RAMS Factory™Pack 03 / 06 · Client deliverable
Permits and isolations · cleanroom HVAC shutdown

No work until every lock is proven

Twelve permits to be in place and ten isolations to be applied and tagged for the cleanroom HVAC shutdown. No work proceeds until every permit is active and every isolation is locked off and proven dead. Three permits remain pending, and each one gates the start of the task it covers.

Client
Apex Pharma Cleanroom
Site
Class C suite, AHU-03
Work type
Planned HVAC service, filter and coil
Reference
BAI-PMT-APX-CLR-001
Sector
Pharmaceutical
Status
3 permits pending

Illustrative example: fictional project and parties.

12Permits required for the shutdown
8Active and authorised
3Pending and gating tasks
10Isolations to apply and prove
BuiltAI Intelligence Ltd · built-ai.ioBAI-PMT-APX-CLR-001 · Rev 01
01Overview

Permit-driven, mapped to tasks

The shutdown runs Sunday 17 May, 02:00 to 12:00, a ten-hour window on a Class C cleanroom air-handling unit. Each permit is mapped to specific tasks and its validity aligns with the outage. Of the twelve, eight are active and authorised, three remain pending, and one is not required because the works stay in the technical area with the cleanroom envelope intact. Five permits are marked critical to safety.

The pending set gates the start

The shutdown cannot commence until three permits are signed off: the hot works permit, which cannot proceed until the fire-system isolation is confirmed, the lifting operations permit for the filter delivery, and the fire-system isolation itself. All three are to be cleared by Friday 15 May; if any remains pending at the cut-off, there is no mobilisation.

02Permit register

The permit register

A sample of the register with each permit's coverage and current status. The full register carries validity windows, signatories, conditions and witnesses.

RefPermitStatus
P01Cleanroom entry, Class C gowning and particle countActive
P02Lockout-tagout, HVAC fans and invertersActive
P03Hot works, localised brazing on chilled-water tailsPending
P04Confined space entry, within the AHU plenumActive
P06Lifting operations, HEPA filter set to roofPending
P07Fire-system isolation, smoke detection in plant roomPending
P09Process isolation, chilled-water loop for coil cleaningActive
P12Aseptic-area override, cleanroom envelope intactNot required
03Isolations

Ten isolations, applied and proven

Every isolation is logged, tagged, applied by a named competent person and removed by the same, in reverse sequence, only when the shutdown signs off. Times shown are the applied time on the shutdown morning.

IDService isolatedApplied byTime
L01 to L03AHU-03 supply, return and exhaust fan motorsBuiltAI Authorised Person02:35
L04Modulating dampers, control supplyBuiltAI Authorised Person02:38
L05 to L06Chilled-water loop and coil tailsApex Authorised Person02:00
L07 to L08Steam supply to humidifier and condensate returnApex Authorised Person02:15
L09Smoke detection, plant-room zoneApex Fire OfficerPending
L10Building management system, AHU-03 in maintenanceApex BMS engineer02:40
04Handback

Removal, reinstatement and handback

Isolations are removed in reverse order by the authorised person who applied them, and only after the shutdown signs off. Handback is staged so the cleanroom returns to classification before the area reopens.

StageActionAuthorised by
Pre-handback checksPlenum sealed, tools accounted for, confined space clearedSite supervisor
Reverse isolation removalL10 back to L01, each proven dead-safe and logged on removalAuthorised persons
Fan and damper restartStaged restart, control supply restored, dampers provenBuiltAI Authorised Person
Fire-system reinstatementSmoke detection returned to service, plant-room zone testedApex Fire Officer
Cleanroom recoveryParticle count returned to Class C before the area reopensApex QA
Permit close-outEvery permit signed off and filed, area formally handed backShutdown manager
Permits authorised8 of 12
Critical to safety5 of 12
Pending to clear by cut-off3 of 12
The cut-off is Friday 15 May

The three pending permits, hot works, lifting and fire-system isolation, are to be signed off by Friday 15 May. If any remains open at the cut-off there is no mobilisation, and the ten-hour window is stood down rather than started against an incomplete permit set.

Reference BAI-PMT-APX-CLR-001Outage Sun 17 May, 02:00 to 12:00Revision 01