • 4 × Ceilings operatives
  • 2 × General labourers
PLANT
  • 2 × Mobile elevated work platforms (4m)
  • 1 × Cable pulling winch (110V)
  • 1 × Hydrostatic test pump
  • 1 × Megger MFT 1741+
  • 2 × Laser levels (rotating)
MATERIALS
  • Cable tray · perforated steel · 300mm wide
  • SWA & LSF cable per schedule LNL-CABLE-04
  • Copper pipework · 22 / 35 / 42mm
  • Ceiling grid · Prelude 24mm exposed
  • Mineral-fibre tiles · 600 × 600mm