Task sequence · structural steel erection

The spine the whole pack is built on

The work broken into a defensible step-by-step sequence with predecessors, durations, hold points and the critical path made explicit. The method statement is built around this. Hazards are mapped against it. Compliance is structured against it. Twenty-one tasks across six phases, four hold points and an eighteen-day critical path.

Client
Saxon Wharf Steelwork
Site
Saxon Wharf Phase 2, Bristol · BS1 6QH
Work type
Structural steel, 5-storey primary frame
Reference
BAI-TSB-SXW-STL-001
Sector
Industrial
Status
For approval

Illustrative example: fictional project and parties.

21Tasks in the sequence
6Phases, pre-erection to finishing
4Mandatory hold points
18Working days, stated critical path
BuiltAI Intelligence Ltd · built-ai.ioBAI-TSB-SXW-STL-001 · Rev 01
01Phases

Six phases, at a glance

The programme runs three weeks, Monday 18 May to Friday 5 June 2026, from pre-erection verification through to handover of the frame to the following trade.

PhaseCoverageDuration
P1 Pre-erectionSetup, survey, bolt check, lift plan (T01 to T04)2 d
P2 Frame Level 1Baseplate to L1 secondary (T05 to T08)4 d
P3 Frame Level 2L2 columns to bracings (T09 to T12)3.5 d
P4 Frame Level 3L3 columns and beams (T13 to T15)3 d
P5 Roof levelRidge, secondary and purlins (T16 to T17)1.5 d
P6 FinishingTorque, fire protection, sign-off (T18 to T21)4.25 d

The six displayed phase durations total 18.25 days. The example does not state an overlap, calendar or rounding basis reconciling this sum with the 18-day critical-path figure.

02Sequence

The detailed sequence

A sample of the task table showing predecessors, durations and type. Six tasks sit on the critical path; four are hold points that stop work until inspected.

IDTaskPredDurType
T02Survey and set-out verificationT010.5 dHold point
T03Holding-down bolts level checkT020.5 dHold point
T06Column erection Level 1T051.5 dCritical path
T07Primary beam connection L1T061.0 dCritical path
T13Column erection Level 3T101.0 dCritical path
T18Final torque-up and weld inspectionT171.5 dHold point
T20Final dimensional surveyT190.5 dHold point
03Governance

How the sequence governs the pack

This task sequence is the spine of the RAMS pack. The hazard-risk-control matrix maps hazards to each task ID. The PPE and plant schedule maps requirements per task. The permits and isolations checklist cross-references permit needs against the hold points. If the sequence changes, the downstream outputs change with it, so the workflow stays governed end to end.

Critical path and gates

The critical path runs through the level-by-level column and primary-beam erection. The four hold points, survey set-out, holding-down bolts, final torque with weld inspection, and the final dimensional survey, each stop work until the inspection is signed.

Reference BAI-TSB-SXW-STL-001Programme Mon 18 May to Fri 5 Jun 2026Revision 01