RAMS Factory
RAMS Factory™Pack 03 / 06 · Client deliverable
Method statement · commercial Cat-A fit-out

Every step sequenced, and gated on inspection

The works above Level 3 on an 18,400 square foot Cat-A fit-out: high-level containment, cable, pipework, ceiling grid, commissioning and handover, in seven inspection-gated steps over six weeks. Each operation is signed off before the next begins, and the method statement is issued only alongside the signed risk assessment.

Client
Linnet Lane Cat-A Fit-Out
Site
Linnet Lane, Manchester · Levels 4 to 6
Work type
Commercial Cat-A fit-out, M&E first fix and ceiling grid
Reference
BAI-MSS-LNL-MCR-001
Sector
Commercial fit-out
Status
For approval

Illustrative example: fictional project and parties.

7Inspection-gated steps
3Floors, Levels 4 to 6
6Week programme to handover
2Hard hold points
BuiltAI Intelligence Ltd · built-ai.ioBAI-MSS-LNL-MCR-001 · Rev 02
01Scope

Cat-A fit-out, Levels 4 to 6

18,400 square feet over three floors. Mechanical risers terminate at Level 3, so this method statement covers the works above that point: high-level containment, cable pull and termination, chilled-water and condensate pipework, ceiling grid, commissioning and handover. The programme runs six weeks, with mobilisation in week 1, M&E first fix across weeks 2 to 4, ceiling grid in weeks 4 to 5, and snagging in week 6.

How the sequence holds

The site supervisor holds the inspection register. Each operation is signed off before the next begins, and BuiltAI cross-references the register weekly against the QA checklist. Any substitution of resource or method is raised as a RAMS revision through the job intake, not decided on site.

02Sequence

Seven steps, inspection-gated

Each step lists its acceptance criteria. The hold before cable pull and the pressure test on the pipework are the two points where work stops until an inspection is signed.

StepMethod and acceptance criteria
01 Mobilisation and welfare set-upWelfare in place, 110V supply tested, exclusion zones at lift lobbies, induction logged
02 High-level cable tray containmentPerforated tray to layout, hangers at 1.5m centres, bonding tested, held for inspection before cable pull
03 Cable pull and terminationArmoured for distribution, LSF for branch circuits, continuity, insulation and earth-loop tested to BS 7671 18th Edition
04 Chilled-water and condensate pipeworkCompression jointed to BS EN 1057, pressure test at 1.5 times working pressure for 60 minutes, condensate fall verified at 1 in 100
05 Ceiling grid installationExposed grid, level checked by laser to plus or minus 2mm, penetrations within 5mm, tiles loose-laid for snagging
06 Commissioning and pre-handover snaggingCommissioning to BSRIA BG 49, chilled-water flush and flow balance, client snag list raised
07 Handover and demobilisationFinal clean, O&M manuals issued, as-builts re-issued, welfare cleared, practical completion signed
03Resources

Personnel, plant and materials

The resource ceiling for this method statement. Daily allocation is tracked by the site supervisor against the weekly programme.

Personnel

1 supervisor (NEBOSH), 6 electricians (JIB Gold), 3 M&E fitters, 4 ceilings operatives, 2 general labourers.

Plant

2 mobile elevated work platforms (4m), cable-pulling winch (110V), hydrostatic test pump, multifunction tester, 2 rotating laser levels.

Materials

Perforated steel tray, armoured and LSF cable per schedule, copper pipework 22, 35 and 42mm, exposed ceiling grid, mineral-fibre tiles.

Gated on the risk assessment

This method statement is issued only alongside the signed risk assessment for the site. Work does not proceed on the strength of the method statement alone.

04Inspection

Inspection and hold points

Each operation carries an inspection and an acceptance criterion, signed by the site supervisor before the next begins. Two are hard hold points where work stops until the inspection is signed.

OperationInspection and acceptancePoint
ContainmentTray to layout, hangers at 1.5m centres, bonding continuity provenHold before cable pull
Cable installationContinuity, insulation and earth-loop tested to BS 7671 18th EditionSign before energise
PipeworkPressure test at 1.5 times working pressure held for 60 minutesHold, witnessed
CondensateFall verified at 1 in 100 along each runSign before close-in
Ceiling gridLevel checked by laser to plus or minus 2mm, penetrations within 5mmSign before tiles
CommissioningChilled-water flush and flow balance to BSRIA BG 49Client witness
HandoverO&M manuals, as-builts and test records issued and acceptedPractical completion
Operations inspection-gated7 of 7
Hard hold points2 of 7
Register cross-checked weeklyAgainst QA
One register, signed as it goes

The site supervisor holds the inspection register and signs each operation off before the next begins. BuiltAI cross-references the register weekly against the QA checklist, and any failed inspection stops that operation until it is corrected and re-signed.

Reference BAI-MSS-LNL-MCR-001Standards BS 7671 · BS EN 1057 · BSRIA BG 49Revision 02